The energy transition in Greece is progressing rapidly, with ambitious targets set for 2030 in the National Energy and Climate Plan (NECP), which is currently under public consultation. The country aims to increase the share of renewable energy sources (RES) in its final energy consumption to 45% and achieve an 80% share of RES in electricity generation by 2030. This goal will be achieved by further investing in solar, wind (including offshore wind parks), and hydropower projects, with over 12 GW of additional capacity planned by 2030. Greece is heavily promoting standalone battery storage systems (BESS) through state aid mechanisms to address grid congestion issues and the intermittency of RES production, aiming to support the deployment of green hydrogen for sectors like heavy transport, shipping, and industry. New natural gas pipelines are already hydrogen-ready. Lastly, lignite power plants are currently in a phase-out process so as to be completely decommissioned by 2028.
Energy efficiency is a key objective according to the NECP, while the share of renewables in heating and cooling is targeted to reach 47%. The participation of RES in the transportation sector is also expected to increase to 32% (from 19%). In addition, there is a strong focus on the shift toward electric vehicles and infrastructure in order to achieve the goal of 100% electric mobility for passenger cars by 2030.
In Greece, the most dominant renewable energy technologies are wind and solar power, which together dominate the country’s renewable energy landscape. By 2022, wind energy accounted for 43.9% of the installed capacity in the interconnected system, while solar PV grew to 51.3%. This marks a significant increase from previous years, driven by the rapid expansion of solar installations and the country’s favourable climate conditions.
Other renewable sources play smaller but notable roles, providing diversity to the country’s renewable energy mix. Small hydropower contributed 679 GWh in 2021, while biogas and biomass facilities produced 448 GWh. Combined heat and power (CHP) units also produced 215 GWh in 2021, based on data published by the Operator of RES and Guarantees of Origin (DAPEEP).
Greece is also exploring emerging technologies like green hydrogen, which is expected to become a significant part of the energy mix in the coming years.
Over the past 12 months, investment in RES has continued to rise, driven by the ambitious goals set by the NECP. Greece’s appeal for renewable energy investments has seen a significant boost, reaching a historic high by ranking 19th in the Renewable Energy Country Attractiveness Index (RECAI). More specifically:
Under the applicable framework, there are numerous administrative regulations governing the development, construction, commissioning and operation of power plants with the use of renewable energy sources (eg, wind, photovoltaic, hydro, biomass, etc). What follows are the major acts of the legal framework which governs the licensing and operation of RES projects.
A number of secondary legislative acts have been issued by virtue of the above-mentioned legislation in order to regulate all aspects relating to the licensing of power plants, as well as the technical and commercial details relating to the structure and operation of the domestic electricity market.
As far as imminent new legislation is concerned, a new draft bill has been put into public consultation regarding the establishment of new provisions which concern:
The agencies, government bodies and institutions which regulate the Greek RES market are the following.
Under Greek law, renewable energy is defined as energy derived from non-fossil, renewable sources, namely:
The key licences applicable to all types of RES projects are listed below.
According to the applicable law, any natural or legal person, through their participation in management, directly or indirectly or as a shareholder, partner, or member of a legal entity with any percentage of ownership, is not allowed to conclude an operating aid agreement without participating in RES Tenders, provided that the natural or legal person owns two projects of the same technology with an operating agreement without participating in RES Tenders, and these RES technologies are eligible to participate in RES Tenders.
As regards restrictions on transfer of RES assets, in principle, the applicable legislation allows the transfer of RES projects, subject to certain limitations governing the transfer of small-scale/exempted projects, which cannot be transferred prior to the execution of the Grid Connection Agreement.
In principle, the applicable legislation does not restrict the access to foreign investment in the renewable energy market, provided that the interested party:
In addition, certain limitations apply for the purchase of real estate by foreigners in border or non-border areas of Greece. In particular, any transaction concerning the establishment of any real or contractual right on real estate located in border areas, by individuals or legal entities with nationality or registered office outside the member states of the EU, is prohibited. This prohibition also applies to the transfer of shares or the change in the partners of companies of any form that own real estate in these areas.
Even though the law imposes restrictions, an exemption from these restrictions is possible through a special procedure, provided that the applicant specifies the intended use of the property, and the application is approved by the relevant authorities.
Further to the streamlining of the licensing procedures for RES projects by virtue of the New RES Law, Laws No 4685/2020 and 4951/2022 introduced additional measures to further expedite and simplify the licensing workstreams for RES projects, the latter being the first initiative of the state in its recent endeavour to simplify the applicable licensing process and ensure that the ambitious RES penetration targets are met. Phase B Licensing Framework also introduced the possibility of integrating storage solutions to RES technologies.
