The principal laws governing the construction market in the State of Kuwait are the Kuwaiti:
In Kuwait, standard contracts are commonly used (eg, FIDIC, NEC3) among contractors and employers to facilitate the drafting phase and to ensure that all parties are following the standard practice in the region as well as globally, with the understanding that one of the parties is usually a foreign entity.
Contracts often originate from, or are inspired by, International Federation of Consulting Engineers (FIDIC) forms, and it is common practice for parties to adopt these forms of contract. Publicly known forms that are often used include the:
As for other mega-projects and public-private partnership (PPP) works, a list of standard contract conditions is published on the Central Agency for Public Tenders (the “CAPT”) website, showing conditions that must be included in build-and-operate contracts, consultancy agreements, bids and tenders, subcontractors’ agreements and design contracts.
It is critical to note that while standard contracts are commonly used, Kuwaiti law may differ in the interpretation and enforcement of standard contractual provisions.
The companies and institutions typically involved as employers in construction projects are either wholly or partly state-owned entities or private entities such as commercial and leisure real estate developers and project companies that are set up for a specific mega-project collaborating with the government (that holds a minority share in the project company).
Employers for construction projects in Kuwait typically include oil and gas, power and water companies.
An employer’s primary rights are to:
Employers often have a right to select the contractor and/or subcontractors. However, most major projects require a fair and non-discriminatory bidding process to ensure equal opportunity and employers are therefore required to select a bidder in line with certain criteria.
Employers often have a right to issue changes to the works and contractors often become contractually obligated to proceed with the changes. In these cases, of course, contractors are entitled to a variation in their compensation and schedule to account for the changes made by the employer.
An employer’s primary obligations are to:
The main contractors in Kuwait usually include a mix of local and foreign construction companies. Mega-projects, such as the Al Zor Refinery Project, the Umm Al Hayman Wastewater Project and the Clean Fuels Project, often include foreign partnerships, joint ventures and foreign consortiums.
However, foreign construction companies are expected to play a greater or more direct role within construction projects in Kuwait. This expectation follows recent amendments to Article 24 of the Kuwaiti Commercial Code and Article 31 of the Public Tenders Law. Under the previous legislation, foreign companies were not able to establish a branch in Kuwait or engage in business activities in Kuwait unless this was through a Kuwaiti agent. In the absence of an exemption from the relevant authority, only Kuwaiti individuals or companies were generally able to submit bids for tenders or contracting too.
Under the amended legislation, foreign companies may establish a branch in Kuwait and, through the same entity, engage in business activities in Kuwait without the prerequisite need for a local agent. Additionally, the amended legislation does not limit the submitting of bids for tenders or contracting to Kuwaiti individuals or companies. As a result, foreign entities may submit bids for tenders or contracting.
The effect of these amendments is that foreign construction companies do not need an exemption from the relevant authority to submit bids for tenders or contracting in respect of construction projects, nor do they need, as a precondition, a Kuwaiti partner or agent to submit a bid. With the unrestricted opportunity to bid for tenders or contracting against local entities, it is likely that foreign entities will participate in a greater selection of construction projects in Kuwait. This is in line with the objectives of the amendments as set out in the explanatory memorandum to Law No 1 of 2024 Regarding Amending Article 24 of the Kuwaiti Commercial Code and Article 31 of the Public Tenders Law, which provide that authorities are no longer permitted to limit any offering to national or foreign companies.
The intended effect of the amendments is to open the market further by allowing greater and wider participation of foreign investment, which, in theory, should lead to better competition and choices within the market.
While the previous legislation, like the amended legislation, allowed foreign entities who submit bids for tenders or contracting to be exempt from complying with certain local partnership requirements, the effect of the amended legislation is that foreign entities do not need to submit bids for tenders or contracting in order to establish a branch in Kuwait wherein they can carry out their business activities. This allows foreign construction companies to facilitate their construction-related business operations in a direct way, whether in respect of activities under bids for tenders or contracting, or of other activities.
Significantly, foreign construction companies may execute or support their operations for a contract through their own branch in Kuwait and without local partners such as agents. In relation to the application of the amendments, anticipated regulations may provide clarification in this respect and in respect of related considerations such as employee sponsorship.
It is common for special purpose vehicles (SPVs) to be set up for large-scale projects to ensure effective risk management. However, the main contractors with the employer will often remain the parent entities. SPVs generally take the form of limited liability companies but may also take the form of closed or public shareholding companies. SPVs in the construction industry are often created between a local contractor, an international contractor and (for example) a facilities management contractor. It is also common, especially with PPP projects, for employers to partake in the ownership of these SPVs.
For smaller projects, local companies are often assigned the contract.
