Power Generation, Transmission & Distribution 2024

Last Updated July 18, 2024

Norway

Law and Practice

Authors



Advokatfirmaet Haavind AS is one of Norway’s leading full-service law firms, with 165 lawyers in total and offices in Oslo and Svalbard. Teams are organised by sector and specialisation as a means of positioning the firm to create added value for customers. The firm’s industry sector focus is particularly directed to renewable energy, construction, real estate, technology, fisheries and aquaculture, and offshore and industry. Haavind’s energy practice, recognised as one of the strongest in the electricity and renewables sector, counts 12 dedicated lawyers who, strongly supported by collaboration with specialised teams focusing on the offshore sector and new energy technologies, advise the largest and most important players in the renewables sector. The team’s lawyers cover every legal aspect of the sector, including regulatory matters, M&A and dispute resolution, and are currently involved in the majority of the largest production (especially hydro and wind) and grid projects.

Norway’s power market is a cornerstone of its economy, characterised by a comprehensive regulatory framework that is aimed at ensuring efficient operation and sustainability. The Norwegian power sector is distinguished by its significant reliance on renewable energy sources, particularly hydropower, which accounts for a substantial portion of electricity generation. As of 2023, approximately 87% of the energy mix derived from hydropower, while wind power contributed around 11% (see more in 2.2 Electricity Imports and Exports).

Notably, more than 75% of Norwegian hydropower production is flexible, thanks to the presence of reservoirs that account for half of Europe’s total reservoir storage capacity. This not only underscores Norway’s commitment to sustainable energy, but also influences the structure and regulatory approach of the industry.

The Norwegian ownership structure of the power industry influences operation, efficiency and strategic direction, and is characterised by a mix of state, municipal and private ownership. The public sector owns approximately 90% of the production capacity for electric power in Norway – mostly due to requirements for a minimum of two-thirds public ownership for hydropower (see more in 1.4 Law Governing the Sale of Power Industry Assets). The largest producer is Statkraft SF, which is wholly owned by the state and Europe’s largest generator of renewable energy. The Norwegian mixed ownership model, combined with a robust regulatory framework, supports Norway’s objectives of maintaining a reliable, efficient and sustainable power system.

Statnett SF, also a state-owned entity, owns almost 100% of the Norwegian transmission system, as well as a significant portion of cross-border cables, including subsea interconnectors. It is mandatory for all grid companies to be legally unbundled, and grid companies with more than 100,000 customers must also be functionally unbundled, as specified in the Energy Act Sections 4-6 and 4-7. Most grid companies are primarily owned by municipalities and counties, although some are privately owned as well. There are no requirements for public ownership for wind power plants, solar power plants, and transmission or distribution facilities.

The governance of ownership and operations within the various segments of the Norwegian power industry is underpinned by several pivotal statutes, notably the Energy Act (“Energiloven”). This Act lays down the foundational legal framework for structuring the electricity sector in Norway, addressing aspects such as market regulation, system responsibilities, and fostering a competitive market landscape. Ownership of hydropower plants is regulated in the Waterfall Rights Act.

The Norwegian Water Resources and Energy Directorate (“Norges vassdrags- og energidirektorat” or the NVE) plays an instrumental role in regulatory oversight of the energy sector. The NVE handles licence procedures, ensures adherence to legal standards and monitors the energy sector to promote efficient and sustainable operations. The Norwegian Energy Regulatory Authority (“Reguleringsmyndigheten for energi” or the NVE-RME) is the regulatory authority for the electricity and natural gas markets.

Other central authorities include various Ministries within the Norwegian government, with the Ministry of Energy (“Energidepartementet”) at the forefront, having the overall responsibility for the energy sector.

Production

As mentioned in 1.1 Law Governing the Structure and Ownership of the Power Industry, about 87% of production comes from hydropower, and 90% of hydropower resources are owned by public entities. The following players are at present the largest in Norway in the production segment:

  • Statkraft AS (100% state-owned);
  • Hafslund Kraft AS; and
  • Å Energi AS (previously Agder Energi, now merged with the Glitre company group).