Regarding the licences required by the framework, please refer to 2.3 Regulated Activities.
In order to achieve greater cost-effectiveness and to incentivise better market integration of RES production, the state replaced the previous guaranteed feed-in-tariff (FiT) scheme, which provided electricity producers from RES a guaranteed sale price for the produced electricity, with a sliding Feed-in Premium (FiP) scheme, in compliance with the recent European directives and principles relating to state aid in the energy sector for the period 2014 to 2020 and, consequently, 2021 to 2025 (EEAG). The full implementation of the Target Model will entail operating costs to RES producers such as clearance and balancing and non-compliance charges, hence the state endeavours to promote green PPAs for commercial and industrial participants.
Key market players:
With regards to the competent regulatory authorities, please refer to 2.2 Regulating Authorities.
The currently applicable legal framework in Greece provides for electricity production from biogas power plants. The applicable technology is based on the anaerobic decomposition of organic matter and the production of biogas, which is then utilised for the generation of electricity. The licensing process and the interconnection of the biogas projects with the Grid (Network or System) is governed by the legal and regulatory framework for RES projects.
Currently, approximately 80 biogas power plants are in the operation phase with an aggregate capacity of 120 MWe and biogas fuel production of 1,4 TWh/year. However, there is no production of biogas and/or biomethane in Greece yet.
There has been no legal and regulatory framework governing the production, trade and supply of biogas and biomethane in Greece. Currently, biogas production is exclusively utilised for electricity generation. Approximately 38 biogas power plants in the operation phase are located in close proximity to the natural gas pipelines of the National Natural Gas Transmission System (NNGTS), meaning that following the introduction of the relevant framework, the conversion to power plants producing biomethane will be feasible, with a production of approximately 0,9 TWh/year.
The Law on Geothermal Energy (4602/2019) governs the terms and conditions for granting exploration, production and/or management licences of geothermal potential. Furthermore, the applicable framework provides a coherent terminology and determines the temperature cutoffs by virtue of which the classification of geothermal fields is performed.
The main geothermal fields are located in the following areas:
The main provisions of the legal framework are the following:
The secondary legislation has been regulated by virtue of:
No geothermal projects are currently in the operation phase. A geothermal field located on Milos island is currently in the exploration phase by PPCR and is expected to host a 5MW RES station by late 2025, provided that the relevant preliminary studies are confirmed.
Greece has set an ambitious target for 2030 and beyond, within the framework of the new National Energy and Climate Plan (NECP), while many Greek and foreign companies are considering their options in relation to potential investment opportunities. The NECP aims at the installation of 1.7 GW of electrolysers by 2030, which translates to 135,000 tons of green hydrogen production. The production of green hydrogen will be utilised for the production of biofuels, mainly synthetic kerosene and synthetic methanol.
According to the updated version of the NECP, which was published by the MEE in August 2024, and will be soon released to public consultation phase, the goal for the production of green hydrogen is set to 1 TWh annually by 2030. The above production model has been structured on the assumption that the production of 1 TWh of green hydrogen requires 1,5 TWh of RES generation.
On the infrastructure front, the MEE and the National Natural Gas System Operator (DESFA) state that the existing gas infrastructure will undergo only minor upgrades to become “hydrogen-ready”, while all new pipelines constructed by DESFA are capable of supporting hydrogen transmission. Furthermore, major international pipelines, such as the Trans Adriatic Pipeline (TAP) and the Greece-Bulgaria Interconnector (IGB) are already capable of handling hydrogen quantities.
A comprehensive regulatory roadmap for the licensing of green hydrogen projects as well as of a set of policies for the financial support of these projects is yet to be established, even though the ongoing normative debate on the pertinent framework between government officials, regulators, grid operators and market players is very dynamic. Greece is following the green hydrogen trend, however without any tangible legislative proposals so far for regulating and promoting the industry.
With respect to biofuels, initiatives and development of the biofuel market began in Greece in 2005 with biodiesel being the only biofuel produced in the country. Greece has also ratified relevant EU legislation (Biofuel Directive, recast by virtue of RED II Directive) into national law, requiring the issuance of a licence in order to perform certain activities, such as biofuel distribution. Biofuel distributors must first obtain a biofuel production licence or execute a biofuel purchase agreement.
