Contributed By Peter & Kim
The principal laws governing the construction industry in (South) Korea include the following.
There are other laws that regulate different aspects of construction and engineering projects and the construction industry in general, such as regarding labour relations, health and safety, government procurement and environmental protection. The various laws governing the aforementioned aspects of construction and engineering projects are as follows.
Labour relations:
Health and safety:
Government procurement:
Environmental protection:
(For the text of these laws, please visit https://www.law.go.kr/LSW//main.html)
In domestic projects, it is common for parties to refer to standard contract forms promulgated by the government. For example, for contracts involving the Korean Central Government, Appendix 7 of the Enforcement Decree of the Act on Contracts to Which the State is a Party specifies the standard form contract to be used. Similarly, for contracts with local governments or their organs, the Act on Contracts to Which a Local Government is a Party applies.
Concerning overseas projects, there is no equivalent standard contract form imposed on or recommended to the parties. However, it is common that FIDIC standard forms (with deviations where necessary) are used for overseas projects. Currently, the FIDIC Red Book and Yellow Book are often referred to by Korean contractors. It is important to note that certain provisions within the general conditions of FIDIC contracts may not align with Korean law and, as a result, may need to be modified through a special provision in the particular conditions to ensure compliance with mandatory Korean legal requirements.
Currently, NEC3 or NEC4 is not often used by Korean contractors.
In Korea, employers in construction projects include a wide range of entities, such as public and private sector organisations or power companies (eg, KEPCO). In recent years, Korean conglomerates have become increasingly more involved in overseas construction projects as employers or as shareholders.
Generally, an employer in a construction contract has the right to receive the completed project as per the specifications. In return, they are obligated to make payment to the contractor according to the agreed terms. They are also commonly obligated through the contract to obtain necessary permits and approvals and to provide site access to the contractor.
The relationship between an employer, contractor, subcontractors and financiers may vary depending on the specific project. Typically:
In private construction projects, it is common for one construction company to be the contractor. Contractually, for public construction projects, a consortium or a joint venture made up of multiple construction companies often becomes the contractor.
The rights and obligations of a contractor under a construction contract typically include:
Subcontractors in a Korean construction project can be specialty contractors who work on specific parts of the project or general contractors who manage multiple parts of the project.
In general, a subcontractor has the right to receive payment for the work they have undertaken and to suspend work if payment is not received. Because of this statutory right to suspend work in the case of non-payment, there is less of a need to adopt and enact statutory adjudication for progress payment. A subcontractor is also typically obligated to:
Article 44(1) of the Labour Standards Act states that, in a project involving multiple layers of contracts, where a subcontractor fails to pay wages to its employees due to reasons attributable to the immediate upper tier contractor, the immediate upper tier contractor will be held jointly and severally liable for the unpaid wages. The provision also states that, where the immediate upper tier contractor’s failure is caused by the actions of its own upper tier contractor, the upper tier contractor will be jointly and severally liable. This provision aims to ensure that workers in a contractual chain receive timely and fair payment for their work. This provision is considered to be a mandatory provision.
Additionally, under Article 14(1) of the Fair Transactions in Subcontracting Act, the employer is required to pay “the subcontract consideration corresponding to the completed portion of manufacturing, repair, construction or service performance” where the main contractor has failed to make such payment.
In Korea, the financiers of construction projects typically include banks, investment firms, governmental institutions and funds, and other financial institutions.
The rights and obligations of a financier in a Korean construction project will depend on the terms of the financing agreement. Generally, a financier is entitled to receive repayment of the funds provided and is obligated to disburse funds in accordance with the terms of the financing agreement and the applicable laws and regulations.
Project financing is usually based on the employer’s budget and often involves long-term continuous contracts. In many cases, special purpose vehicles (SPVs) are used to limit liability and manage financing risks. This approach is common in both domestic and international projects.
The scope of works in a construction contract is typically determined by the contract documents, which may include the programme of requirements, specifications and drawings.
In some cases, the scope of works may also be determined by reference to industry standards, codes of practice, or other relevant regulations and requirements. Where there is a dispute regarding the scope of the contract between the parties, the contract may be invalidated, in its entirety or in part, under Article 22.5 of the Framework Act on the Construction Industry if one party unilaterally determines the scope of the contract and infringes upon the legitimate interests of the other party.
