The Republic of Ecuador Constitution establishes non-renewable natural resources (including oil and gas) are part of the inalienable, unseizable and imprescriptible assets of the state. Therefore, oil exploration and exploitation activities must be carried out by the state through its public companies or by mixed economy companies. These activities could be granted to private entities through contracts accepted by Ecuadorian law, but only by exception.
When E&P activities are carried out by private entities, these companies operate as contractors of the state and are entitled to receive petroleum as their share in production-sharing agreements or as payment in service agreements.
The following governmental agencies primarily regulate hydrocarbon activity.
Ecuador has one state-owned company (NOC) for the hydrocarbons industry, Empresa Pública de Hidrocarburos del Ecuador, EP PETROECUADOR, which is in charge of exploration and production of oil and gas, transporting, refining, storing and commercialising both nationally and internationally all hydrocarbons (upstream, midstream and downstream operations). Currently, EP PETROECUADOR is the main oil producer and performs exploring and producing activities in respect of hydrocarbons in dozens of fields.
EP PETROECUADOR was merged in 2020 with Empresa Pública de Exploración y Explotación de Hidrocarburos PETROAMAZONAS EP, which exclusively handled upstream operations.
The Constitution grants the state exclusive ownership of energy resources, minerals, hydrocarbons, biodiversity and forest resources. All hydrocarbons belong to the state and for that matter EP PETROECUADOR has preferential rights for upstream, midstream and downstream operations.
The oil and gas activities legal framework is complemented with the Hydrocarbons Law, Environmental Organic Code, Regulations on the Hydrocarbons Law, the Hydrocarbons Operations Regulations, the Hydrocarbons Operations Environmental Regulation and EP PETROECUADOR specific resolutions, among others.
Companies or joint ventures must have an executed contract to explore and develop hydrocarbons, according to the Ecuadorian law.
A general contract has a four-year term for exploration that can be extended up to six years and a 20-year term for production, that can also be extended if reserves have been added or there are new investments with a five-year plan.
The Hydrocarbons Law provides the following form of contracts for traditional upstream and E&P activities.
Licences generally must be issued by formal bidding procedures. Public tender processes are held under the terms and conditions set by the Ministry. Usually, once a bidder is qualified, they must submit a technical and economic bid to back up their investment proposal. This proposal will be qualified by the Hydrocarbons Tenders Committee which may recommend the Ministry to award a contract. Once the bidder has been awarded the contract, they must open a local branch or subsidiary to execute the contract in Ecuador.
Exceptionally, licences could be directly awarded, with no bidding process, to an international NOC.
Under the Constitution, the Hydrocarbon Law and the contract terms, the government stake must not be lower than the contractor party. In a service contract, the government part consists of the oil export price minus the per barrel tariff paid to the company, plus all applicable taxes. The government always participates in at least 25% of the gross income of the oil exports of the contract plus all oil transportation and commercialisation fees.
In addition, a company stake consists of the per barrel tariff paid by the government, minus the expenses (investments, operating costs, taxes, etc). The company’s portion may be reduced when oil prices are lower than required to compensate the per barrel tariff.
Under a production-sharing contract, the government income comes from the oil exports of its share, plus taxes and contributions paid by a company or joint venture. In this case, the participation of the contracting company consists of income from the oil exports of its share, minus expenses (investments, operating costs, taxes, etc) which must be paid in accordance with the law and the contract.
Main taxes are income tax, value-added tax and 15% profit-sharing.
Tax law provides a ring-fence provision under which each contract shall keep its accounting independent from other contracts entered by the same party. Therefore, each contract is considered as an independent unit for tax purposes. Consequently, profits under one contract may not be offset with the losses under another contract or other activities of the company.
A contractor pays 15% profit-sharing of which 3% corresponds to direct and indirect employees of the company and the remaining 12% to the government activities with the communities within the area of influence of the exploration and production established in the contract. Additionally, the company must pay a 25% income tax.
Other applicable taxes also include the 15% value-added tax that the company pays on all goods and services required for its operations. Such tax is not refundable under production-sharing contracts. Under service contracts, the amount established (15% value-added tax plus the stated tariff in the contract) is invoiced once a month.