The currently applicable framework defines net-billing, virtual net-billing, net-metering and virtual net-metering solutions as mechanisms where the energy generated is offset with the energy consumed.
Net-metering is an electricity billing mechanism that allows consumers to offset the cost of electricity consumption with the electricity generated by a power plant. Self-consumers, both on an individual basis and through RES Aggregation, are eligible to:
With regards to individual or collective self-consumers developing net-metering solutions, the maximum capacity is set to:
The RES projects can be developed and be installed by individuals or legal entities of public or private law which possess ownership or lawful utilisation rights over the premises in which the generating plant is installed, including but not limited to ownership, leasing, or other forms of concession, having obtained written consent from the property owner.
The right to proceed with the development of virtual net-metering solutions is extended to legal entities of public or private law that pursue objectives of public interest or other purposes that serve the general or local welfare. Holders of virtual net-metering solutions must either possess ownership or lawful utilisation rights over the premises where the generating station is installed, including but not limited to ownership, leasing, or other forms of authorised concession, and have obtained written consent from the property owner.
Regarding net-billing solutions, the holder of the power plant may have ownership rights, or the power plant may be held by a third-party or managed by a third-party.
The framework for self-consumption units installed on rooftops provides for the award of subsidies to developers of self-consumption projects under the Ministerial Decision YPEN/DAPEEK/36988/970. It provides that RES projects are eligible to receive investment support, provided that the holder of same has secured ownership rights or lawful use of the installation site. Rooftop self-consumption units can be installed in shared spaces, provided that a consent is granted by the assembly of the building’s owners in accordance with the apartment building regulation.
Based on the currently applicable legal framework and infrastructure, electricity generated from RES is exclusively injected into the Distribution Network or the System. With regards to grid connection of RES projects, the rule of thumb is that:
Key parties:
The ownership, and the transmission and distribution activities of the electricity sector, can only be performed with the granting of a relevant licence and certification process, as per the Energy Law.
Battery Storage
Currently in Greece, approximately 699 MW of pumped hydro storage is in the operation phase. With regards to BESS, the framework reflects the licensing process for BESS, including the issuance of:
By virtue of Law 4920/2022, the legal basis has been set for the award of investment grants and Operating Aid support to BESS, subject to the European Commission’s prior approval of such aid and for the adoption of any further implementing measures.
Greece notified to the European Commission in June 2022 its intention to establish a scheme in order to provide support for the development of BESS in Greece. Following the approval of the European Commission in September 2022 (Reference: State Aid SA.64736), the Ministerial Decision governing the BESS Tenders was finally issued in May 2023 and was amended in November 2023.
The selection of BESS will be made through three successive BESS Tenders, which will be conducted for an aggregate capacity of 1,000 MW projects. BESS selected will receive CTOs with priority and will be awarded operating aid and investment grant support.
The first (411,79 MW tendered) and second (299,77 MW tendered) BESS Tenders were conducted for BESS developed throughout the country, without location-specific requirements, while the third Tender will be conducted on the grounds of a location-specific criterion – ie, for BESS intended to be installed exclusively in the lignite phase-out zones (Regional Units of Kozani and Florina, Region of West Macedonia, as well as in the Municipality of Megalopolis, Region of Peloponnese).
BESS projects selected have received CTOs with priority, while the holders of the projects have undertaken the obligation to set their projects into commercial operation by 31 December 2025.
The Ministerial Decision governing the third Tender has been amended by virtue of a new Ministerial Decision dated 18 September 2024, providing for the specifics of the tender process for BESS projects of an aggregate capacity of 200 MW with a location specific area – ie, to be installed within the lignite phase-out areas of West Macedonia and Megalopolis in Peloponnese, which will be required to enter into commercial operation at the latest by 30 April 2026.
Extensive curtailments first appeared in 2023 in an effort to counter grid congestion and safeguard the stability and fail-safe operation of the System. Since spring 2024, curtailments are part of system management on low demand, where there have been situations of even complete curtailment of controlled RES production.
There is no rational way to completely avoid curtailments as the move is made to increasingly higher levels of RES penetration, and the existence of curtailments is part of the optimal long-term development of a renewables-based production system and should be taken into account in the planning and business plans of new investments.
In principle, there is a distinction between the following categories of curtailments, depending on the reasons for them.
The problem of insufficient electrical space was addressed by two main categories of curtailments:
It is also worth bearing in mind that in the spirit of EU Regulation 943/2019, RES curtailments in the context of re-dispatch are allowed, instead of infrastructure investments, if proven to be the best option and under strict regulatory control, while at the same time there must be grid development planning to remove congestion.