A contractor’s main rights are to:
A contractor’s main obligation is to execute the work in line with the contract’s requirements and specifications as required by applicable regulations and to pay its subcontractors for their completed work in a timely manner.
The Kuwaiti Civil Code also places obligations on the contractor, such as to remedy defects. Additionally, it places obligations on the contractor to perform the work in line with the current usage and within a reasonable time limit as required by the nature of the work, with due consideration of usage in the trade.
The contractor is also obligated to inform its employer about any defects caused or revealed in the course of the work in the materials provided by the employer, or where other elements have arisen which tend to impede immediate performance of the work in the appropriate conditions. If the employer provides the contractor with materials, the contractor becomes obligated to keep those materials safe, including being obligated to:
The main contractor will often subcontract parts of the work to specialist subcontractors and, in many cases, will be required to accept subcontractors that have been nominated by the employer. Subcontracting is permitted, provided it is specifically allowed in the main contract. Given the scale of the projects and the specialist works required, subcontracting is very common, particularly in relation to specialist fields such as:
Subcontractors have the same rights and obligations towards the contractor that the contractor has towards the employer. One key right afforded to subcontractors in Kuwait, in addition to those the contractor has in relation to the employer, is expressly provided for in the Kuwaiti Civil Code: the right to obtain payment directly from the employer (from monies owed or due to be owed by the employer to the main contractor). In these cases, where the subcontractor is entitled to monies from the contractor and the contractor has failed to make payment to them, the subcontractor may claim the amounts directly from the employer.
Relevant institutions that typically act as financiers in a construction project include banks and financing institutions that are well known in Kuwait.
Public bodies may also be responsible for financing construction projects in Kuwait.
In 2014, the Kuwait Authority for Partnership Projects (the “KAPP”) was established to oversee all PPP projects and to promote private sector participation in infrastructure development. The main aim of the KAPP was to establish a long-term development plan for the country and to attract private sector investors in key strategic industries such as energy, water, transportation and healthcare. In some cases, a governmental entity may take part in financing a construction project.
In Kuwait, various types of companies and institutions may act as designers in a construction project, including architectural firms, engineering firms, design consultancies and (sometimes) specialised design divisions within construction companies.
In general, the rights and obligations of the designer under a construction contract in Kuwait include the following.
In Kuwait, the relationship between the designer, the employer and the contractor involves close collaboration throughout the project’s life cycle. The designer works closely with the employer to understand project requirements and objectives, translating them into design concepts and specifications. The contractor relies on the designer’s plans and specifications to carry out the construction work accurately. Effective communication and co-ordination between all parties is essential to ensure the successful delivery of the project.
The scope of work in a construction contract is usually predetermined and agreed upon between the parties in the contract itself or during the life of the project through additional addendums to the initial scope of work or through change orders.
The programme of requirements and specifications is often built up and assembled by the employer or the consultant in charge before the project commences. The value-engineering options and specifications are also determined and fixed by the employer, agreed upon and presented to the contractor who will execute and perform them.
Procedures for variation orders and changes are usually determined in the contract to allow the parties to the agreement, specifically the contractor, to apply for a change proposal and for the employer to be able to respond by either rejecting or approving it.
Changes and variations issued by the employer, either on its own initiative or at the request of the contractor, typically fall within the contractual provision stating and allowing for this. Changes are usually gateways for entitlements to financial adjustments and time extensions. The authors have encountered cases involving claims for prolongation or time extension due to changes or variations that were made to the provisional turnover schedule stipulated in the contract. In these circumstances, time extensions for the completion of the works will be implemented and claims for prolongation costs will take place.
In colossal construction projects, the design responsibilities are often handled by a design consultant who is engaged by the employer.
Work will mostly be undertaken by two key players: the contractor/subcontractor and the employer. The responsibility of the employer will typically include payment and financial obligations. The engineer or consultant will mainly be responsible for supervising the execution and performance works. Lastly, the contractor will be mostly or entirely responsible for the execution of the works.
Site accessibility is usually the responsibility of the employer. They are responsible for granting the contractor access to the site within the timeframe required by the works programme. The employer is also responsible for informing the contractor of the status of the site, including existing pollution and ground conditions.
Once the site is under the custody of the contractor, they are responsible for the site. When in possession of the site, they are normally responsible for the maintenance of the site, health and safety measures and on-site noise and pollution levels.
With respect to archaeological finds, the party (whether the contractor/subcontractor or the employer) who makes the discovery is responsible for reporting it to the authorities and for informing the parties to the contract to ensure that all works are halted until an investigation has taken place.
In general, construction permits are acquired from the Kuwait Municipality and it will be the responsibility of the employer to acquire them.
Furthermore, once the permits have been obtained for the design of the works, the contractor is responsible for obtaining permits for the execution of the works.
According to the Kuwaiti Civil Code, amounts due to contractors and engineers who have been entrusted with the erection, reconstruction, repair or maintenance of buildings or other works have a privilege over the works to the extent of the increase resulting from the works and of the value of the immovables at the time of sale under Article 1081 of the Kuwaiti Civil Code.
The contractor is usually responsible for the maintenance of the works. Corrective works during the defect liability period are undertaken in line with the division of the works specified in the contract.
The employer is usually responsible for operation, finance and transfer functions. In specific cases, there may be exceptions for PPP projects or for build, own, operate or transfer contracts.
The process universally used for construction projects when implementing a test for completion of the works is typically enshrined in the contract and is agreed on between the parties prior to the works starting. However, it is worth noting that many standard construction contracts are inspired by a FIDIC form, which, in the Red Book, provides that tests for completion be undertaken by the engineer in charge, the design consultant or the principal within 14 days from the date following notification.
Once the completion certificate is issued and the completion date arrives, the employer will be invited to take over the works from the contractor. The delivery date is considered to be the date on which the takeover occurs, either implicitly or explicitly.
There is a decennial liability provision under Articles 692 to 697 of the Kuwaiti Civil Code, which places joint liability on the contractor and the designer in charge, if the subject of the construction project is deteriorated. Specifically, the architect/engineer and contractor are jointly liable for total or partial destruction or damage and for any defect that threatens the strength and safety of a building or a fixed construction, for ten years from collapse or three years from the discovery of the defect.
The contract will also often include a provision referring to the contractor’s obligation to remedy the defects or to complete any remaining works within the scope of works stipulated in the contract.
The concept of responsabilité décennale is also relevant. This concept originated in the French Civil Code (Article 1792-1) and evolved from a desire to protect building owners who could not ordinarily be expected to possess the technical expertise required to identify defects in design or construction at the point of delivery of a project, particularly where the defects were latent.
Contract payments can generally be categorised into two types: fixed lump sum or remeasurement contracts.
In fixed lump sum contracts and in line with Article 690 of the Kuwaiti Civil Code, the contractor does not have the right to demand a price increase. This remains the case even if modifications or additions are made to the construction plan unless the changes result from fault on the part of the employer or have been expressly authorised by the employer.
In remeasurement contracts, the value of the work is calculated based on an estimated predetermined price schedule or bill of quantities (BOQ). The BOQ will usually include an extensive inventory outlining the materials, components and labour necessary for the successful execution of the construction project. In that regard, Article 689 of the Kuwaiti Civil Code stipulates that, if it becomes evident during the execution of the project that it will be necessary to significantly exceed this estimate, the contractor is obliged to promptly inform the employer. Failure to promptly notify the employer will result in the contractor forfeiting the right to claim the increase.
The most frequently used approach for payment is usually tied to the certification of completed work by the contract administrator/project manager/project management consultancy, which will be in line with applicable Kuwaiti law (specifically Article 677 of the Kuwaiti Civil Code). This certification, which is usually followed by an inspection of the finished work, occurs either periodically or at predetermined milestones or stages as agreed upon beforehand.
The value or percentage of the overall contract price is usually tied to the completion of the milestone(s) as pre-established within the agreement. Once these milestone(s) and subsequent inspection have been completed, a contractor is expected to be paid in line with that determined percentage.
In Kuwait, indexation of prices is typically used in construction contracts to manage the risk of large price fluctuations, especially given the potential impact of volatile market conditions and inflation.
The risk of large price fluctuations is typically divided between parties through contractual arrangements and mechanisms, such as the following.
Indexation Clauses
Contracts may include clauses that tie the contract price to a specified index, such as a consumer price index (CPI) or a construction cost index. This allows for automatic adjustments to the contract price based on changes in the selected index, thereby mitigating the risk of price fluctuations.
Price Escalation Provisions
Contracts may include provisions that outline how price escalation or adjustments will be calculated and applied in the event of significant changes in market conditions, such as fluctuations in material costs or currency exchange rates.
Risk-Sharing Agreements
Parties may negotiate risk-sharing agreements where both parties agree to share the impact of price fluctuations up to a certain threshold. Beyond this threshold one party may bear a larger portion of the risk.
Fixed-Price Contracts Versus Cost-Reimbursement Contracts
The choice between fixed-price contracts and cost-reimbursement contracts can also influence how the risk of price fluctuations is allocated. Fixed-price contracts shift more risk to the contractor. Cost-reimbursement contracts may provide greater flexibility but can expose the employer to more risk.
Overall, the specific allocation of risk for price fluctuations in construction contracts in Kuwait depends on the negotiation and agreement between the parties. Indexation of prices is a common strategy for managing this risk.
It is important to note that, in the absence of applicable legal provisions governing due dates of payments, the specific measures and provisions regarding late or non-payment can vary depending on the terms and conditions of the individual construction contract. Parties may negotiate and customise these provisions to suit their particular project requirements.
In government contracts involving large and complex projects, advance payments to the contractor are usually utilised. These payments provide financial support to the contractor to cover initial project costs such as mobilisation, procurement of materials and hiring of labour. Advance payments serve as a form of assurance to the contractor that funds are available to start the project (this is especially the case for foreign contractors).
The contractor is usually paid through interim payments throughout completion of the project, as the contract usually defines the percentage of work completion required to trigger an interim payment. These payments allow the contractor to cover ongoing expenses and ensure a steady cash flow throughout the project.
Delayed payments may occur for various reasons, such as administrative delays, financial constraints or disputes between parties. In these cases, contractual provisions may specify a grace period or a timeframe within which payments should be made. If payment is not made within the specified timeframe, this may trigger consequences such as interest accrual or the right to suspend work.
Despite that, Article 110 of the Kuwaiti Commercial Code stipulates that, if an employer is obligated within a contract to provide payment within an agreed timeframe, they are obligated to provide the contractor with compensation for delay in payment. This compensation takes the form of legal interest, which is fixed at an annual rate of 7% from the due date of the payment. Late payments may also be dealt with by providing the employer with legal notices compelling payment within a specified date and these may be issued by the contractor or by the competent local courts.
The specific invoicing method used may vary depending on the terms and conditions of the construction contract. The chosen method should be clearly defined in the contract to ensure transparency and to facilitate smooth payment processes.
Invoicing methods (agreed upon between the parties) may include a delivery of invoices in physical form, usually as hard copies. However, certain contracts may utilise electronic systems, such as ACONEX or Focus, to simplify the document exchange process, including for the submission of invoices.
Planning in construction-related activities and projects will likely involve planning the validity of the permits, the accessibility of the site, etc. Categories of permitted construction-related activities and their corresponding licensing requirements depend on the type of project, the height of the building and any internal directives that may be applied by the ministry in charge.
Planning will also occur in the period before work commences. Foreign entities seeking to work on construction projects in Kuwait must have a foreign investment licence from the Ministry of Commerce and Industry and a commercial presence in Kuwait. All consultants and contractors must also obtain a classification/licence from the Ministry to carry out the works in Kuwait.
The planning process before or during construction works also involves various permits, including:
Upon completion of the works, the contractor will need to request a completion certificate from the employer.
In the event of a delay, the obligations of the parties are usually enshrined in the contractual provisions and stipulate the procedure that should be followed internally between the contractor and the employer to reach a settlement or to resolve the delay issue.
The contract also usually provides that the contractor should notify the employer upon the occurrence of, or the prediction of, a potential delay. The notice should include the amounts that were incurred and the expected costs and length of delay.
Under the Kuwaiti Civil Code, the primary circumstances where delays are excusable are where:
In Kuwaiti construction practice, there may be excusable and non-excusable delays. When concurrent delays occur, the contractual provision would most probably govern the situation.
In Kuwait, the employer will generally be entitled to remedies in the event of delays if they are caused by a related and immediate breach by the contractor. Article 293 of the Kuwaiti Civil Code Article states that “in the case of impossibility or delay of performance in rem of an obligation, the debtor must compensate the damage resulting therefrom to the creditor, save where the debtor establishes that non-performance or delay of performance was due to a cause beyond his control”.
An extension of time will be awarded based on the contractual procedure. The extension-of-time request will be submitted by the contractor to the employer and the employer will need to answer and respond to the notice within a certain period, which is usually 30 or 45 days.
The extension-of-time root cause could be changed by law, change orders or variations in general that will considerably affect the provisional turnover dates, the force majeure event or an event that severely impacted the timeline of the project.
Kuwaiti courts will likely dismiss claims that the extension-of-time request should be submitted within a certain timeframe. Even when time limits stipulated in the contract are not respected, the courts have requested extensions of time for:
In some contracts, such as FIDIC standard form contracts, there is an option to claim for a circumstance considered to be a force majeure event. The Kuwaiti legislators have described force majeure events and emergency situations as an external cause outside of the contract. In particular, Articles 214 and 215 of the Kuwaiti Civil Code specify that a force majeure event arises where the performance of the contractual obligation is impossible due to an external reason beyond the control of the performing party. In this situation, the contract will automatically be revoked.
Article 437 of the Kuwaiti Civil Code also specifies that the force majeure event should not be predictable.
As inspired by the French Civil Code, the Kuwaiti legislature establishes that the force majeure event could be traced using a series of criteria or a series of elements, including:
According to Article 295 of the Kuwaiti Civil Code “it is permissible to agree that the obligor will bear liability for cas fortuit and force majeure”.