The income of a service contract comes from fees paid to the company or joint venture. On the other hand, in a production-sharing contract, income is based on the sales price and the referenced oil price.
Tax returns are filed annually, and the fiscal year runs from January 1st to December 31st of each year. The statute of limitations before the tax authority to review timely filed tax returns runs out after three years.
Moreover, the company or joint venture can deduct its investments in accordance with the rules for amortising investments for each contract, as well as all operating and transportation costs of each fiscal year and all taxes and contributions paid each year in accordance with the law and the contract.
National oil company EP PETROECUADOR holds preferential rights to explore and produce oil and gas in the entire Ecuadorian territory. NOC’s oil production range is 75–80% of total activity in Ecuador.
An international community NOC, directly or by means of a joint venture, may not need to participate in a bidding process to get a direct award of an E&P contract.
The Hydrocarbons Law provides that public or private companies, contractors and associates must contract a minimum of Ecuadorian personnel. According to this, 95% of the working personnel, 90% of administrative personnel (95% within two years of operations having started) and 75% of technical personnel must be Ecuadorian (unless there is no professional offer in this specific job market). Foreign personnel must promote technology and knowledge transfer to local employees.
Likewise, if the activities are carried out in the Ecuadorian Amazon or Eastern circumscription, the norms of preferential employment have been established by virtue of which no less than 80% of the assigned personnel to such area shall be permanent residents of the region. From this assigned percentage, 60% must belong to the influence zone under a gender, youth and aboriginal criteria; 20% residents from the main activities province; and 20% permanent residents from the circumscription.
Goods and services procurement in the circumscription must be acquired directly or indirectly in the area by establishing awarding benefits by appointing with local, municipal, provincial or regional priority.
Pursuant to the local framework for developing and production stages, exploration commitments and/or activities must be executed within the first four years, extendable for an additional two years. Therefore, production is carried out in the subsequent 20 years in the case of oil exploration and production contracts.
Nonetheless, the Hydrocarbons Operations Regulations allow early exploitation, in terms of which the contractor may execute development and production activities within the exploration period, with prior authorisation from the Ministry.
Once a discovery has been made, it must be reported to the Ministry. A request must be submitted to the Ministry, which must contain the investing company or joint venture field development plan. Once the field development plan has been approved, the production stage will start. The authority has the capacity to regulate fields and well production rates.
The licensee or contractor acts as an operator and, therefore, must take on all investments, exploration and production risks as well as environmental liability pursuant to its environmental obligations. Additionally, a contractor shall comply with all employment laws in regard to maximum number of foreign employees. Other key terms include termination provisions in the event of the contractor breaching the law or the contract.
For an assignment with prior approval from the Ministry, the law requires an evaluation of the assignee to be performed. Such approval needs to be issued through a ministerial decree.
The assignor shall pay a premium for the transfer. The amount is equivalent to one per thousand (0.1%) of the net profit obtained in the preceding year, for each one percentage (1%) of participation transferred, according to the income tax returns. This premium shall in no case be less than USD5,000) for each one percentage of participation. Actual payment may be split between assignor and assignee.
Furthermore, the assignee shall pay to the Ministry a premium for the improvement of the economic conditions of the contract, in the amount of USD5,000 for each one percentage of participation.
Contracting rights may be transferred upon payment of the respective premiums and if such operation was approved by the Ministry. If a company or joint venture does not proceed accordingly, such action may provoke a unilateral termination of the contract (caducidad). Likewise, non-compliance with the procedure may trigger a unilateral termination of the contract.
Competent authorities have the capacity to regulate E&P operations as well as production rates. Ecuador is no longer a member of OPEC; therefore, it is not subject to its production rates. There are no quotas or similar restriction.
Most oil production is transported to the “Balao” Terminal on the Pacific Coast. The SOTE pipeline is owned by EP PETROECUADOR and transports ORIENTE crude oil of an average of 24 degrees API. On the other hand, the OCP pipeline is owned by a private consortium of companies that transports NAPO crude oil of an average of 18 degrees API.
A private company may build and operate a pipeline until the maturity date set in each contract when, subsequently, the pipeline will be relinquished to the state. Currently, OCP is the only primary pipeline owned by a private entity. Its contract is in its final stages.