Based on the above, the state is called upon to take careful steps to formulate the framework for permanently and effectively addressing the above challenges, for which there are no obvious and established solutions. Successfully addressing issues such as curtailment imposition and the allocation of electricity space will largely affect the successful implementation of national targets regarding the development of the energy mix in the direction set out in the NECP.
With regards to alternative off-grid solutions that could mitigate the risk of imposition of curtailments on RES production, Wired Power Purchase Agreements (“Wired PPAs”) (also called physical on-site PPAs) could propose a solution, provided that the framework and the grid infrastructure allow the execution of such agreement.
This is in essence a behind-the-meter power purchase agreement. The generator/seller delivers energy directly to the off-taker via the consumer’s site network and as such there is no use of the distribution or transmission system. Note that this type of PPA has not been implemented in Greece yet and its implementation in the future is complex and as such highly remote.
The transportation and storage of biofuels from renewable sources is governed by Laws 3054/2002, 3423/2005 and 3769/2009.
The holder of a Biofuel Supply Licence (see 5.2 Gas) is required to develop infrastructure for the storage of biofuels and proceed with the licensing thereof – ie, the issuance of an Installation and Operation Licence.
As per the currently applicable framework, the transportation and distribution of biofuels is exclusively performed through road transportation.
Following the introduction of the new legal framework governing the production of biogas and biomethane, the currently applicable legal and regulatory framework governing the transportation and supply of biofuels is expected to be amended.
The currently applicable framework in Greece does not provide for the transportation and storage of heat from renewable sources yet. The same applies to the heat grid infrastructure, which has not been developed in Greece.
The introduction of the legal framework governing the production of hydrogen is currently pending, as is the secondary legislation governing the transportation and storage of hydrogen.
With regards to the “hydrogen-ready” infrastructure, please refer to 3.4 Hydrogen and Other Biofuels and Renewables.
DESFA (the National Natural Gas System Operator) has already established partnerships with various hydrogen projects, both on hydrogen production in the country and hydrogen infrastructure development by other EU TSOs, TAP, Bulgatransgaz, Snam and North Macedonia NER amongst the more relevant.
With regards to biofuels, which are not produced from RES, such as biodiesel, transportation and storage is governed by Laws 3054/2002 and 3423/2005. The Technical Regulation introduced in 2013 provides for the technical specifications for the distribution and storage of biodiesel.
Within the framework of the Target Model Law, the restructuring of the wholesale electricity market sets out the basic rules and principles for the transition from the mandatory pool model to the European Target Model.
As a result of the above legislative initiatives, the Electricity Markets consist of the following pillars.
The above-mentioned Day-Ahead, Intra-Day and Balancing Markets (the “Wholesale Electricity Markets”) entered into operation on 1 November 2020.
With regards to electricity trading and supply activities, the issuance of an Electricity Trading and/or Supply Licence is regulated by the Energy Law and the provisions of the Electricity Licensing Regulation dated 2012. The Energy Law and the Electricity Licensing Regulation differentiate the criteria for the issuance of the above licences, inter alia, on the basis of the type of licence requested and the legal form of the applicant entity.
Legal entities based within EU, member states of the EEA, members of the Energy Community and/or states that have executed bilateral treaties either with the EU or with Greece, are eligible to obtain an Electricity Trading and/or Supply Licence. Alternatively, an interested entity can establish a branch in Greece. An entity’s engagement in the activities of electricity supply or trading in another EU member state entails the application of more favourable market entry rules.
The currently applicable framework provides for the issuance of a Biofuels Supply Licence. The requirements for the issuance of the above licence are the following:
The competent licensing authority is the Directorate of Organisation and Supervision of the petroleum-related market of the Ministry of Environment and Energy.
The holder of the supply licence is required to develop infrastructure for the storage of biofuels and proceed with the licensing thereof – ie, the issuance of an Installation and Operation Licence.
The regulatory framework governing the trade and supply of heat from RES has not been developed in Greece yet.
The framework governing the market for the trade and supply of hydrogen has not been introduced yet. However, the recently issued joint Ministerial Decision No 118664/2023 of the Minister of Environment and Energy and the Minister of Transport and Infrastructure defines the terms and conditions as well as the technical specifications for the installation of hydrogen fuel stations for road transport. The Ministerial Decision governs the terms and conditions for the licensing process related to hydrogen fuel stations– ie, the issuance of the Installation Licence and the Operation Licence.