Transmission

The transmission grid owner and operator/TSO is Statnett SF, which is 100% state-owned.

Distribution

Most grid companies are completely or partly owned by one or more municipalities. The following are at present the largest in Norway among grid distribution:

  • Elvia AS;
  • Tensio AS;
  • Glitre Nett AS;
  • BKK Nett AS; and
  • Lede AS.

Electricity Suppliers

Electricity suppliers are mainly private-owned companies, with some public ownership added to the mix. Among the largest in this segment, are Fortum AS and Fjordkraft AS.

Public Ownership Hydropower

To utilise water resources for electricity production, the power producer must acquire the necessary property rights for the waterfalls and pertinent rights: see the Waterfall Rights Act. The Act does not apply to small-scale hydropower plants under the limit of 4,000 natural horsepower.

Licences under the Waterfall Rights Act are exclusively granted to public entities. These entities may be Norwegian state-owned enterprises, municipalities or county authorities, as well as companies where public bodies make up at least two thirds of the capital and the votes. Private entities are permitted to own up to one third of a company that possesses a licence under the Waterfall Rights Act.

A licence application under the Waterfall Rights Act shall be filed to the Ministry of Energy.

According to the Energy Act Section 4-8, only the TSO (Statnett SF) can own transmission grid facilities.

The Security Act

Foreign investments may be subject to ownership screening under the Security Act. This ownership screening requirement applies to entities that fall under the purview of the act, as well as suppliers of goods or services involved in classified procurements. Following amendment to the Security Act in 2023, a ministry has the authority to determine that Chapter 10 (which covers ownership screening) should be applicable to businesses determined to have significant importance for national security.

When acquiring a qualifying holding in an entity that is subject to Chapter 10 of the Security Act, the acquirer is required to notify the Ministry. Currently, this requirement applies to only a limited number of entities within the energy sector.

No Special Protections or Incentives

The regulatory framework governing licensing is applied equitably to investors, irrespective of whether they are domestic or foreign.

There are no special protections that apply to foreign investors, or special incentives or protection to encourage foreign investment in the Norwegian power industry. Foreign investors may obtain the same property rights and will have access to domestic courts.

The principal laws governing the sale of power industry assets and transactions are the Waterfall Rights Act and the Energy Act.

The Waterfall Rights Act

The Waterfall Rights Act regulates waterfalls that have the potential to yield 4,000 natural horsepower or more. A licence for such waterfalls can only be issued to public entities, such as state-owned enterprises, municipalities and county authorities, or to companies where these entities hold at least two thirds of the capital and voting rights. Private entities can own up to one third of the capital and one third of the voting rights in such companies. These requirements apply to sales of assets or businesses in companies holding waterfall rights pursuant to the Waterfall Rights Act, as well as in amalgamations and mergers.

Additionally, the transfer of regulation facilities or shares in regulation facilities can only occur simultaneously with the transfer of waterfall rights, as described in the Watercourse Regulation Act.

The Energy Act

According to the Energy Act, all grid companies must undergo legal unbundling, meaning they cannot engage in activities other than grid development and operation. Grid companies with more than 100,000 customers must also undergo functional unbundling, operating independently from other companies within a vertically integrated company group.

Transmission grid facilities can only be owned by the TSO (Statnett SF) and cannot be sold to others.

Furthermore, owning and operating an energy facility requires a licence under the Energy Act. In cases of amalgamations and mergers, the parties involved must ensure the transfer of the licence by applying to the NVE.

The energy authorities are responsible for processing licence applications and issuing licences for grid and production facilities. Most of the licences are given by the NVE, which is also the supervisory authority.

NVE has been designated as the emergency management authority by the Ministry of Energy (see the Energy Act Chapter 9 and the Regulation on Security and Emergency Preparedness in the Power Supply System). The Directorate co-ordinates emergency response work and appoints the overall management of the Power Supply Preparedness Organisation (KBO). NVE supervises that provisions given in or in accordance with KBF are followed.