Private companies may construct and operate refineries, upon formal authorisation. Nevertheless, currently, all existing refineries are owned by EP PETROECUADOR.
Most gas stations are privately held by distribution companies. Others are held by private individual owners that are required to be affiliated with a distribution company.
EP PETROECUADOR currently has the majority of commercialisation and distribution markets and all the commercialisation and distribution is done through products sold by it. However, private companies may access such phases upon obtaining authorisation from ARCH and the Ministry, which will evaluate its financial and technical capacities.
Private companies are authorised to distribute and sell gas, diesel and LPG to final consumers, upon approval by the Ministry. Private companies receive certain subsidised products from EP PETROECUADOR or its subsidiaries and are allowed to have a margin that is set by the government each year. Currently, subsidies set on prices of certain fuels have been reduced or lifted. Accordingly, profit margins for distributors are no longer in force for certain fuels.
A licence from the Ministry or ARCH, depending on the case, is required to execute distribution or commercialisation activities. Licences do not result from bidding processes and may be renewed every five years. For obtaining a state licence, the following factors, among others, may be observed: technical capacity, economic means, locations and plans.
All oil products excluding lubricants are produced, refined or imported by EP PETROECUADOR. Therefore, for private companies to carry out related activities, a licence from the Ministry is required, or they must enter into a contract with EP PETROECUADOR that establishes the terms of the activities.
For 2025, the following taxes apply to downstream operations; 15% value-added tax, 15% profit-sharing and 25% income tax.
The company in charge of refining and importing hydrocarbon products is EP PETROECUADOR. Furthermore, pursuant to the law, distribution of such products shall be made exclusively by EP PETROECUADOR, acting by itself or through the contractual forms established in the law. Therefore, EP PETROECUADOR has preferential rights for distribution. However, private companies do most of the distribution, given that EP PETROECUADOR owns few gas stations.
There are no specific local content requirements for downstream operations established in the Hydrocarbons Law. However, if downstream operations are carried out in the Ecuadorian Amazon circumscription, the norms of preferential employment have been established by virtue of which no less than 80% of the assigned personnel to such area shall be residents of the circumscription.
Generally, all activities are controlled by ARCH, which may impose fines and has competence to suspend any establishment and even terminate a licence or contract. Furthermore, an environmental licence is required for downstream operations, and companies shall abide with environmental regulations.
Pursuant to the Constitution and the law, the hydrocarbons industry is considered a strategic sector throughout its phases. Accordingly, the Ministry may declare eminent domain on land, buildings, facilities and other assets. For this purpose, all expenses and payments must be borne by the private investor. This capacity may not apply for gas stations.
The law states that in an event of shortage in transportation capacity, the oil produced by the NOC has preference over the oil produced by private entities. Accordingly, remaining transportation capacity shall be distributed among private producers, subject to the production capacity of each company.
A system of secondary pipelines (RODA) is owned by EP PETROECUADOR, but each operating company oversees constructing its own facilities when a production-sharing contract is concluded. The point of delivery is typically at the connection to a secondary pipeline, for service contracts. On the other hand, the operator must pay transport fees to the different secondary or main pipelines it desires to use to get its oil to the Pacific Coast, for production-sharing contracts. Under each contract, companies may also construct and use a secondary pipeline with a prior authorisation from ARCH.
Unless force majeure events occur, there is enough transportation capacity to transport oil to terminals, through SOTE and OCP. Transportation tariffs for OCP are set by the contracting parties, while those for SOTE are set by EP PETROECUADOR applying regulations that assess quality and distance.
Ecuador has oil transportation agreements with Colombia, where operators may transport Colombian hydrocarbons through secondary pipelines for getting to the main Ecuadorian pipelines service to the Pacific Coast. For the same purposes, another cross-border transport operation has taken place since 2024 by using river vessels from Peruvian oilfields to transport production in the Amazon region.
Some pipelines may be constructed under the provisions established in each contract and used by private companies. However, such pipelines may serve a public purpose; consequently, third parties may request to access that infrastructure in similar terms applicable to the owners.