Regarding the trade and supply of biofuels not produced from RES, such as biodiesel, the requirements for the issuance of a Biofuel Supply and/or Trading Licence have been determined by virtue of Law 3054/2002.
The issuance, supervision, minimum content, revocation and trading of GOs (“Guarantees of Origin”) is regulated by the Phase B Licensing Framework. RAWEW has been authorised to issue the Regulation for GO Auctions, which has been issued by virtue of RAWEW’s Decision E-79/2024.
Through the GO auction process, conducted by DAPEEP, additional cash flows will be generated in favour of the RES Special Account, which is the funding source for RES producers that receive operational aid. The rationale of the provision is to ensure that the market value of the GOs of RES producers that receive operational aid are appropriately taken into account in the relevant support scheme, in accordance with the provisions of Directive (EU) 2018/2001.
Power Purchase Agreements (PPAs) have been a standard market practice in Greece since the end of 2021, mostly as a mechanism introduced to provide grid connection priority to RES producers which have elected to proceed with the execution of a PPA instead of the participation in RES Tenders, as a prerequisite for the execution of Operating Aid Agreements.
Based on track record, the following types of PPAs have been executed in Greece.
As a standard practice, the PPAs in Greece follow the pricing structure of pay-as-produced and have a minimum validity period of eight years, starting from the electrification/commercial operation of the RES project. Usually, for project financing purposes, PPAs in Greece have a term of ten to fifteen years. Overall, PPAs executed at EU level in 2023 correspond to 16,2 GW of RES projects; Greece ranked fifth as the PPAs executed in 2023 correspond to 0,95 GW of RES projects.
Overview of Onshore Project Development
In Greece, renewable energy production, particularly from wind and solar, has experienced significant growth over the past few years. Notably, in 2022, investments in PVs experienced growth of 72%. In 2022, total energy production from renewables grew to 19.22 TWh. Wind and solar dominated the energy mix, representing 55% and 36.9%, respectively, of total renewable capacity in 2022. RES projects that are currently in advanced development stages (ie, have received access to the grid) but were not energised until July 2024, amount to 14.4 GW of installed capacity. Integrating these projects in the energy system will require investment in grid infrastructure and deployment of utility scale BESS.
Key Stakeholders
The key agencies in the renewable energy market are listed below:
Key Legal Workstreams
The key legal workstreams related to the development of RES projects in Greece involve three separate legal workstreams that need to be followed and particularly in parallel to one another or as a prerequisite to one another, as follows.
In particular:
EPC and O&M Contracting Standards
EPCs
The dominant structure for EPC contracting in Greece follows a traditional EPC approach with full wrap, though contracts involving free-issued equipment are also prevalent. Liquidated damages (LDs) are widely used to cover performance issues, including delays in commissioning, reliability, performance, and capacity. Typically, LD caps range from 10 to 15% of the contract price, and these amounts are calculated based on the overall contract price.
The defect liability period in Greece usually extends for two years from the Provisional Acceptance Certificate. Additionally, latent defect liability under Greek law lasts for ten years beyond the initial defect liability period. Contracts that provide a full wrap are favoured, with mechanisms such as the assignment of equipment warranties, such as inverter warranties, offering additional protections. Security packages typically include bank guarantees such as advance payment guarantees, performance guarantees (usually 10% of the contract price), and warranty guarantees (5%).
O&M
O&M agreements for renewable energy projects in Greece typically extend beyond the warranty period for up to ten years, often aligning with the loan duration or overall project lifecycle. Availability guarantees are the standard in O&M agreements, ensuring the project maintains a certain level of uptime. Bonding requirements usually include performance bonds, which are typically set at 50% of the contract price and renewed annually throughout the duration of the O&M contract.
Greece is in the early stages of developing its offshore renewable energy market. In July 2022, the updated legal framework governing offshore PVs entered into force, while a few weeks later, the legal framework for offshore wind parks (OWPs) was established.
As offshore projects have not yet reached advanced development stages, the particularities of the relevant EPC, O&M and other contracts have not yet been formulated. However, it is anticipated that the principles mentioned in 6.1 Onshore Project Development will also apply hereto.
Offshore PVs
The Phase B Licensing Framework introduced a simplified process for the fast-track development of up to ten “pilot” offshore PVs (OPVs) – ie, PV systems of an installed capacity of 0.5–1 MW consisting of:
OPVs are issued with a single licence/certificate permitting their installation and operation, upon prior application of the interested investor. The licensing streamlines pertaining to conventional PVs with an installed capacity greater than 1 MW (see 6.1 Onshore Project Development) are not applicable to OPVs.