Issues regarding unforeseen circumstances are governed by the terms of the construction contract and the Kuwaiti Civil Code. As long as the contractual provisions do not contravene express provisions in the law, they will be upheld.
Various provisions of the Kuwaiti Civil Code apply to unforeseen circumstances. For example, if, prior to delivery or takeover, the work has perished or sustained damage due to a force majeure event, the contractor may not claim the agreed consideration or reimbursement of their expenses, unless the employer had at the time of the perishing or damage breached its obligation to take over the work.
Likewise, in this situation the employer will not be able to claim the value of the materials provided, unless the contractor was, at the time of the perishing or damage, in default of their obligation to deliver the work and has not established that the thing would have sustained damage had they made timely delivery.
While the Kuwaiti Civil Code generally prohibits the costs (of the contractor) for completing works from affecting the extent of the contractor’s obligations, in the event of an unforeseen extraordinary circumstance which renders the performance of the obligation arising as a result oppressive (if not impossible) and which would result in a heavy loss to the contractor, a tribunal may reduce the obligation of the contractor, or increase the price to be paid by the employer for the same obligation. There are therefore circumstances where the employer may have to pay more for the same amount of work, if an unforeseen extraordinary circumstance occurs, such as new tariffs on raw materials resulting in an extraordinary increase in cost to the contractor.
For events such as force majeure which may be unforeseen, and barring a provision to the contrary, harm resulting from the event excuses the party who would otherwise be liable for the harm caused. For example, if a war broke out and destroyed the contractor’s work in progress, thereby causing the contractor to be delayed and the employer to suffer harm as a result, the contractor would not be liable for the employer’s harm because their failure to perform the work was the result of a force majeure event.
Finally, as regards recoverable damages arising from a breach of contract, the Kuwaiti Civil Code provides that the breaching party is only liable for the harm which could normally have been foreseen at the time of entering into the contract, save where the breaching party committed fraud or gross negligence.
Depending on the cause of the disruption to the works, the contractor may be entitled to an extension of time to perform the obligation, as provided for in the Kuwaiti Civil Code. However, contracts usually specify the circumstances in which a contractor may be entitled to this.
While the concept of disruption is not directly addressed, the Kuwaiti Civil Code excuses performance of an obligation under the following circumstances:
The concept of disruption is not expressly recognised under the provisions of the Kuwaiti Civil Code. Experts broadly acknowledge that construction disruption claims are uncommon in Kuwait. A distinction should be made between the disruption concept and the concept of delays. Here there is little overlap, as in Kuwaiti practice and following Kuwaiti precedents there are not many cases focusing on claims that arise due to a lack of productivity or inefficiency in the execution of the project.
In these cases, a basic claim for damages must be established. This means that a breach on the part of the employer should be taken into consideration or proven in some way for the court or the arbitral tribunal to establish the disrupting event that caused the damage affecting the contractor. As is the case in most damages claims, the damage must be established and there must be a link between the cause and the damage.
The Kuwaiti Civil Code lists certain liabilities that are mandatory, such as any liability classified as a crime (eg, fraud) gross negligence or involving death of an employee.
In line with Article 227 of the Kuwaiti Civil Code, anyone who has committed a wrongful act that caused harm to others is obliged to compensate them, whether the harm is direct (mubashir) or consequential (mutasabib), even where the actor is not a discrete person.
The concepts of gross negligence and wilful misconduct exist under Kuwaiti civil law. The Kuwaiti legislature refers to gross negligence as a breach of the contractual relationship and the duty of care. It refers to wilful misconduct as a breach of the duty of good faith.
The concepts are covered by the legislation governing contracts, usually the Kuwaiti Civil Code and the Kuwaiti Commercial Code. The Kuwaiti legislature does not make a distinction between gross negligence and ordinary negligence (see Salama Ahmad, Notices in Obligation Theory (First Edition, Ain Shams Library)), page 266, where the Egyptian Supreme Court stated that a doctor was required to exercise prudent care which is consistent with medical principle and so would be liable for professional negligence and ordinary negligence (Egypt Supreme Court, No 461 of Year 36, 21 December 1971, page 1062).
An important example stated in case precedents is the gross negligence of a doctor. This could be implemented in the case of gross negligence of a contractor or subcontractor in a construction project, ie, when a subcontractor commits an error on the construction site due to its gross negligence or due to not adhering to quantum or scientific calculations, if related to a power plant or a wastewater project.
In one Kuwaiti case, the court held that a doctor must follow the proper diagnostic procedure and undertake the common medical examination. It was also held that the doctor’s fault must be obviously proved and it must be shown that they acted unprofessionally, whether unknowingly or negligently, contrary to basic and scientific principles of medical treatment (see Kuwait Supreme Court Case No 66, 69/2003 dated 27 October 2003 and Kuwait Supreme Court Case No 519/2010 dated 20 April 2011).
For the calculation of damages, the measure of relief may differ where the damage resulted from the breaching party committing fraud or gross negligence (see also 5.6 Unforeseen Circumstances).
The Kuwaiti Civil Code permits parties to contractually agree the limitation of their liability in the event of a breach of contract resulting in damages (see 5.6 Unforeseen Circumstances). However, an agreement will be rendered null if it exonerates a party from liability for an unlawful act before it occurs. In other words, waivers of liability for future acts that contradict express provisions of Kuwaiti law are generally unenforceable.
Indemnities are frequently used in Kuwaiti construction contracts to manage risk and assign responsibilities among the parties involved. The particular areas for which indemnification may be provided can vary based on the project’s nature and the negotiated terms of the contract.
Common subjects for indemnification provisions include the following.
Design or Construction Defects
The contractor may indemnify the employer against any costs, expenses or damages resulting from defects in the design or construction of the project. This includes omissions, errors or failures to meet contractual specifications or industry standards in line with Articles 663 and 665 of the Kuwaiti Civil Code.
Third-Party Claims
One party may agree to indemnify the other party against any actions, claims, demands or lawsuits brought by third parties related to the construction project. These are especially typical in instances where the performance of the contractor’s obligations is delegated or utilises the work of third parties and where the contractor assumes the responsibility of the third parties’ actions and accordingly indemnifies the employer in line with Article 204 of the Kuwaiti Civil Code.
Intellectual Property Infringement
If the project involves the use of intellectual property, one party may indemnify the other party against any claims or damages arising from infringement of intellectual property rights, particularly pertaining to any unauthorised use of background and developed intellectual property.
Environmental/Regulatory Compliance
The contractor may indemnify the employer for any costs, fines or liabilities associated with non-compliance with environmental laws, regulations or permits during the course of the construction project.
Delay Claims
The contractor may indemnify the employer against any costs or damages resulting from delays and other disruptions caused by the contractor’s actions or failures to perform according to the contract, in line with Article 293 of the Kuwaiti Civil Code.
In construction projects in Kuwait, the provision of guarantees can vary and the subject is often governed by mandatory or regulatory laws, depending on the regulatory sector which the project involves. The following are some typical guarantees used in construction projects in Kuwait.
Performance Guarantees/Bonds
These guarantees are issued by a bank and ensure that the contractor will fulfil their contractual obligations, complete the project as specified and adhere to any expected industry quality standards. If the contractor fails to meet these obligations, the employer can make a claim against the bonds to recover losses.
Retention Guarantees
These types of guarantees are also known as security deposits and may be provided by the contractor to ensure their compliance with maintenance obligations or other imposed obligations after the completion of the project. They allow the employer to retain a certain percentage of the contractual value until the contractor fulfils their agreed-upon post-completion obligations.
Warranty Guarantees
These types of guarantees are typically provided by the contractor and/or the employer to ensure the quality and performance of the completed work or the equipment used and procured by either party. These guarantees protect the employer or the contractor from defects that may arise during the specified warranty period. If issues occur within the warranty period, the employer/contractor can claim against the guarantee for necessary repairs.
Payment Guarantees
These types of guarantees include payment bonds or guarantees issued by a bank or other financial institution, which are used by the employer as a form of ensuring that subcontractors, vendors/suppliers and other parties involved in the project will be paid for their services and materials.
Statutory Guarantees
Article 688 of the Kuwaiti Civil Code provides certain protections and guarantees that if, for any reason, the contract for work is terminated by an employer before completion, the contractor is entitled to compensation. This compensation includes:
Please refer to 7.1 Indemnities.
Other specific types of insurance policies provide coverage for certain aspects of the construction project. The following are some common types of insurance policies taken out in construction contracts in Kuwait.
Contractors’ All-Risks Insurance (CAR)
This is a frequently secured insurance policy for contractors. It offers them protection against physical loss or damage to the construction project. It typically encompasses risks such as fire, theft, vandalism, natural disasters and accidental damage that may occur during the construction phase.
Professional Indemnity Insurance
This is often obtained by design professionals, including architects and engineers. It serves as a safeguard against claims that may arise from errors, omissions or professional negligence in the design or consulting services that the professionals provide.
Employers’ Liability Insurance
This is commonly obtained by employers to protect themselves against legal liabilities in the event of workplace accidents, injuries or occupational diseases experienced by employees working on the construction project. This insurance provides compensation to employees affected by these incidents and covers the associated legal expenses.
Delay in Start-Up (DSU) Insurance
This offers coverage for financial losses that the employer or the contractor may face due to project start delays resulting from design errors, material supply disruptions or unforeseen circumstances.
The specific contractual provisions regarding the consequences of insolvency in a construction contract in Kuwait may include the following.
Termination Rights
Construction contracts typically include provisions that allow the non-insolvent party to terminate the contract in the event of the other party’s insolvency.
Step-In Rights
Some construction contracts may include provisions allowing the employer or another party to step in and take over the responsibilities of the insolvent party. This provision enables the project to continue despite insolvency.
Performance Bonds
Performance bonds or guarantees may provide financial security to the employer if the contractor becomes insolvent or fails to fulfil their contractual obligations. In the event of insolvency, the employer may have the right to make a claim against the performance bond to recover losses or secure an alternative means of completing the project.
Assignment of Claims
The contract may include provisions allowing the non-insolvent party to assign any claims or amounts owed by the insolvent party to a third party. This can help protect the non-insolvent party’s interests and mitigate the financial impact of insolvency (in line with Article 680 of the Kuwaiti Civil Code).
Risk-sharing is not regulated within the law per se. However, as in many other jurisdictions, the sharing of responsibility for certain risks is a common practice in construction contracts in Kuwait. The distribution of risk between employers and contractors is generally influenced by the economic and market conditions prevailing during contractual negotiations. That said, some common risks often shared in construction contracts include the following.
Design Risk
Parties may allocate responsibility for design-related risks such as errors, omissions or inadequacies in the design documentation. The responsibility will typically be borne by the employer and will start from when they direct (eg, in FEED documentation) that the contractor bases their work and costs estimation for completing the project on the design.
Force Majeure Events
Construction contracts often contain provisions addressing force majeure events and these provisions typically allocate the risk of these events between the parties. The provisions specify which party will bear the additional costs or delays caused by force majeure events. Article 233 of the Kuwaiti Civil Code limits liability for damages caused by force majeure events. However, Article 295 of the Kuwaiti Civil Code provides that parties may agree in advance to accept and/or limit liability for damages caused by force majeure events.
Delay and Liquidated Damages
Contracts commonly include provisions primarily placing obligations on the contractor for delays extending beyond the agreed-upon timeframe. They may specify the precise calculation method and amount of liquidated damages that the party responsible for the delay must pay.
Site Conditions
Construction contracts typically address the risk of encountering unforeseen site conditions that may affect construction. Provisions usually place responsibility for providing suitable site conditions on the employer.
Standard construction contracts commonly include provisions related to personnel, as can be observed in various contract templates such as the 1999 FIDIC Red Book. These provisions typically require contractors to:
The Labour Law
In addition, Kuwaiti Law No 6 of 2010 on Labour in the Private Sector (the “Labour Law”) contains dedicated provisions for construction workers. These are as follows.
Working hours
Articles 64 and 65 of the Labour Law stipulate that workers are prohibited from working for more than 48 hours a week or eight hours a day, except in specific cases as mentioned in the Law. During Ramadan, the working hours per week are reduced to 36.
Overtime
Article 67 of the Labour Law stipulates that overtime work should not exceed two hours a day or 180 hours a year or three days a week and 90 days a year. Workers have the right to provide evidence of being assigned extra work or to receive overtime pay, which should be 25% higher than their regular pay for the same period.
Public holidays
Article 68 of the Labour Law stipulates that if the work circumstances require the worker to work on any officially recognised public holiday, they have the right to receive double the regular remuneration for that day and should also be provided with another day off as compensation.
In line with Articles 681 and 682 of the Kuwaiti Civil Code, possibilities exist under Kuwaiti jurisdiction in relation to subcontractors.
A contractor has the option of delegating the execution of all or part of the work to a subcontractor unless the contract explicitly prohibits this or the nature of the work requires the contractor’s expertise. The involvement of a subcontractor does not absolve the principal contractor from their obligations towards the client or from their liability for the actions of the subcontractor.
In addition, when carrying out a contract, both the subcontractor and the workers employed by the principal contractor have the right to directly pursue legal action against the employer. However, their claims are limited to the extent of the amounts owed by the employer to the principal contractor at the time the legal action is filed. Similarly, the workers of the subcontractor may also take legal action against both the principal contractor and the employer, but only up to the amounts owed to them.
In Kuwait, intellectual property provisions in construction contracts typically address the ownership, use and protection of intellectual property rights related to the project, specifically the use of any background or developed intellectual property. These provisions specify the ownership of intellectual property and may grant licences or permissions for its use, including any measures to protect the intellectual property from unauthorised use or disclosure.
Construction contracts may also outline obligations for parties to take the necessary steps to safeguard intellectual property rights and may include confidentiality agreements and non-disclosure clauses. Indemnification clauses are commonly included to protect against intellectual property infringement claims. The transfer of intellectual property rights upon completion of the project is often addressed, including the transfer of ownership or usage rights to the employer or relevant parties.