Considering there are still some subsidies in force for certain fuels, restrictions have been reduced or even eliminated in recent years. While other fuels remain highly subsidised, EP PETROECUADOR remains the main importer and producer of hydrocarbons distillates sold to private distributors and commercialising companies for a pre-established price (for certain fuels) and with pre-determined price profit margins for sales to the public (for certain fuels). Consequently, there are no pre-established profit margins for distributors for certain fuels.
The Cargo Reserve Act states that all crude and distillates imports and exports must be through FLOPEC, Ecuadorian Public Fleet. This demands all sellers and buyers to get receive this entity’s services or grant the first right of refusal when no vessel services are available for the necessary routes and dates.
In general, the Hydrocarbons Law and its Regulations set the legal frame for export of crude oil, natural gas and petroleum products and the Hydrocarbons Operations Regulations establish that the Ministry shall determine the quotas for export of hydrocarbons to public and private companies. Calculations are based on the estimates of releases (levantes) of the applicable legal framework and contractual provisions. Furthermore, the Ministry shall be responsible for the distribution of the exported volumes.
For other LNG considerations please see 7.2 Liquefied Natural Gas (LNG) and for cross-border pipelines please see 3.10 Laws and Regulations Governing Transportation.
The Ministry is entitled to approve any transfer of interest in downstream licences or an indirect transfer of ownership. Subsequently, payment of premiums is required by law. In respect of taxes for transfers of interest in downstream licences, capital gains tax on the sale of shares is applicable.
Foreign investment may be protected through investment agreements, which seek to obtain stability. According to an investment agreement, investments generated in the country have tax incentives such as reduction on income tax percentage, deductions for the calculation of income tax, exoneration of remittance tax and exoneration of advance payment for income tax for all new investments. Such benefits are available if the investor executes an Investment Protection Agreement (IPA).
Foreign investors will have tax stability in income tax and other national direct taxes, exclusively with respect to the rates and exemptions of each tax in force on the IPA signing date.
Non-discriminatory treatment is offered in the administration, operation, expansion and transfer of investments, which shall not be subject to arbitrary or discriminatory measures. Investments and foreign investors will be granted full protection and assurance, in such way that they will have the same protection that Ecuadorians receive within the national territory. As per the law, property of the investors will be protected and all forms of confiscation are prohibited, either in respect of national or foreign investments.
Where dispute resolution methods for oil contracts are concerned, international arbitration may be agreed by the contracting parties, subject to approval from the State General Attorney Office. With regard to international arbitration for an investment agreement, this will only be applied if it exceeds USD10 million, and will be held under the rules of UNCITRAL, PCA, ICC or CIAC.
It is important to note that international arbitration under Bilateral Investments Treaties (BITs) with other countries may not be accessible, given that Ecuador denounced most of them. Despite such denunciation, the survival clause or “Sunset Provision” applies to investments made before the termination date, extending its protection for an additional period. All other future investments may be outside the scope of treaty protection.
Finally, we must warn that according to the Hydrocarbons Law, following due process, the state has the power to terminate an oil and gas contract unilaterally (caducidad) upon breach of law or contract as a result of the administrative procedure set in the law. The termination decision can be challenged judicially and may be followed by action for damages after termination.
Foreign investment is permitted without constraints. Furthermore, the law does not provide an obligation to have local partners.
There are no official sanctions issued by the Republic of Ecuador. In practice, since 2022, EP PETROECUADOR has announced that awarded foreign companies must refrain from trading hydrocarbons of Russian origin with Ecuador. Some public statements said consequences of international enforceable sanctions were prevented against the country and its officials.
The main environmental regulators are: (i) the Ministry of Environment, Water and Ecological Transition; and (ii) decentralised autonomous governments (provinces and municipalities).
The principal environmental laws comprise:
Environmental legal requirements start with the requirement to obtain an Environmental Licence following a specific procedure set in the law. Authorised environmental consultants shall prepare an Environmental Impact Study (EIS), which is required for the issuance of the Environmental Licence. The EIS presents the characteristics of the environmental conditions prior to the execution of the project, a risk analysis and the description of the specific measures to prevent, mitigate and control the environmental alterations resulting from implementation of the project.
Although the law dictates that a community consultation process is required in order to acquire an Environmental Licence; the state, however, has competence to issue the final decision even if the majority of the community opposes the project. Accordingly, Environmental Licences are issued by the Ministry of Environment, Water and Ecological Transition for each phase of the industry (exploration and production) upon approval of the EIS by the same ministry.
It must be noted that the Constitution prohibits extractive activities in protected areas and in areas declared as intangible, including logging. Exceptionally, hydrocarbons may be exploited at the request of the President of the Republic, and after declaration of national interest by the National Assembly, which, if deemed convenient, may call a referendum.
Furthermore, the Ministry of Environment, Water and Ecological Transition has competence to conduct audits and oversee compliance with the EIS and all applicable laws. As a result, in case of breach, aside from penalties, it may determine that the company has to remediate environmental damages. If the company does not proceed accordingly, the Ministry of the Environment may request the Ministry of Energy and Non-Renewable Resources for the termination (caducidad) of the contract.
Additionally, Ecuador has a strict liability regime for environmental damages. Therefore, the burden of proof demonstrating that no damage has occurred falls on the operating company. Liability for environmental damages may not be assigned to subcontractors, although a knock-for-knock clause is included. There are no caps on liability under local legislation. There may be a cap on liability in certain contracts among private entities or subcontractors; however, in contracts directly signed with the state there are no caps on liability.
It is important to mention that a common provision in main contracts is the requirement to conduct a study on an environmental baseline to determine the status of the assigned area. According to each contract, the company may have to operate in compliance with applicable environmental standards during the term of the project. To terminate a project, the Ministry of Environment, Water and Ecological Transition shall approve a final audit.
Environmental regulation is the most notable area that contains differences between onshore and offshore operations.
The Environmental Regulation for Hydrocarbon Activities states that for offshore management of liquid waste, any offshore platform shall have adequate tanking capacity to receive fluids from drilling and production, in order to remove polluting components prior to their discharge. In offshore operations, the discharge of oil-based drilling mud, which must be treated and disposed of on land, is prohibited. On closed platforms, closed circuits must be installed for the treatment of all liquid waste.
Regarding offshore exploratory and advanced operations, exploratory drilling shall include gravel processing systems, with closed effluent treatment systems, and a system of grey water treatment. Additionally, for offshore production tests, the agent must use systems to recover and treat polluting fluids.
In respect of offshore drilling, in case of temporary or definitive abandonment of an operations area, a well must be permanently abandoned. Also, the agent must take other measures to avoid damage or impediments to fishing, navigation or other activities.
For offshore industrialisation facilities, extracted gas must be dehydrated and the formation water shall be discharged into the environment or injected in accordance with the provisions of environmental regulations.
In an unprecedented judicial decision, the Constitutional Court mandated the National Election Council to run a plebiscite on decommissioning all hydrocarbons activities on Block 43 known as ITT (Ishpingo-Tambococha-Tiputini). Results were in favour of stopping extraction and the current government is facing challenges on fulfilling the people’s decision: “to progressive and orderly withdrawal of all activity related to oil extraction within a period of no more than one year from the notification of the official results”.
Due to lack of specific legislation, during 2024 two Executive Decrees were issued establishing an ad-hoc committee and establishing technical milestones over several years for the decommissioning process.
The judicial ruling mandated that the state may not exercise any actions aimed at re-initiating new contractual relations to continue with the exploitation of block 43.
The Ecuadorian Constitution mandates the state will adopt appropriate and transversal measures for the mitigation of climate change by limiting greenhouse gas emissions, deforestation and atmospheric pollution. In accordance with this, the Environmental Organic Code establishes that the state must create and strengthen the conditions for the implementation of mitigation and adaptation measures to fight climate change.
The Environmental Organic Code establishes that the decentralised autonomous governments (provinces and municipalities) may include climate change criteria in their territorial planning.
The Ministry of Environment, Water and Ecological Transition is entitled to exclusive attributions for granting oil and gas licences to ensure they are conducted in compliance with environmental laws and regulations.
On the other end, decentralised autonomous governments have competence to grant permissions for infrastructure construction required for the development of oil activities (facilities) and other operating permits.
