Construction Law 2023

Last Updated June 08, 2023

Slovenia

Law and Practice

Author



Odvetniška družba Andrić is a professional team of six legal experts specialised in the fields of corporate, real estate, construction, insolvency and IT law. It remains the firm’s goal to provide clients with a wide range of legal services which commercial companies may require in order to ensure the unhindered performance of their business. The leading principles of the firm’s work are quick responsiveness and the ability to adapt to the needs of clients, as well as the continuous improvement of the quality of its services. The firm’s offices are located in the heart of Ljubljana in direct proximity to all the important judicial, administrative and other institutions, which enables it to pursue the interests of its clients quickly and effectively. The key areas of practice in relation to the construction sector are retail networks, real-estate project development, development financing, cross-border transactions and expropriation procedures.

The principal laws governing construction matters in the Republic of Slovenia are the Construction Act (GZ-1), the Code of Obligations (OZ) and the Spatial Management Act (ZUreP-3). In addition to these, construction contracts may also be governed by the Special Construction Usages specifying the rights and obligations of the contracting parties in more detail, however, these may be excluded from the contractual relationship should the parties choose to do so.

In the Republic of Slovenia, there are no provisions mandating the use of a standardised construction or construction-related contract, however, International Federation of Consulting Engineers (FIDIC)-approved provisions are most widely used and are even stipulated as necessary in some projects financed by EU cohesion funds. The most commonly used are the FIDIC:

  • red book, which represents the general terms and conditions of construction work;
  • yellow book, which is intended for the relationship between the contractor and the designer; and
  • silver book, which is used for turnkey construction works and is intended for contractors and clients.

Employers in Slovenia are mostly legal entities, most often in the form of a limited liability company. They must procure the permits necessary for the construction project, hand over the construction site and all the documentation necessary for the execution of the construction project to the contractor, and pay the agreed contractual amounts in accordance with the construction contract. They have the right to appoint and carry out construction supervision and must notify the contractor of the identity of the nominated supervisor. Employers typically have no direct relationship with subcontractors, however, they may, under certain conditions, be directly liable to subcontractors, should the contractor not fulfil its obligations towards such subcontractors. Employers are generally financiers of their own construction projects, however, should a construction project be financed by a third-party financier, such financier usually has no relationship with any party to the construction other than the employer (eg, loan agreement). 

The contractors are legal entities, mainly limited liability companies or independent entrepreneurs. They must keep a construction log and a construction ledger and carry out all the work necessary for the completion of the construction in accordance with the construction contract, applicable standards, laws and technical regulations, as well as perform other administrative/organisational tasks related to the safety and maintenance of the construction site. Furthermore, they are responsible for the work of the subcontractors whom they have entrusted with the execution of the work. 

Unless otherwise specified in the construction contract, the contractor does not have to carry out the work personally but may contract it out to subcontractors. Subcontractors, as well as contractors, are legal entities, usually limited liability companies and independent entrepreneurs. Subcontractors follow the instructions and orders of the contractor, who remains solely liable for the performance of the work in relation to the employer, as if the contractor performed the work itself. 

Financiers are most often banks or investment funds. In principle, the financier has no relationship with any party involved in the construction other than the employer, unless explicitly agreed otherwise with individual participants in the construction project. 

The scope of the works is covered by the technical documentation, which is prepared by the designer, usually at the employer’s request. The designer is a legal entity or a natural person who, as a participant in construction projects, prepares the technical documentation and meets the conditions under the law governing architecture and engineering. The technical documentation is a systematically arranged set of plans or technical descriptions, reports, calculations, drawings and other annexes, which determine the location, and the functional, design and technical characteristics of the construction. On the basis of such technical documentation, a building permit is issued, in accordance with which the contractor is required to carry out the construction work.