Statnett is the Norwegian transmission system operator nationwide, and is tasked with always ensuring a reliable security of supply. This responsibility requires the maintenance of a power grid with sufficient transmission capacity. Additionally, Statnett manages peaks in electricity consumption and oversees the import of the necessary volumes of electricity to meet demands.

NVE has been designated as the rationing authority by the Ministry of Energy. NVE shall ensure that the necessary plans and procedures for notification, implementation, execution and termination of power rationing are always prepared.

Onshore Wind – Local Planning Decision Required

As of July 2023, the Energy Act and the Planning and Building Act was amended with an aim to improve the licensing process for onshore wind projects. Prior to NVE’s handling of a licence application pursuant to the Energy Act, an onshore wind project would need a positive local planning decision from the hosting municipality that allocates the planning area for onshore wind. The objective of the law amendment is to strengthen the role of municipalities in the licensing process for onshore wind, to reduce the level of conflict, and thereby laying the foundation for further expansion of wind power, including strengthening the power balance and achieving national climate goals.

The Norwegian government has furthermore, to accelerate the processing time of onshore wind projects, adopted new criteria for NVE’s handling of licence applications for onshore wind. According to the new criteria, large onshore wind projects, projects with approved zoning plans in the local municipality and onshore wind projects in Finnmark country will be prioritised. Additionally, according to the wind power message issued in 2020 by the Norwegian government, licence applications containing documentation of involvement from reindeer husbandry in the assessments and an agreement on mitigating and compensating measures will be prioritised in the licensing process over applications lacking proper documentation of these aspects.

Unbundling Requirements

In 2023, amendments were also made to the Energy Act that extend the exemption from the functional separation requirement for grid companies. The requirement now applies to grid companies with 100,000 or more grid customers (before amendments: 10,000).

New Prosumer Scheme for Local Solar Power

By amending the regulations, the government has made it possible for electricity customers in housing co-operatives, multi-family dwellings and commercial buildings to share self-generated electricity. The changes to the regulations mean that grid customers on the same property can avoid grid rent and fees for consumption of electricity they produce themselves, for example with solar panels. The legislative changes entered into force on 1 October 2023.

Amendments to Strengthen Security of Supply

From 1 July 2024, the so-called “governance mechanism”, amending the Watercourse Regulation Act, will enter into force. The purpose is (see Prop. 33 L (2023–2024) p. 5) to establish instruments that will collectively help strengthen security of supply during periods of increased uncertainty in the Norwegian power system and in surrounding energy markets.

The changes consist of three main elements: a new purpose clause in Section 1a; a new Section 29a, with a requirement for a strategy to contribute to security of supply; and amendments to the Energy Act Section 6-2 (4) to provide regulatory authority to lay down regulations to avoid power rations, such as reporting of hydropower production.

Taxation

The former high price taxation on hydropower was removed with effect from 1 October 2023. The resource rent taxation on hydropower is still 45% in 2024. The taxation applies to hydropower plants with generators of at least 10 MVA.

From 2024, onshore wind power is subject to the resource rent tax at 25%, the production tax at NOK2.3 cent per kWh and ordinary income tax at 22%.

Retail Market

On 3 November 2023, the Norwegian government proposed several measures to reduce the information bias consumers experience in the electricity retail market, with an aim to make it easier for electricity customers to identify advantageous electricity contracts and help electricity customers get away from unfavourable contracts.

Solar Power Licence Scheme

On 19 December 2023, the government proposed amendments to the Energy Act and the Planning Act concerning processes for the establishment of licensable onshore solar power plants. The proposals follow up the National Assembly’s request resolution of June 2023, in which the government is asked to submit a proposal on how ground-mounted solar power plants can be included in the Energy Act.

The proposals entail a change in the decision-making processes and mainly follow the same pattern as was adopted for wind power plants in 2023 (see Prop. 111 L (2022–2023)). See further 1.6 Recent Changes in Law or Regulation. The deadline for submitting comments was 31 January 2024.