In January 2024, the Organic Law on Energy Competitiveness came into force, which establishes that private companies, at their own risk, may develop projects not foreseen in the Electricity Master Plan, without being subject to a public selection process, as long as the power of the project does not exceed 10 MW.
In the fourth quarter of the year, in the context of the energy crisis that is seriously affecting Ecuador with service cuts for up to 14 continuous hours due to the lack of rainfall that caused shortages in the hydroelectric plants on which the country largely depends, the National Assembly issued a legal reform to allow the private sector to present projects of up to 100 MW in non-conventional renewable energies and renewable energies transition, not contemplated in the Electricity Master Plan.
Court decisions and government plans have set up the deadline for replacing flares with Teas for 2030. The Regulation for the Utilisation of Associated Gas was issued on 5 November 2024 and establishes the rules for using associated gas for generating electricity and/or industrial products and thus reducing flaring associated with outdoor burning of gas. After implementing these actions and when the maximum gas utilisation capacity is reached, flaring shall be authorised in controlled volumes. During 2025, the Ministry must define the contractual pipeline for PPAs and other commercialisation matters and licences.
There are no other material ways in which energy transition is affecting traditional oil and gas development plans in the region.
The Ministry may regulate further features for interests in heavy crude below 15 degrees API, pursuant to the Hydrocarbons Law, although this has not yet been executed in a particular case.
There are recent specific regulations which apply to all local and foreign natural persons or companies, whether public, mixed economy or private, who are interested in engaging in commercialisation, storage, refining, industrialisation and transportation of Natural Gas (NG) – which includes Compressed Natural Gas (CNG) and Liquefied Natural Gas (LNG).
In general, interested companies must demonstrate having owned or received from third parties authorised gas pipelines, terminals or means of transport. Authorisations may be suspended or terminated due to non-compliance with regulations, at the request of the holder, or by decision of the competent authority.
Production-sharing contracts of exclusive service contracts are taking place in the industry. The Ministry expects to award several production-sharing contracts to local and international companies during 2025. The government is constantly analysing the convenience in releasing mature blocks and fields for private companies to enhance global production.
ITT decommissioning is a relevant milestone in the industry due to its legal consequences. In addition, Ecuador is about to have a prior consultation on the Indigenous Communities’ Act for Extractive Activities. It must be enacted by the National Assembly due to a Constitutional Court ruling on this collective right. The court ruled on the need for an Environmental Consultation Law, prior to the enforcement of new legislation and informed consultation regulations are in force, but these cannot be applied within territories of indigenous communities.
Av. 12 de Octubre N26-48 y Lincoln
Edificio Mirage
16th floor
Quito
Ecuador
+593 238 10950
adonoso@robalinolaw.com www.robalinolaw.com/enLegal Framework and Administrative Structure of the State in Energy Matters
According to Article 314 of the Constitution of the Republic of Ecuador, energy in all its forms is considered to fall within the strategic sector due to its economic, political and environmental importance, and the (central) state is in charge of its administration, regulation and control.
The main Ecuadorian regulatory entity establishes that the state must promote energy efficiency and the use of renewable energies (Article 414, Constitution of the Republic of Ecuador), a provision aligned with the constitutional position of limiting greenhouse gas emissions, deforestation and atmospheric pollution, aimed at mitigating climate change.
To comply with these constitutional provisions, in 2015, the Organic Law of the Public Electric Energy Service was issued, recently amended by the Energy Competitiveness Law in 2024, which sets out that the state will establish promotion mechanisms that take advantage of energy resources, especially from renewable sources.
According to the Constitution and the aforementioned law, the state must manage energy resources in accordance with the Electricity Master Plan (PEME), mainly through public companies. However, through the Ministry of Energy and Mines, it may delegate to joint ventures and, exceptionally, to private, state-owned and foreign companies and companies of popular and solidarity economy, the participation in activities of the energy sector when necessary to meet the requirements and needs of the population or when public companies cannot meet this need. The Ministry may also delegate to private, state-owned, foreign and popular and solidarity economy companies the execution of projects that use non-conventional renewable energies that are not included in the PME (Article 25, Organic Law of the Public Service of Electric Energy). In the case of private equity companies and those of the popular and solidarity economy, the state and these companies must sign a concession contract and prior to the start of operations they must have the necessary environmental permits.
The state, through the Ministry of Energy and Mines (MEM), is the administrative authority in charge of the planning, control and development of the energy sector. In addition, the Agency for the Regulation and Control of Electric Energy (ARCONEL) is a technical administrative entity in charge of regulating and controlling the public electric energy service and the general public lighting service.
ARCONEL issues the corresponding regulations for electricity companies, the National Electricity Operator (CENACE) and consumers or end users and controls compliance with the regulations and obligations established in the enabling titles. CENACE, which is a technical entity attached to the MEM that acts as the technical operator of the National Interconnected System (SNI), manages commercial energy transactions and is responsible for the continuous supply of electricity. Finally, the purpose of the public company Corporación Eléctrica del Ecuador, CELEC EP (CELEC), is to be responsible for the generation, transmission, distribution, marketing, import and export of electricity.
Currently, the energy and electricity sectors are mainly governed by the following regulations:
Legal Framework and Administrative Structure of the State in the Field of Oil and Gas
Like energy, oil and gas, as they are non-renewable natural resources, are considered to fall within a strategic sector regulated by the central state. The regulations of the sector are mainly set out in the Hydrocarbons Law, the Regulations to the Hydrocarbons Law, the Hydrocarbon Operations Regulations, which contain the technical provisions of the activity, and the specific environmental regulations that are contained in the Environmental Regulations of Hydrocarbon Operations. There are also secondary regulations issued by the Agency for the Regulation and Control of Hydrocarbons.
The Ministry of Energy and Mines is responsible for formulating the hydrocarbons policy approved by the President of the Republic, as well as for implementing the relevant laws and regulations. Because it is considered a highly technical activity, the provisions are issued by the Agency for the Regulation and Control of Hydrocarbons (ARCH) (Article 9, Hydrocarbons Law).
As mandated by Article 315 of the Constitution, the Public Hydrocarbons Company of Ecuador, EP Petroecuador, is the first port of call for the execution of the activities of exploration, exploitation, transportation and commercialisation of hydrocarbons. Similarly, the state may delegate participation in the oil and gas sector to joint ventures in which it has a majority of shares. Exceptionally, it may delegate this activity to a private initiative (Article 316, Constitution of the Republic of Ecuador).
The Energy Efficiency Law created the National Energy Efficiency Committee, chaired by the Minister of Energy and Mines and made up of several ministries and trade associations. Among the functions of the committee is the co-ordination of the operation of the National Energy Efficiency System, evaluating the performance and results of the policies and objectives of the National Energy Efficiency Plan, as well as the investment plans and programmes implemented for their fulfillment; and to propose the changes or reforms that are necessary.
Trends and News in the Oil and Gas Sector
Through a popular consultation held on 20 August 2023, the citizens decided by a majority to prohibit the extraction of crude oil from block 43 ITT located in the Yasuni National Park area, after the Constitutional Court issued the constitutionality opinion on the question posed. This block reached a production of 57,466 barrels of oil per day on 22 June 2023. With the planned closure of this block, the government is looking for alternatives to maintain the income from the sale of oil, which is very important for the Ecuadorian economy.
Among the measures taken, the Ministry of Energy and Mines announced the government plan to capture USD41,500 million in investments focused on the oil sector in five rounds, under participation contracts in which the contractor assumes the investment and, as payment, receives a percentage of the production of the blocks (Article 12-A, Hydrocarbons Law).
Another investment that the Ministry is seeking is related to the construction of a new variant of the OCP heavy crude oil pipeline, which requires an investment of approximately USD120 million, to recover the pipeline’s transport capacity, affected by the erosion of the Coca River that forced the construction of emergency bypasses and the reduction of the pipeline’s diameter.
At the end of 2024, the Ministry of Energy and Mines exceptionally authorised the delegation of the Sacha oil field, the most productive in Ecuador and currently operated by the Public Company Petroecuador, to foreign state-owned companies or their subsidiaries. A proposal is already being analysed by the Hydrocarbon Tenders Committee.