In the event that the employer requests a variation of the works, there are typically two options for determining the scope and price of variations. The first one is that the parties determine, already in the underlying construction contract, the price for any potential variations requested by the employer, or at least a mechanism for determining the price. In the second option, the parties are completely free to negotiate the price of variations. In such a case, the employer must request that the contractor send a quotation for additional works, including the price, the period of performance and the period of validity of the quotation. Once there is consensus between the parties, they conclude an addendum to the construction contract. Time-related costs are usually not charged as they are included in the construction service.

The technical documentation is prepared by the designer, usually on the basis of a design contract concluded with the employer. The designer’s task is to ensure, in accordance with the rules of their profession, that the documentation is prepared in such a way that it complies with statutory and professional requirements. The designer is responsible to the employer for the content and correctness of the technical documentation used to obtain a building permit.

After the building permit is obtained, the employer concludes a construction contract with the contractor who is responsible for carrying out the work in accordance with the building permit and technical documentation. In order to ensure the correct performance of the works, the employer must nominate a supervisor who is responsible, in relation to the employer, for supervision of the contractor’s work and is, usually, entitled to act and issue binding instructions on behalf of the employer.

The contractor is responsible for the layout, protection and appropriate marking of the construction site and must ensure the safety of the site, those working on it, passers-by, traffic, neighbouring properties and the surrounding area. 

During construction, the contractor must give access to the construction area to the designer who drew up the design documentation for the construction and to the designer of the design documentation for the execution of the works. The contractor is also required to give access to the investor, the supervisor and the occupational safety and health co-ordinator. Once construction is completed, the contractor is obligated to remove construction obstructions and any access restrictions and to clean and dispose of waste from the site area in an appropriate manner. Any special requirements regarding pollution, obstacles, geotechnical conditions and especially archaeological finds, are usually dealt with by the employer in the building permit obtainment phase, as the employer is also typically obliged to obtain consents and permits beforehand from authorities specialised in the above-mentioned areas. 

Construction usually requires notification of the start of construction and final building permit which is issued on the basis of the technical documentation provided and submitted by the designer on behalf of the employer. In the case of minor structures, the construction may be carried out without a permit. Once construction is completed, the employer is usually obliged to obtain fit-for-use permit, unless the construction was carried out without a building permit or the structure is merely temporary. The employer remains solely responsible for acquiring the building permit and all other permits in accordance with the Construction Act. The new Construction Act (GZ-1) establishes the possibility of obtaining a final building permit also in a summary determination procedure. Therefore, the competent administrative unit may issue a final building permit within 30 days based on complete documentation provided by the investor.

Slovenian legislation does not include any special provisions as to which party is responsible for the maintenance of the works during construction. The contractor is responsible for the maintenance of the entire construction site during the work itself, unless otherwise specified in the construction contract.

A supervisor appointed by the employer is also involved in the construction project. The supervisor’s task is to supervise the work of the contractor and the designer so as to ensure compliance with the requirements of the construction contract and the Construction Act, preventative action and the timely prevention of defects. 

The employer is usually the one entitled to give instructions to all participants in the construction project, except for insurance companies and banks, as these are usually contracting parties of the contractor only to the extent that the contractor has to provide bank guarantees, bills of exchange, proof of insurance coverage, etc, to the employer.

According to the Construction Act, the employer must obtain a fit-for-use permit upon completion of the construction. Such a permit is issued – under the condition that the works have been carried out in accordance with the building permit – by the competent administrative authority for construction matters following a technical inspection conducted by a specially appointed committee. The employer must apply for a fit-for-use no later than in the 30 days following notification by the contractor or supervisor that the construction is completed. If the employer fails to submit an application for fit-for-use within the prescribed time limit, it may be submitted by the contractor, the supervisor or another person who is the owner or holder of the rights in rem in the immovable property where the construction is located.

On completion of the works, the contractor is obliged to enter the date of completion in the construction log and invite the employer to accept and take over the works. The works are typically deemed to be completed upon the obtainment of the fit-for-use permit, however, the parties may agree otherwise. The takeover process typically includes the contracting parties signing a handover protocol, detailing the works taken over and any potential defects to be remedied by the contractor.

According to the general provisions of the Code of Obligations, the employer is obliged to inspect the work as soon as is reasonably practicable in the ordinary course of events and to inform the contractor immediately of any defects found. After inspection and acceptance of the work, the contractor is no longer liable for apparent defects which could and should have been noticed during normal inspection, unless the contractor was aware of them but failed to point them out to the employer. This does not apply to hidden defects not noticeable at first sight, as the contractor remains liable for these for two years after the acceptance of the works. Furthermore, the contractor is liable for any defects in the solidity of the construction, should these appear during the ten years following the acceptance of the works.

The general provisions concerning liability may be expanded upon by the parties and it is customary for the contractor to provide extra warranties and security instruments in the construction contract. 

The price is usually determined in accordance with one of two options, the first one being the turnkey clause and the second being the unit of measurement. The widely used turnkey clause means that the contractor is obliged to perform all the works necessary for the completion of the project, excluding additionally requested and unforeseeable works. The second option means that the price is determined per unit of measurement, therefore the final price depends on the materials used and hours of work.

Construction works are typically paid monthly by the employer in accordance with the progress made by the contractor, taking into account the timeliness and correctness of the works (reserved payments, contractual penalties, etc). Should the employer fail to fulfil its payment obligations, the contractor is usually entitled to suspend the works until payment or, ultimately, withdraw from the contract. 

The contractor typically invoices the works monthly in accordance with the progress made and, upon completion of the works, a final settlement is made by both contracting parties detailing the settled and potential outstanding amounts. 

The timetable is usually agreed upon by the employer and the contractor and enforced by the supervisor engaged by the employer to act on its behalf. Should the contractor not comply with the timetable, a contractual penalty for the delay is usually imposed on the contractor, and, in certain cases, the employer may also withdraw from the contract and cash in a bank guarantee issued by the contractor’s bank as an instrument securing the performance of the works.

In the event of any delays, the contractor usually informs the employer and asks for an extension. Should the employer deem the request to be well founded, it may grant the extension – typically, an annex to the underlying contract is concluded. Should the request not be well founded, the employer may make use of the remedies described under 5.1 Planning Programme. Time-related costs are not charged as they are included in the construction service.

See 5.1 Planning Programme

See 5.2 Delays

Force majeure means any unforeseen and unexpected event occurring independently of the will of the parties and which the parties could not have foreseen at the time of conclusion of the contract, which affects the performance of the contractual obligations. The contracting parties may specify in the contract precisely which events shall be considered force majeure. Extensions of time shall be granted on the basis of an annex to the basic contract.

Unforeseen circumstances are set out in the Special Construction Usages that apply to construction relationships, unless explicitly excluded by the parties in the construction contract. The contracting parties may, as already pointed out in 5.5 Force Majeure, additionally define what constitutes unforeseen circumstances. 

In the event of any disruptions, the contractor usually informs the employer and asks for an extension. Should the employer deem the request to be well founded, it may grant the extension. An annex to the underlying contract is concluded.

Under Slovenian law, a construction contract cannot exclude liability for damage caused intentionally or by gross negligence, or that affects the solidity of the construction.

See 6.1 Exclusion of Liability.

The parties to the contract have the option to exclude liability for slight negligence, but the court may invalidate such clauses if the clause results from an unequal relationship between the parties to the contract. The parties may agree on a maximum amount of damages if the amount so fixed is not manifestly disproportionate to the damage or if the law does not dictate otherwise in the particular case. The contractor may be free from liability in relation to the employer if it warned the employer that the requested work would not be appropriate, but the employer insisted on its performance despite the contractor’s warning.

The parties to the contract agree on the compensation at their own discretion. In most cases, the contractor is liable to the employer for delay and defective performance of the works. The contractor typically has insurance coverage for different types of damage caused by the contractor in connection with the performance of construction works.

Bank guarantees for the performance of work and for the rectification of defects within the warranty period are the most widely used instruments to ensure that the contractor fulfils its obligations under the construction contract. Additionally, the parties may agree that the employer reserve a portion of the amounts owed to the contractor each month as a security instrument similar to the bank guarantees. Lately, insurance policies for the performance of work and for the rectification of defects within the warranty period have started to feature more prominently in construction projects instead of bank guarantees.

The Slovenian Construction Act provides for compulsory construction insurance to cover damage arising in connection with the carrying out of the activity. The contractor would typically take out insurance covering the construction works, damage to the construction site and building, damage to health or assets of third persons, force majeure, etc. 

In the event of insolvency proceedings being opened against either the contractor or the employer, the construction contract usually provides for the possibility of withdrawal from the contract by the other party. 

Risk sharing is possible, but not common, as the employer typically transfers all possible construction-related risks to the contractor. 

Construction contracts usually contain a provision stipulating that the contractor remains solely responsible for the performance of the works in relation to the employer, regardless of whether such personnel or subcontractors actually performed the work on the contractor’s behalf.

The contractor typically has the option to subcontract the work, unless otherwise specified in the construction contract. It is common, however, for the contractor to reveal its subcontractors to the employer prior to the conclusion of the construction contract. 

All intellectual property is typically transferred to the employer to the extent necessary for the execution of the construction project.

In the event of a breach of the construction contract, the employer can claim restitution and damages against the offender or make use of security instruments issued in its favour. Ultimately, the employer may also withdraw from the contract.

The construction contract may limit the liability of the parties, however, under Slovenian law, the right to seek a remedy before a competent court cannot be waived.

See 9.2 Restricting Remedies.

To the extent permitted, direct and consequential damages are typically limited, however, liability for intent and gross negligence cannot be excluded. 

Retention and suspension rights stipulated under the general rules of obligations are typically not excluded, unless explicitly agreed otherwise by the parties.

The contracting authority may terminate the construction contract in certain cases. In the event of termination, the client must pay the contractor the appropriate part of the agreed price for the work done up to that time and fair compensation for the necessary costs.

Construction-related disputes are typically adjudicated by the specialised commercial law departments of the district courts. The location depends on the jurisdiction clause agreed upon by the parties. 

The parties may initiate a mediation procedure, but only where both parties agree to it. Mediation is very commonly used, both before and after the initiation of court proceedings. The parties may also agree that their dispute be settled in arbitration proceedings, however, they must agree on an appropriate arbitration clause at the conclusion of the construction contract or at a later time.

Odvetniška družba Andrić

Štefanova ulica 13A
1000 Ljubljana
Slovenia

+386 1 43 00 333

+386 1 43 00 320

info@andric.si www.andric.si
Author Business Card

Trends and Developments


Author



Odvetniška družba Andrić is a professional team of six legal experts specialised in the fields of corporate, real estate, construction and IT law. It remains the firm’s goal to provide clients with a wide range of attorney services, which commercial companies may need in order to ensure the unhindered performance of their business. The leading principles of the firm’s work are quick responsiveness and the ability to adapt to the needs of clients, as well as the continuous improvement of the quality of its services. The firm’s offices are located in the heart of Ljubljana in direct proximity to all the important judicial, administrative and other institutions, which enables it to pursue the interests of its clients quickly and effectively. The key areas of practice in relation to the construction sector are retail networks, development financing, cross-border transactions and expropriation procedures.

Contractual Price Increase in Construction Contracts Due to the Increase of Construction Material Prices

Recently, we have witnessed an unexpected increase in construction material prices. While this is a circumstance that is statutorily regulated with regard to a construction contract, price increases such as those experienced recently have seldom been so rapid. Thus, there is hardly any case law covering this issue. However, lately, numerous global crises have shaken the world, which has directly affected the increase in construction material and element prices. For example, the COVID-19 pandemic crippled the entire world between 2020 and 2022, causing a shut-down of numerous production plants engaged in the production of construction materials, which, in turn, caused a decrease in the supply of, and an increase in the demand for, energy-generating products and construction materials. After the COVID-19 restrictions were lifted, the production plants could not remedy the negative effects sufficiently and with appropriate expediency, causing the price of construction materials and elements to remain high. The situation has not been aided by the current war in Ukraine, which has caused a termination of trade relations with Russia, a major producer of raw materials, such as steel and aluminium. This has caused the withdrawal of those raw materials from the market, a massive increase in prices of energy-generating products and fuel, and – in some markets – a limitation of exports.

Determination of prices in a construction contract

The Slovene Code of Obligations sets forth three basic forms of price stipulation clauses: price per unit of measurement, lump-sum price and turnkey lump-sum fixed and unchangeable price.

The first method – price per unit of measurement – means that the contractor must foresee the quantities and prices of materials and the costs of construction equipment necessary to perform the works. The number of working hours of individual workers is usually not explicitly given, but is inferred in the aforementioned prices. If this method is used, the contractor is entitled to payment for all excess works, but does not have the right to payment for any works that have not been necessary or performed. The second method – lump-sum price – means that the price is determined in a total amount for the entire construction project covering all the works necessary for the construction in question. If this method is used, the contractor is not entitled to payment for any excess works, as the contractor should have foreseen the necessary quantity of materials, works and costs in its quotation. However, the contractor would still be entitled to payment for any unforeseeable works. The third method – the turnkey lump-sum clause with a fixed and unchangeable price – is the safest for the employer and is also most commonly used. This clause covers all unforeseen and excess works and also excludes the influence of any works not necessary or not performed.

All these clauses are affected differently by price increases or inflation affecting the construction material elements. Initially, it must be pointed out that the principle of monetary nominalism is established in Slovenia on the basis of Article 371 of the Code of Obligations, meaning that in the case of monetary obligations the debtor is obligated to pay to the creditor the agreed upon number of monetary units. This is an optional provision that may be derogated from by the contracting parties through so-called valorisation clauses, such as an indexation clause or a currency clause, tying the contractual price to the value of an agreed index or currency. However, despite these options, such valorisation clauses are seldom used in construction contracts, as it is in the employer’s interest to set an as fixed as possible construction price or investment cost in order to adhere to its envisaged financial plan.

Lex specialis concerning a construction contract

Due to the above-mentioned reasons that may lead to an increase in the construction material prices, the Code of Obligations lays down special rules pertaining only to a construction contract and derogating from the above-described monetary nominalism principle, as well as from the rules regulating the termination of an agreement due to changed circumstances (known as the rebus sic stantibus clause).

In principle, the contractor may demand an increase in the contractual price for the works performed in time, provided that during the period from the conclusion until the fulfilment of the contract the prices of elements on the basis of which the price was determined have increased by such a margin that the contractual price should have been higher by at least two percent. This general rule may be applied under the condition that the contract does not state otherwise. Considering the fact that this provision represents background law, it may be derogated from by way of an agreement between the parties.

It is also important that the contractor is not in delay with the performance of the works, as it would be unfair to the employer to be liable for construction element price increases occurring during the period when the contractor should have already finished with its work. Should such a delay be a consequence of a force majeure or an act or omission by the employer, the contractor would still be entitled to demand an increase.

In certain cases, the contractor which is in delay with the fulfilment of its obligations under the construction contract due to reasons within its sphere of influence may still be entitled to a construction contract price increase; namely, where the prices of elements on the basis of which the price was determined have increased by such a margin that the contractual price should have been higher by at least five percent. This means that the contractor who is at fault for the delay must meet stricter conditions for the assertion of its price increase claim compared to the contractor who is in not in delay or is in delay but through no fault of its own.

There is an important limitation to the above-described claims of the contractor, namely that the contractor may only demand a difference in the price exceeding the two or five percent margin, respectively.

According to the Code of Obligations, as well as the Special Construction Usages (applicable if the parties fail to explicitly exclude their applicability to the contractual relationship), the construction contract price increase is calculated using the price determined by the contract as a basis.

Considering the fact that the most commonly used clause in construction contracts in Slovenia is the turnkey lump-sum clause with a fixed and unchangeable price, this means that in most construction contracts, the contractor waives, in advance, the right to demand an increase due to unforeseen and changed circumstances, however, even such a waiver is not absolute, as it may not violate the fundamental conscientiousness and honesty principle postulated in the Code of Obligations. This is the reason why Article 656 of the Code of Obligations contains a provision stipulating that the contractor may, despite the above-mentioned clause, demand an increase in the construction contract price if the prices of elements on the basis of which the price was agreed have increased by such a margin that the contractual price should have been higher by at least ten percent. In such an event, the contractor is entitled to demand an increase by the margin exceeding the ten percent increase. It must be pointed out that this provision is widely considered to be mandatory, which is why its applicability cannot be excluded by way of an agreement between the parties.

The manner in which the price increase claim is asserted

Should all the prerequisites for the contractor’s claim to demand an increase in the construction contract price be fulfilled, the contractor must submit a proper demand to the employer which must be substantiated and corroborated by appropriate evidentiary documents showing that the construction material prices have indeed been increased by a requisite margin. Legally speaking, such a demand of the contractor represents a unilateral entitlement of the contractor to achieve a formation or change of a legal relationship without the consent of the counterparty. This means that the counterparty has no legal means to defend against such claim, but may withdraw from the contract if the price increase would be significant.

According to the settled case law, no new contract or addendum has to be entered into with regard to the increase of the construction contract price as a consequence of the contractor’s unilateral entitlement, however, in practice, this is usually done so as to avoid and potential disputes. Should the employer refuse to acknowledge and/or pay the increased construction contract price to the contractor despite the contractor’s claim being well-founded, the contractor may avail itself of any legal remedies afforded to it under the construction agreement, mostly before the competent courts or before the competent arbitration tribunal if its competence is explicitly agreed by the parties prior to or after the dispute in writing.

Odvetniška družba Andrić

Štefanova ulica 13A
1000 Ljubljana
Slovenia

+386 1 43 00 333

+386 1 43 00 320

info@andric.si www.andric.si
Author Business Card

Law and Practice

Author



Odvetniška družba Andrić is a professional team of six legal experts specialised in the fields of corporate, real estate, construction, insolvency and IT law. It remains the firm’s goal to provide clients with a wide range of legal services which commercial companies may require in order to ensure the unhindered performance of their business. The leading principles of the firm’s work are quick responsiveness and the ability to adapt to the needs of clients, as well as the continuous improvement of the quality of its services. The firm’s offices are located in the heart of Ljubljana in direct proximity to all the important judicial, administrative and other institutions, which enables it to pursue the interests of its clients quickly and effectively. The key areas of practice in relation to the construction sector are retail networks, real-estate project development, development financing, cross-border transactions and expropriation procedures.

Trends and Developments

Author



Odvetniška družba Andrić is a professional team of six legal experts specialised in the fields of corporate, real estate, construction and IT law. It remains the firm’s goal to provide clients with a wide range of attorney services, which commercial companies may need in order to ensure the unhindered performance of their business. The leading principles of the firm’s work are quick responsiveness and the ability to adapt to the needs of clients, as well as the continuous improvement of the quality of its services. The firm’s offices are located in the heart of Ljubljana in direct proximity to all the important judicial, administrative and other institutions, which enables it to pursue the interests of its clients quickly and effectively. The key areas of practice in relation to the construction sector are retail networks, development financing, cross-border transactions and expropriation procedures.

Compare law and practice by selecting locations and topic(s)

{{searchBoxHeader}}

Select Topic(s)

loading ...
{{topic.title}}

Please select at least one chapter and one topic to use the compare functionality.