Variation Request by the Employer
If an employer has requested a variation, the scope and price would typically be determined by mutual agreement between the employer and the contractor, based on the provisions of the construction contract, or, in the absence of such provisions, on any relevant laws and regulations. In Korea, construction contracts usually contain clauses that specify the procedure for requesting and approving variations, as well as the conditions under which the contractor is entitled to additional compensation for such variations.
Variation Request by the Contractor
If a contractor has requested a variation, the scope and price would also be determined by mutual agreement between the employer and the contractor, based on the provisions of the construction contract, or, in the absence of such provisions, on any relevant laws and regulations. The increased contract price following a variation would typically be determined based on the actual cost incurred by the contractor for the various works plus a reasonable profit margin as agreed between the parties. However, it is also possible to set out in the contract that the increased contract price for a variation be “value-based” (not cost-based). In either case, the contractor’s entitlement to additional money for a variation may be subject to certain limitations or require the contractor to adhere to a procedure, such as providing timely notice to the employer and obtaining their approval before carrying out the variation works.
Time-Related Costs
Time-related costs are typically dealt with by including provisions in the construction contract that address the contractor’s entitlement to additional time and compensation for delays that are due to the employer. For delays where neither the contractor nor the employer is responsible, it is common that the contractor is granted permission to seek an extension of time only (but no additional costs).
It is common to have delay liquidated damages provisions in the event of a delay, which are calculated based on the number of delays after the agreed date for completion. According to the Korean Supreme Court, any liquidated damages for dates during which the employer is responsible for the delays may be deducted from the total liquidated damages amount. The construction contract may specify the procedure for seeking an extension of time and/or additional costs, as well as the conditions under which the contractor is entitled to such relief.
Unfair Contract Terms
If one party to the contract refuses to approve the request for modifying the contract amount due to design changes or changes in economic conditions, or refuses to approve the request for modifying the contract period due to changes in the scope of work, the terms of the contract may be considered significantly unfair to one of the parties. In such a case, according to Article 22.5 of the Framework Act on the Construction Industry, the contract or the relevant provision may be invalidated.
In general, the responsibilities regarding the design process are allocated between the employer, the designer, the contractor and other parties in accordance with the terms of the construction contract. The division of work can vary depending on the type of construction project and the parties involved. In general, there are three possible divisions of work.
It is important to note that the specific allocation of responsibilities may vary depending on the project and the contractual arrangements between the parties. For example, in some cases the designer may also be responsible for overseeing the construction process to ensure that it is carried out in accordance with the design, while in other cases the contractor may take on a greater role in the design process.
In general, the responsibilities regarding the design process are allocated between the employer, designer and contractor, although other parties may also be involved depending on the specific project. While the allocation of work can vary depending on the type of construction project and the parties involved, there are a few common ways that the division of work is structured.
In addition to these common structures, there may be variations and combinations of such structures depending on the specific project and parties involved. The allocation of work is usually specified in the construction contract, which outlines the roles and responsibilities of each party involved in the project.
The responsibility for the status of the construction site regarding pollution, underground obstacles, geotechnical conditions, archaeological finds and other related matters would depend on the terms agreed upon in the construction contract.
Under Korean law, there are several regulations that govern site conditions, including:
In construction contracts, the allocation of risk for site conditions is typically addressed in the site investigation clause, which specifies the scope and level of investigation required to assess site conditions. The allocation of risk can also be addressed in other clauses, such as the indemnification clause or force majeure clause.
In Korea, when undertaking a construction project, there are various permits to consider. These include building permits, construction permits, environmental permits and other licenses, which may differ based on the project’s nature and location. The responsibility for obtaining these permits rests either with the employer or the contractor, depending on the terms of the construction contract. It is common, however, to agree in a contract that the employer is responsible for obtaining various governmental permits.
According to the Korean Building Act, individuals undertaking the construction of a new building or significant repairs to an existing one must obtain permission from the relevant municipal authority. However, there is an exception for certain small-scale buildings, where submitting a notice to the authorities instead of obtaining permission is sufficient for proceeding with construction or repairs. Furthermore, once the construction is completed, the employer must apply for a separate “approval for use” from the municipal authority to legally occupy and utilise the building. Notably, the general provisions of the Building Act are complemented by municipal regulations that outline specific building codes in detail.
The responsibility for maintenance of the works is generally agreed upon between the parties in the construction contract. The contractor is usually responsible for maintaining the works until the end of the defects liability period, during which time the contractor is required to repair any defects that arise. After the defects liability period, the responsibility for maintenance may be transferred to the employer or a third-party maintenance contractor. However, the lapse of the defects liability period does not mean that the contractor is exempt from liability for damages for defective works that were discovered during the statutory limitations period.