Furthermore, the seabed and the seashore where the OPV and relevant infrastructure will be situated is secured via concession acts issued by the competent Minister for a period of 22 years.
Offshore WPs
While the market is still maturing, significant upcoming projects are expected, particularly with the establishment of the Pilot OWP Projects area in the sea region near Evros and Samothraki, with a capacity of up to 600 MW. Greece’s offshore wind capacity is anticipated to expand significantly by 2030, with a focus on developing both fixed-bottom and floating OWP technologies.
Key Stakeholders
The key agencies involved in the development and licensing of OWPs are listed below:
Key Legal Workstreams
The regulatory framework includes several important steps:
Community Participation
The government is highly involved in regulating and overseeing the development of OWPs, with multiple ministries and agencies playing a role in approving the national development plan, environmental studies, and licensing. Community participation is built into the process through public consultations, especially during the environmental impact assessment phases. This ensures that local communities are informed and can participate in decision-making processes regarding the location and development of OWPs.
Permits and Licensing
Developers must follow a structured process to obtain the necessary permits:
Construction and Operational Phases
Construction of OWPs in Greece involves significant preparatory work, including environmental and technical studies. The operational phase is supported by government-provided operating aid agreements, usually lasting 20 years. Special provisions apply to the development of OWPs, such as grid connection responsibilities and compliance with environmental regulations. A 2% Special OWP Fee is imposed on OWP producers, contributing to national renewable energy funding.
Based on Greek market precedents and subject to commercial agreement with the financiers, project financing is usually effected by financial institutions through the following two financing structures.
Corporate Finance
Corporate finance loans are structured either in a standard loan form or through the issuance of bonds subscribed by a banking institution.
In principle, the bank does not require equity injection by the shareholder, however the capital structure of the borrower is examined a priori for the purposes of loan sizing.
Regarding recourse, in case the borrower is a revenue-generating entity, the banks rely on having recourse to such revenues and the borrower’s assets if a default occurs. In case the borrower is considered less creditworthy, banks seek to have recourse over the assets of the shareholders/group.
Depending on the borrower’s creditworthiness, collaterals include corporate guarantees by the parent company or an “asset rich” group company or pledges of certain company assets and/or receivables. Corporate financing is flexible in terms of timing to closing and does not entail heavy transaction documentation.
Project Finance
A project finance structure without recourse (ie, without corporate guarantee) will require robust contracts securing a minimum level of revenue.
Project finance loans are structured as bond loans, disbursed gradually in accordance with the progress of the project’s development.
The shareholder/sponsor of the borrower is required to inject part of the CAPEX (which may be lower than the bank’s participation). Banks expect a ratio (equity/debt) within the range of 40/60, 30/70, or 20/80 depending on project cash flow profile.
Own equity is injected either in the form of capital or in the form of shareholder loans.
Project financing does not entail recourse to the shareholder and the corporate group, nevertheless limited recourse may be anticipated during the development stage in case of funding shortfalls – ie, any additional funding that may be required in order to complete the project development must be covered by own funds of the sponsor.
Project finance documentation includes separate agreements (loan agreement, accounts agreement, security agreements etc), while it also requires due diligence on behalf of the bank.
The mechanism through which state aid is granted to eligible projects is the operating aid scheme, whereby state aid is awarded to successful bidders through RES Tenders. The current tendering cycle of 2021–2025 was approved by the EU in 2021. This scheme operates through competitive tendering processes, where various renewable energy technologies, such as wind and solar, participate in auctions to secure a reference tariff for the electricity that they inject into the grid, through FiP.
After the end of a RES project’s life cycle, or if for any reason it ceases to operate, the project owner must remove the installations it has placed and ensure the restoration of the installation site in accordance with the restoration plan that is drafted by the project owner. The usual timeline agreed in project agreements for decommissioning a RES power plant ranges between six and twelve months, depending on the technology and location of the project site. Greece has established a legal framework governing the recycling of PV modules since 2014, stipulating that PV panels are considered electrical equipment subject to recycling, a process managed by a certified management agency. Under this framework, a recycling fee is set by the pertinent management agency, which is incorporated in the sales invoices issued by importers of PV panels.
Policy initiatives are expected to be undertaken by the Greek government in the following months regarding the below: