Recent Developments in Construction Law
Overview
Turkey’s construction sector has seen an unusually large wave of legislation, case law and administrative guidance since late 2023. The reason for this is twofold: (i) post-earthquake safety and urban renewal priorities, and (ii) the need to cushion contractors against a volatile cost environment. In the following, the authors provide a practical tour of the headline developments, grouped according to the issues board members, lenders and project owners most often ask about.
Stronger risk management rules for new builds and urban renewal
Urban Transformation Law (Law 6306) – November 2023 amendments
The changes were as follows:
These changes make it markedly easier (and faster) to unlock redevelopment projects, particularly strata title apartment blocks in Istanbul’s earthquake risk zones – investors should revisit feasibility models that had assumed long owner-consent timelines.
Building Inspection Law (Law 4708) – concrete sampling communiqué (22 February 2024)
This law tightens on-site presence rules for site engineers during concrete pours, standardises the chain of custody for test samples and mandates digital reporting of results to the relevant Ministry’s portal. This matters for business because developers risk automatic suspension of works if sampling uploads are missing. Contractual time bars should therefore build in inspection buffers.
Site Chiefs Regulation – 6 April 2024
This regulation caps the number of floors and the total floor area a single site chief (şantiye şefi) may supervise, but sets looser caps for disaster reconstruction projects until 31 December 2025. This matters for business because staffing plans must ensure each project retains a dedicated, qualified site chief, and sharing staff across multiple small sites will be harder.
Remote land-registry transactions – 3 December 2024
Parties can now sign title deed transfers from different land-registry offices via the Land Registry and Cadaster Information System (Teokratik Adres Kontrol Bilgi İşleme Sistemi; TAKBİS) after paying fees online, enabling the closure of asset deals without flying all signatories to the same city; this is particularly useful for large portfolio sales.
Public works contracts and inflation relief
Presidential Decree No 8089/8090 (16 January 2024) – the “Enhanced Price Adjustment Decree”
The Enhanced Price Adjustment Decree covers Turkish lira (TL)-denominated construction contracts tendered before 1 March 2023 and still open on 28 December 2023.
For contracts with a price-adjustment clause, the B-coefficient rises from 0.90 to 1.00, and to 1.15 for TOKİ (Turkey’s government-backed housing agency) housing. For contracts without any clause, the employer must pay 15% of the domestic producer price index (D-PPI) change. Contractors may also claim an extension of up to six months if they applied by 15 February 2024.
As a practical tip, the higher coefficient should be factored into cash flow forecasts, and loan covenants tied to project margins should be updated.
Council of State decision (28 February 2024) on Article 46/6 of the Construction Works Tender Regulation
This decision struck down the “60% formula”, which had artificially lowered the value of work experience certificates in land-for-flat deals, calling it non-transparent and anti-competitive. Bidders may now restore certificates to their full value, improving their ability to pre-qualify for high-budget public tenders.
Regulation amendment of 10 December 2024
The relevant Ministry responded to the aforementioned ruling by introducing a clearer 85% benchmark (building permit area × unit cost × 0.85), which applies prospectively and allows the reissuance of past certificates.
As a practical tip, whether previous certificates can be upgraded within the 30-day window should be checked, and the higher amounts in 2025 tenders should be used.
Public Procurement Authority circular and decisions, May–June 2024
Tender documents can no longer force contractors to supply unrelated items (cars, laptops, etc) for the administration’s own use, and several tenders where bid rejection steps skipped document request procedures were annulled. These decisions serve to cut hidden project costs and strengthen challenges against arbitrary exclusions.
Courts sharpen contract discipline and property-rights balance
Key Court of Cassation rulings (2024)
Oral construction contracts – burden of proof
The 6th Civil Chamber overturned lower courts that had demanded the contractor prove works done under an oral deal; the rule is that the landowner must disprove completion once the contractor alleges performance. One should make sure contracts are in writing, but if not, the ruling offers a litigation lifeline.
Architectural drawings – IP rights
Reusing designs prepared for one public project in another without the architect’s consent infringes economic rights under the Copyright Law and triggers damages. Public sector employers can no longer assume automatic, unlimited assignment.
Title-deed transfer suits
Where a flat-for-land contract promises turnkey delivery, the unit buyer cannot force deed transfer until the builder resolves all zoning and occupancy permit defects; courts must quantify cure costs and allocate them under the contract. Pre-sale purchasers should therefore insist on escrowed hold-backs.
Constitutional Court – property rights versus safety
Article 18 of the Squatter Housing Law (Law 775), which allowed municipalities to demolish illegal structures without any written decision or judicial review, was annulled in February 2024. The Court held that even unpermitted buildings may embody constitutionally protected property, and owners must have access to a judge before the bulldozer arrives. Municipalities must now issue a reasoned order open to administrative appeal.
Safety and staffing compliance checklist for 2025 tenders
The checklist items are as follows.
Strategic takeaways for boards and lenders
The main takeaways are as follows.
Conclusion
The post-earthquake reforms have tightened technical compliance while softening the economic blow of high inflation on ongoing projects. Early adopters – developers who digitalise permit files, renegotiate escalation clauses and refine staffing plans – will enter 2025 tenders with a clear edge. By contrast, overlooking seemingly “minor” rule changes (concrete sampling, site-chief limits, demolition due process) can still halt works or void certificates.