Maintenance works in general entail actions taken to keep the works in good condition and repair. These may include cleaning, repair or replacement of equipment, systems or components, and general upkeep. The details of maintenance works are typically outlined in the construction contract; for instance, in provisions for ongoing maintenance and inspections during the defects liability period and beyond. The parties may also agree upon separate maintenance contracts to cover specific aspects of the works or ongoing maintenance needs.
While it is possible, it is not common in Korea for the employer to instruct the contractor to undertake functions such as operation, finance or transfer in the construction process.
It is, however, standard practice for an employer to instruct a third-party vendor to carry out operation works following completion of the building or plant.
The typical tests for completion of the works may include visual inspection, functional tests and performance tests, depending on the nature of the project.
The testing process starts with the contractor notifying the employer of the completion of the works. The employer then inspects the works to verify whether the works have been completed in accordance with the contract and the applicable laws and regulations. If the works meet the requirements, the employer issues a certificate of completion to the contractor.
After the issuance of the certificate of completion, the parties may conduct additional tests to ensure that the works are fully functional and meet the applicable standards. For example, in the case of a building project, the parties may conduct tests on the building’s fire safety system, its elevator operation, and the air conditioning system.
The party bearing responsibility for the testing process is typically agreed upon in the construction contract between the employer and the contractor. The contract should (and normally will) specify the types of tests required and the party responsible for conducting each test.
The process of completion and takeover of a construction project are closely related and often occur simultaneously.
The procedures and requirements for completion and takeover are typically set out in the construction contract and must be followed by the parties involved.
Contractor Liability Period
In Korea, the Civil Act provides for the contractor’s liability for defects in construction works. According to Articles 667 and 671 of the Civil Act, the employer can demand repair of the works by the contractor or seek payment of damages in lieu of a repair claim. This warranty claim can be exercised by the employer within five years or ten years from the completion of the construction works, depending on the type of materials used in the construction.
Remedies for Defects
If defects occur in the construction or its design, the employer has the option to either invoke the defects liability clauses in their contract or seek damages for non-compliance under the relevant contract law. The employer is entitled to demand specific performance from the contractor to repair defects in the ordered works, except when the relevant defect is minor and the cost of repair would be excessive.
However, the employer cannot use the statutory defect liability clauses to claim indirect or consequential damages from the contractor, even if the contractor could have foreseen these damages. To seek these kinds of damages, the employer has to claim damages in parallel under Article 390 of the Civil Act, demonstrating that:
Notification Period and Legal Consequences
Article 671(2) of the Civil Act provides that the employer must notify the contractor within one year from the day the destruction or the damage took place.
In Korea, the contract price for construction contracts is typically determined through various methods such as lump sum, unit price, cost plus and target cost. The contract price normally includes the cost of labour, materials, equipment and other expenses incurred by the contractor. In some cases, the contract price may also include a contingency amount for unforeseen circumstances.
In Korea, construction contracts typically include provisions to manage late or non-payment. These provisions may include clauses specifying the amount and timing of payments, interest rates for late payments, and remedies for non-payment, such as the right to suspend work or terminate the contract.
Advanced payments, delayed payments and interim payments may all be used in construction contracts in Korea.
Advanced payments may be made to cover upfront costs such as costs for materials or equipment, while delayed payments may be used to incentivise timely completion of the project. Interim payments are typically made at certain milestones or stages of the project and may be tied to the completion of specific tasks or deliverables. The specific payment structure and schedule will depend on the terms negotiated between the parties in the contract.
Invoicing in construction contracts in Korea is typically performed on a monthly basis or upon reaching certain milestones as agreed upon in the contract. Invoices often include detailed descriptions of the work performed, materials used and expenses incurred during the billing period.
In Korea, the planning process in construction contracts is typically agreed upon between the employer and the contractor. The employer usually provides the contractor with a scope of work and design documents, and the contractor is responsible for developing the construction schedule and method of execution. The contractor may also provide suggestions for alternative methods or materials to improve the project’s efficiency and cost-effectiveness.
To safeguard the planning process, milestones, milestone payments and certificates are commonly used in Korean construction contracts.
In the event of delays, the parties generally use the dispute resolution mechanism set out in the contract. Generally, the contractor must notify the employer of any delay event promptly, and the parties must work together to mitigate the delay and determine whether an extension of time is necessary. The contract will usually provide for specific procedures and timelines for notifying and assessing delays, which the parties must follow. Where the contractor causes a delay, it may be liable for damages (in particular, delay liquidated damages).
Time-related costs are typically dealt with in the contract through the inclusion of provisions on liquidated damages or extension of time. Liquidated damages are a predetermined amount of damages that the contractor will be liable to pay the employer in the event of a delay beyond the agreed completion date. Extension of time clauses, on the other hand, provide for an extension of the agreed completion date in the event of a delay caused by factors outside the contractor’s control. The contract will typically set out the procedures for applying for an extension of time or for assessing liquidated damages.
Concurrent delays are generally treated as an apportionment of responsibilities between the parties for the delay. The parties’ rights and obligations in relation to concurrent delays will depend on the specific terms of the contract. It is common for contracts to provide for an apportionment of responsibility for concurrent delays, with the contractor only being liable for the portion of the delay that is attributable to their actions or omissions. In the absence of such express provision, concurrent delays are often treated as a matter of apportioning causation.
In the event of delays caused by the contractor, the employer may seek various remedies to address the situation. The most common remedy is liquidated damages, which are pre-agreed monetary amounts set out in the contract for each day or week of delay.
Notably, under Article 398(2) of the Civil Act, the court has the authority to reduce the amount of the liquidated damages to a more reasonable and appropriate level if the amount is unreasonably excessive.
In addition to liquidated damages, the employer may also be entitled to other remedies, such as:
The typical process for requesting an extension of time involves submitting a written notice to the employer detailing the circumstances that have caused the delay and the expected duration of the delay. The notice should also include the proposed new completion date.
The grounds for granting an extension of time are generally set out in the construction contract and may include factors such as:
The specific procedures for requesting an extension of time and the grounds for granting it may vary depending on the terms of the contract and the specific circumstances of the project.
Force Majeure Under Korean Law
Force majeure is a recognised concept in Korea. However, although the term “force majeure” is used in various laws such as the Civil Act and the Commercial Act, no specific definition is provided. Therefore, to understand it and the circumstances under which it can be recognised, it is necessary to refer to the relevant case law. The Supreme Court has described force majeure as an event caused by factors beyond the debtor’s control and impossible to anticipate or prevent by ordinary means.
Additionally, since Korean law allows parties to freely determine the meaning and scope of a force majeure clause, the content of the agreed-upon clause is crucial in defining force majeure and its application.
Limitations on Force Majeure
As mentioned above, contracting parties have the freedom to define force majeure clauses, which can include limitations or exclude specific circumstances. This can be achieved by clearly and specifically stating the circumstances considered as force majeure in the contract. However, any such limitations or exclusions must be reasonable and not violate public policy or mandatory laws.
Contractual Consequences of Force Majeure
The legal and contractual consequences of force majeure under Korean law depend on the specific terms of the contract and the event’s circumstances. Generally, force majeure can:
The treatment of unforeseen circumstances in construction contracts is primarily determined by the parties’ agreement in the contract. It is common for construction contracts to include clauses related to unforeseen circumstances, such as force majeure events, changes in law or unforeseeable site conditions.
In addition to the parties’ contractual terms, the Civil Act also provides that, if the performance of an obligation becomes impossible due to an unforeseeable event beyond the control of the debtor, the obligation is extinguished.
Disruption is generally acknowledged as a legal and/or contractual ground for extension of time and/or compensation. Disruption can be caused by a variety of factors, such as delays in delivery of materials, changes in design, or weather conditions.
To establish disruption, the contractor must prove that the event was unforeseeable and beyond their control. The disruption must also be shown to have caused delay or to have imposed additional costs on the project.
Disruption may be measured or proven through various methods, such as schedule analysis, productivity analysis or cost analysis. The parties may need to engage experts or consultants to assess the impact of the disruption on the project schedule and costs.
Proving disruption can be a complex process, and it is important for contractors to keep detailed records and documentation throughout the project to support any claims for extension of time or compensation.
There are several liabilities that cannot be contractually excluded pursuant to mandatory law provisions. These include:
Wilful misconduct and gross negligence are recognised in Korea. Under Korean law, a “grossly negligent act” refers to an easily foreseeable and avoidable action that is conducted without exercising even a minimal level of care. Exclusion clauses are generally deemed unenforceable for liability arising out of a wilful misconduct or grossly negligent act.