Transition to Renewable Energies
Although Ecuador is a developing country and is therefore considered among those that have fewer greenhouse gas emissions, like others in the same situation, it will suffer to a greater extent from the effects of this crisis.
To reduce global greenhouse gas emissions and implement measures to adapt to climate change, countries can implement two types of actions: mitigation and adaptation. Mitigation aims to both reduce countries’ net greenhouse gas emissions – for example by decreasing the use of fossil fuels.
As mentioned above, the Constitution prescribes that the state shall limit greenhouse gas emissions. In this framework, Ecuador is a signatory to the Paris Agreement, despite being responsible for only 0.15% of global emissions.
Ecuador presented its first Nationally Determined Contributions (NDC) report, which states that by 2025 a 4% reduction in greenhouse gas emissions from the sector called “land use, land use change and forestry” (USCUSS) is expected. Continuing with the adoption of standards and policies at the national level, in 2017 the Organic Environmental Code was issued, Article 250 of which establishes that climate change management will be carried out in accordance with the national climate change policy and strategy. Shortly thereafter, in 2018, Ecuador adopted the 2030 Agenda for Sustainable Development as a State policy (Executive Decree No 371 in April 2018).
In 2018, greenhouse gas emissions from the energy sector accounted for 51% of Ecuador’s total emissions. Of this percentage, approximately 20,000 gigagrams of carbon equivalent came from the transport sector; 6,900 gigagrams from the energy industries; 4,000 gigagrams from other sectors (commercial, industrial, residential, agriculture, forestry and fishing); 3,000 from non-specific activities; 2,500 from the manufacturing and construction industry; and finally, approximately 1,800 gigagrams come from fugitive emissions from the manufacture of fuels (Ecuador’s greenhouse gas inventory).
As of 3 September 2024, the production of electricity from hydraulic sources amounts to approximately 19,574 MWh, equivalent to 82% of total production, and non-conventional sources generate approximately 1,600 MWh. Clearly, the main source of energy in Ecuador is hydropower, which far exceeds other types of generation that add up to 3,249 MWh.
Even so, directing Ecuador towards the energy transition, the Ministry of Energy and Mines called for a contracting process for non-conventional renewable energy projects, with sources such as solar, wind, geothermal, biomass, tidal and hydroelectric power of smaller capacities (Article 3, paragraph 10 of the Law on the Public Service of Electric Energy).
The power required for hydroelectric projects, among all projects, is 150 MW, a minimum of 3 MW and a maximum of 50 MW per project, and the term of the concessions will be 30 years. This block is aimed at projects that are located on the Pacific slope, to balance with the generation of projects located on the Amazon slope, complementing production in times when the latter slope reaches its lowest levels, affecting energy production.
On the other hand, in the wind block projects, the call establishes that the power required, among all the projects, is 200 MW, a minimum of 10 MW and a maximum of 100MW per project, and the term of the concession will be 25 years.
For photovoltaic projects, the power required, among all projects, is 120 MW, a minimum of 3 MW and a maximum of 60 MW per project, and the term of the concession will be 25 years. However, according to official sources, the usable potential for this type of energy is 60 MWp.
Finally, in respect of the biomass, biogas and urban waste biogas block, the power required between all projects is 30 MW, with a minimum of 1 MW and a maximum of 15 MW per project, and the term of the concession will be 20 years. In Ecuador, there are a few projects of this nature, mainly focused on the processing of sugarcane.
These projects were launched without neglecting other conventional sources, such as a 400 MW natural gas combined cycle block, which still remains the main source of electricity generation for Ecuador. The processes have already been awarded to the winners, but the execution of them has not begun, since it has not been possible to establish some conditions such as the payment mechanism and the acquisition of private land where the resources must be located.
The main source of energy for the transport sector in Ecuador continues to be fossil fuels. Each year, the limit of consumption and emissions levels that all types of vehicles circulating in the country must comply with is established. According to the Energy Efficiency Law, as of 2030, all vehicles that are incorporated into the public transport service must be 100% electric or zero emissions (Article 14, Organic Law on Energy Efficiency), opening an important market in Ecuador.
Other government plans towards the energy transition include the following.