Recent Trends in Construction Law
The post-earthquake rebound is still the main growth engine
This rebound is characterised by:
As a business takeaway, more than half of medium-sized contractors’ 2025 revenues are tied – directly or via subcontract chains – to quake-related housing and infrastructure. Bid capacity and working capital lines should be prioritised for these tenders.
Costs are stabilising but remain far above 2022 levels
Construction Cost Index (CCI) – March 2025
The latest reading for the CCI is +18.8% (materials), declining from +40% in mid-2024. Steel and cement prices cooled on softer export demand.
Housing Price Index – April 2025
The latest reading for the Housing Price Index is +32.9% (nominal; –3.6% real). Real prices are now falling against the Consumer Price Index (CPI) for the first time since 2019.
Inflation buffers
The Enhanced Price Adjustment Decree lets contractors on older public contracts recover up to 100% of input price changes; for new contracts, firms still create bespoke escalation clauses pegged to D-PPI.
Although material inflation is no longer an existential threat, margin planning should still stress test 15–20% annual swings in steel and cement prices.
Sustainability moves from “niche” to procurement baseline
Green cement is now mandatory in public works in Turkey. A communiqué from 16 March 2024 caps clinker ratios at 0.80 in public tenders from 1 January 2025, tightening to 0.75 in 2030.
There has also been momentum in respect of Leadership in Energy and Environmental Design (LEED) and the Building Research Establishment Environmental Assessment Method (BREEAM). Turkey now ranks ninth globally for LEED projects, with 1,800+ registered or certified buildings; private developers use certification to attract green finance.
Turkey is the EU’s largest cement supplier; 42% of Turkish exports to the EU will be carbon border adjustment mechanism (CBAM)-covered, accelerating domestic carbon pricing reforms and with a pilot emission trading system (ETS) set for early 2025.
From 2025 onwards, project models that ignore clinker limits, environmental product declaration (EPD) requests or CBAM-driven cost uplifts risk being flagged as “non-compliant” in both public and bank due diligence screens.
Finance and PPP activity broaden beyond classic highways
As green funding channels, the International Finance Corporation (IFC) and local banks have launched green mortgage pools and covered bonds totalling more than USD150 million to spur energy-efficient housing.
The PPP pipeline now tops USD215 billion. Since 1986, Turkey has signed 272 PPP deals; more than half closed in the past decade, and transport still accounts for the lion’s share, but new hospital, port and data centre PPPs are now on the market.
Regarding international contracting strength, eight Turkish firms feature in the “2024 Top 250 International Contractors” of the Engineering News-Record (ENR), and deals such as Yapı Merkezi’s USD3 billion Uganda railway highlight overseas diversification despite a domestic focus.
Equity investors will increasingly ask for ESG screens and CBAM readiness; meanwhile, Turkish contractors’ overseas earnings provide an FX hedge against TL-denominated domestic margins.
Technology adoption accelerates slowly but decisively
Building information modelling (BIM)
A government pilot requires BIM files for public buildings over 20,000 m² in size in 2024–25, and BIM is already mandatory for private megaprojects. Obstacles reported include fragmented standards and skill shortages.
AI and data analytics
AI has seen early use in safety risk prediction and cost optimisation, and professional bodies have promoted continuing professional development (CPD) courses in 2024–25. However, obstacles include cultural resistance and limited local case studies.
e-Ruhsat/Building Control System (Yapı Denetim Sistemi’ne; YDS) digital inspection
Ministry portals now handle concrete sampling, site chief registration and permit tracking nationwide. However, SMEs struggle with hardware and connectivity in rural sites.
Business takeaway
Digital compliance (e-concrete logs, QR-coded site chief IDs) is increasingly becoming a legal requirement; chief investment officer (CIO) budgets that focus only on BIM may miss “small” but critical inspection systems.
Labour force and governance adjustments
Concerning site chief limits, April 2024 regulation caps the floor area that a single site chief can oversee, forcing firms to budget for more certified staff or face permit suspension.
Oversight of concrete pours has also been strengthened. A communiqué from 22 February 2024 demands real-time digital upload of sampling data; missing entries trigger automatic work stoppages.
Finally, the Court of Cassation shifted the burden of proof to landowners where oral construction contracts exist, underlining the importance of written agreements for dispute management.
Housing affordability shifts demand patterns
Real housing prices are cooling but remain high. Nominal home prices rose 33% year on year in April 2025, but they fell 3.6% after adjusting for the CPI. New-build delivery still lags urban demand, especially in Istanbul.
An increase in small-footprint and modular homes has also been seen. Container and prefab units cost roughly half the price of a conventional flat and can be installed on peri-urban land, and demand is rising among young families and retirees. Developers exploring smaller unit sizes, build-to-rent housing and prefab townships may be able to capture unmet price-point segments while also reducing cycle time.
Strategic implications for boards
Based on the foregoing, the recommendations for boards are as follows:
Conclusion
Turkey’s construction market is entering a “high-discipline, high-demand” phase. Earthquake rebuilding and urban transformation underpin volume, and sustainability rules – along with decrees on digital inspection and cost control – raise the compliance bar. Companies that industrialise (potentially involving the prefab marketing and BIM), decarbonise (potentially involving green cement or EPDs) and professionalise (eg, through robust contracts or digital records) are best placed to turn the post-2023 rebuilding wave into stable, export-ready growth over the next five years.
Ağaoğlu My Dream Villaları Villa No 1
Tunuslu Mahmut Paşa Cd. No 25
Üsküdar
İstanbul
Turkey
+90 216 401 22 52
info@firatgultekin.av.tr www.firatgultekin.com.tr