It is also common for designers to provide collateral warranties to third parties (such as funders, purchasers and key tenants). These warranties serve as a legal agreement between the designer and the third party, providing the third party with certain rights and protections in relation to the design of the project.
Please refer to 5.3 Remedies in the Event of Delays.
The Kuwaiti Civil Code provides for parties involved in construction contracts to have a range of remedies at their disposal in the event of a breach. Damages can most commonly be sought to recover financial losses resulting from a breach and specific performance may be pursued. This involves the non-breaching party requesting that the breaching party fulfil their original contractual obligations.
Additionally, termination of the contract is an option in the event of a material breach, allowing the innocent party to cease their performance under the contract and possibly entitling them to seek damages for any losses suffered due to the breach. Another potential remedy is rectification, which involves requesting that the breaching party correct any defects in or non-conformance with the construction work, to align it with the agreed upon contractual requirements.
It is not uncommon in Kuwait for parties to contractually limit the remedies available in construction contracts. These limitations are generally permitted provided they are not in violation of any mandatory provisions of Kuwaiti law and are freely negotiated and agreed upon by the parties.
However, certain statutory limitations on damages are included within the Kuwaiti Civil Code. Article 303 of the Kuwaiti Civil Code states that, if it can be proven that the “aggrieved” party did not suffer any damage, the agreed upon damages will not be payable. In addition, the court has the authority to reduce the amount of damages if it can be proven that the stipulated damages within the contract were greatly exaggerated or if the obligation has been partially fulfilled. Any agreement that contradicts these provisions is considered void.
In addition, according to Article 304 of the Kuwaiti Civil Code, if the actual harm suffered exceeds the agreed upon damages, the aggrieved party cannot claim an increased amount unless they can provide evidence of fraud or serious misconduct.
In Kuwait, contractual sole remedy clauses are frequently used in construction contracts to limit the available remedies for a party in the case of a breach. While they are generally enforceable, there are instances where their enforceability may be challenged in the Kuwaiti courts. Factors that may affect the enforcement include:
Enforcement of a contractual sole remedy clause is often subject to the interpretation of the competent court. If a sole remedy clause is found to be unconscionable, excessively unfair or contrary to public policy, a court may refuse to enforce it. Similarly, if a party can demonstrate that the other party fraudulently induced them into agreeing to the clause or made material misrepresentations, the clause may be deemed void.
In construction contracts in Kuwait, the exclusion or limitation of liability for certain types of damages is a common practice. The specific forms of damages typically excluded can vary based on the terms negotiated between the parties. However, there are several common types of damages that are often excluded or limited in these contracts.
For example, consequential damages, which are indirect or special damages resulting from the breach, are commonly excluded or limited, as they do not exist and are therefore not enforceable under the applicable Kuwaiti law.
In addition, punitive damages, which aim to punish the breaching party for their misconduct, are generally excluded. These damages extend beyond compensating for actual losses and are not usually permitted under Kuwaiti law. By excluding punitive damages, the focus remains on compensating the injured party rather than on seeking punishment.
For foreign entities contracting with local entities in Kuwait, the paying entity is generally required to withhold 5% from each payment or the total contract value until the recipient provides a valid tax retention release letter (the “RRL”) which has been issued by the Ministry of Finance (the “MOF”). The RRL is granted by the MOF when it is convinced that the taxpayer has fulfilled their tax obligations in Kuwait or qualifies for tax exemption.
The Kuwaiti Civil Code provides for possibilities where a construction contract may be terminated. These are as follows:
Commercial circuit courts are usually regarded as the most competent courts in Kuwait to adjudicate on construction dispute matters.
In the majority of construction dispute-related claims, the trial judge will be likely to refer the case to an expert from the Ministry of Justice to investigate technical matters related to the claim. This is because the expert will possess the necessary technical expertise and knowledge to assist the judge in reaching a well-informed judgment. The expert is often assigned broad responsibilities, including:
However, the legal aspects of the dispute remain within the judge’s remit.
Kuwait has long recognised the significance of arbitration and has sought to incorporate it into its legal framework, particularly due to the growing importance of arbitration and the expansion of international and local business activities in Kuwait (see Kuwait Law No 11/1995 on Judicial Arbitration with Respect to Civil and Commercial Matters).
The Law has aimed to provide comprehensive coverage of arbitration requirements, authorising the establishment of the Kuwait Commercial Arbitration Centre (the “KCAC”) in 1999 with the primary goal of promoting arbitration as a means of resolving commercial disputes. It was established to facilitate a flexible and efficient arbitration procedure in Kuwait.