The Serious Accidents Punishment Act, enacted in 2022, holds business owners, managing officers, public officials and corporations accountable for “severe accidents” resulting from a breach of safety and health obligations. It imposes criminal liability and introduces punitive damages of up to five times the amount of actual damages for cases involving wilful misconduct or gross negligence. The Act covers a range of incidents, including accidents at industrial sites and public disasters caused by product defects or inadequate management. It targets those who fail to ensure the safety of business operations or who neglect their supervisory duties.
Under Korean law, parties are generally free to agree to limit or exclude their liability through contractual provisions. Consequential loss exclusion clauses are commonly seen in Korean construction contracts.
However, the scope and extent of such limitations may be subject to limitations imposed by mandatory provisions of the law. For example, if one party to a contract unreasonably decreases or increases its liability for damages resulting from a breach of contract, thereby infringing upon the legitimate interests of the other party, the contract may be invalidated under Article 22.5 of the Framework Act on the Construction Industry.
Indemnities are generally used in Korean construction contracts to allocate risk between the contracting parties. While the subjects for which indemnities may be used can vary, the most common subjects for which one party could indemnify another include:
Guarantees commonly used to limit risk for parties in Korea include performance guarantees, payment guarantees and retention guarantees. Generally, the contractor provides performance guarantees, and the employer provides payment guarantees and retention guarantees.
The scope of guarantees used can vary depending on the specific provisions of the construction contract.
In Korea, construction contracts typically require the parties to take out various types of insurance policies to manage risks that may arise during the project. Insurance requirements are not only contractually agreed upon but also governed by mandatory or regulatory laws. For example, the Industrial Accident Compensation Insurance Act mandates that parties obtain industrial accident compensation insurance.
Some other insurances that parties will typically take out include:
The scope and coverage of these insurances may vary depending on the specific terms of the contract and the project’s nature.
In general, provisions addressing the consequences of insolvency of a party to a construction contract typically address two key aspects. First, they address the potential impact on the project itself. Second, they outline the rights and obligations of the other parties involved in the contract. Such provisions may include:
While Korean law does not explicitly declare “ipso facto termination clauses” as illegal or invalid, the Korean Supreme Court has ruled that ipso facto clauses are either invalid or unenforceable until the relevant insolvency proceedings are concluded. Article 119(1) of the Debtor Rehabilitation and Bankruptcy Act states that “[w]hen the debtor and the other party to a bilateral contract have yet to complete performance of the contract at the time rehabilitation procedures commence, any custodian may cancel or terminate such bilateral contract and request the debtor to meet his/her obligations and require the other party to fulfil his/her obligations…” Consequently, the custodian has the discretion to choose whether to terminate the contract or to enforce its performance. Thus, using an ipso facto clause to terminate the contract would undermine the intended purpose of this Article, which grants the custodian the statutory right to choose the appropriate course of action.
Sharing responsibility for certain risks is a common practice in the Korean construction industry. Risks that may be shared between the parties include, but are not limited to, risks related to unforeseen ground conditions, changes in law or regulation, labour disputes and force majeure events.
In Korea, construction contracts typically arrange for risk sharing through provisions such as the following:
Construction contracts typically include contractual provisions regarding personnel involved in the construction project. These provisions aim to ensure the appropriate staffing and management of personnel to facilitate the smooth execution of the project. While the specific provisions may vary depending on the nature and complexity of the project, some general contractual provisions regarding personnel in construction contracts may include:
Subcontracting is a common practice in the Korean construction industry and construction contracts typically include provisions regarding subcontracting. However, this is subject to certain limitations and conditions.
The Framework Act on the Construction Industry (FACI) establishes various prohibitions and regulations to ensure fair and balanced subcontracting practices.
In addition to the FACI, the Fair Transactions in Subcontracting Act aims to protect subcontractors, particularly smaller enterprises, from unfair contractual terms imposed by contractors. This Act addresses issues such as:
In Korea, intellectual property (IP) provisions are commonly included in construction contracts to govern the ownership, use and protection of IP rights within the project.
While contractual provisions regarding IP can vary depending on the project’s nature and the parties’ negotiation, some key elements are typically addressed.
Under Korean law, in the event of a breach of a construction contract, several remedies are available to the parties involved. Depending on the breach and the entitled party, available remedies include the following:
It is common practice to include clauses in contracts that limit or exclude the liability of a party, including liquidated damages provisions, indemnities and warranties. Korean contract law respects party autonomy, allowing parties to agree upon their own contractual terms as long as they are not contrary to public order and good morals.
The Korean Commercial Act permits parties to limit or exclude their liability for damages. This is, however, subject to certain restrictions, especially in cases where the damage is caused by gross negligence or intentional misconduct.
For construction contracts, parties can choose to deviate from the provisions of statutory defect liability under the Civil Act, which are not mandatory. They can agree to shorten or lengthen the stipulated defect liability period, or agree on a different start date for the statutory defect liability period.
However, while parties are generally free to contractually limit remedies, the Korean courts still exercise their discretion to review such clauses and may render them invalid if they are considered excessively unfair or if they violate considerations of fairness and balance of interests. However, in practice this discretion is exercised with utmost caution and only comes into play in exceptional cases.
Contractual sole remedy clauses are often observed in construction contracts to limit the available remedies for breach of contract. These clauses specify that the remedies explicitly mentioned in the contract are the sole remedies available to the parties, excluding other legal remedies that may be available under the law.
Enforcement of sole remedy clauses is generally governed by the terms of the contract. If the clause is clear and unambiguous, and the parties have freely and voluntarily agreed to its terms, the courts are likely to enforce it. However, it is important to note that the enforceability of contractual sole remedy clauses may be subject to limitations under Korean law. For instance, if the clause is found to be unconscionable, unfair or contrary to public policy, it may be deemed unenforceable.
It is worth noting that even where a sole remedy clause is enforceable, it may not completely limit the remedies available to a party in certain circumstances. For example, if a breach of contract is accompanied by a tort or a criminal act, the aggrieved party may still have other remedies available to them under Korean law.
In construction contracts, parties commonly include clauses that exclude or limit certain forms of damages. While the enforceability of such exclusions is subject to the specific circumstances, applicable laws, and the interpretation of the contract by the courts, there are certain types of damages that are typically excluded or limited in construction contracts.
Retention and suspension rights are not generally contractually excluded in Korea. In fact, these rights are recognised and widely used in the construction industry to protect the interests of both the employer and the contractor.
In particular, the delivery of works by a contractor is generally deemed to be an obligation that must be performed simultaneously with an employer’s obligation to make payment to the contractor (see Article 536 of the Civil Act). This means that if an employer expresses its intent not to pay the contractor, the contractor has a statutory right not to deliver the relevant works without being held in breach of the contract.
The termination provisions in a construction contract usually provide the grounds for termination, the process to be followed, and the consequences of termination. The consequences may include compensation, damages or penalties, depending on the circumstances of the termination.
Under Korean law, a construction contract can be terminated for various reasons, including but not limited to the following.
Termination for Change of Circumstances
Under Korean law, although there is no explicit provision regarding the doctrine of change of circumstances (the so-called rebus sic stantibus jurisprudence), the courts recognise the termination of a contract based on the principle of good faith stated in Article 2 of the Civil Act. This recognition serves as an exception to the principle of strict adherence to the contract. Termination may occur when “a significant change of circumstances has occurred that the parties could not have anticipated at the time of contract formation, and such change is not attributable to the party seeking termination. Enforcing the contract as written would result in a significant violation of the principle of good faith.” However, in practice, claims or defences based on the principle of change of circumstances are rarely accepted in Korea.
Termination of Contract After Completion
Similar to subclause 6.1 of the FIDIC Red, Yellow and Silver Books, Article 668 of the Civil Act grants the party who commissioned the work the right to terminate the contract if the final outcome of the work contains defects that render the contract’s purpose unachievable. However, it is important to note that this provision does not apply to buildings or structures on land. Consequently, once a building or structure has been completed, a construction contract for that specific project cannot be terminated or withdrawn, as specified in the proviso of this Article. This provision is regarded as a mandatory requirement under Korean law.
The legal system in Korea follows a three-tier trial structure, consisting of the District Courts of the first instance, followed by the Appellate Courts where factual issues may be reviewed, and finally, the Supreme Court, which exclusively addresses legal issues. The Supreme Court serves as the ultimate appellate authority for all cases, except those falling under the purview of the Constitutional Court.
While there is no dedicated court specifically designated for handling construction disputes, the District Courts and the Appellate Courts have specialised divisions dedicated to construction matters. The Seoul Central District Court and Seoul High Court are frequently chosen for construction cases.
In Korea, alternative dispute resolution methods are also frequently used and recognised as effective ways to achieve efficient and confidential resolutions in construction disputes.
#3805 Trade Tower
511 Yeongdong-daero, Gangnam-gu
Seoul 06164
South Korea
+82 2 538 2900
+82 2 538 2901
ContactSE@peterandkim.com www.peterandkim.com