Surplus Heat

The government wishes to encourage companies planning facilities that require a lot of energy to carry out cost-benefit analyses of the potential for utilising surplus heat. On 16 May 2024, the Ministry of Energy presented a proposal for a new regulation on cost-benefit analysis of the possibilities for utilising surplus heat (waste heat).

Grid Connection

On 7 May 2024, the Ministry of Energy sent out for consultation a proposal to amend the energy legislation to require grid companies to assess whether projects seeking new or increased capacity in the grid are sufficiently mature. The purpose is to help ensure that projects that in fact will be implemented receive the required grid connection and capacity.

RME proposed, on 28 May 2024, further regulatory changes to incentivise faster grid connection of customers.

  • In local distribution grids – To provide a financial benefit to grid companies that deliver increased capacity and connect more customers. The scheme is proposed to be implemented through the revenue regulation and will increase the grid companies’ total income. RME proposes that the scheme should last for up to five years.
  • Higher grid levels – Grid companies should be reimbursed for the costs of early grid studies. This reduces the grid companies’ financial risk in connection with the assessment of grid development. It gives the companies the opportunity to have more “ready-made concepts” when customers request connection.

Nuclear Power

On 21 May 2024, the government announced work on a Norwegian Official Report (NOU) about nuclear power. The government also submitted for public consultation notification of a proposal for a study programme for nuclear power plants in Taftøy Næringspark in Aure and Heim municipalities. The government is committed to establishing a solid foundation of knowledge on nuclear power in Norway. Although this does not currently result in any material changes, this signifies a shift in the government’s policy.

Offshore Wind

Offshore wind is on the move in Norway as the Norwegian Continental Shelf is “going green”. The regulatory framework is still under development: for updated information and the latest news about the Norwegian offshore wind development, see Offshore Wind Insight (haavind.no).

The Norwegian energy sector is unique in several ways, particularly due to its geographical, climatic and legislative characteristics. Some of the distinctive features are as follows.

  • Hydropower dominance– Norway’s energy mix is heavily dominated by hydropower, which accounts for around 87% of domestic electricity production. The country’s topography, with its numerous rivers, waterfalls and mountainous terrain, is ideal for hydropower generation.
  • High share of renewable energy– Norway has one of the highest shares of renewable energy in its total energy consumption in the world, largely thanks to its extensive use of hydropower.
  • Energy export– Norway is not only self-sufficient in terms of energy, but also a significant exporter of electricity, primarily to neighbouring countries such as Sweden, Denmark, Finland, and the Netherlands, through interconnectors.
  • “Europe’s battery”– With its vast hydropower storage capacity, Norway acts as a sort of “green battery” for Europe. It can store excess electricity when demand is low and generate and export electricity when demand is high, thus providing grid stability and storage capacity for the integration of more intermittent renewable energy sources like wind and solar power in the European grid.
  • Public ownership– A significant share of Norway’s energy sector is under public ownership. See more 1.2 Principal State-Owned or Investor-Owned Entities.
  • Offshore wind power– The government has set significant ambitions for offshore wind development. By 2040, the goal is to allocate areas capable of producing 30,000 MW from offshore wind. Currently, offshore wind represents the primary focus for new energy production initiatives in Norway.

The Norwegian Wholesale Electricity Market

Norway’s electricity market is an example of a mature, liberalised energy system that has been evolving since the early 1990s. As a part of the Nordic electricity market, Norway has been at the forefront of market-based energy trading, emphasising efficiency, competition and cross-border integration.

The Energy Act is the principal law governing the structure and function of the wholesale market. REMIT, the EU framework for detecting and deterring wholesale energy abuse, is not implemented into Norwegian law. Many of the regulations that follow from REMIT are, however, implemented through the Energy Act and its Regulations as well as the Nord Pool’s (private law) regulatory framework that prohibits market abuse.

At the heart of Norway’s electricity sector is a market-based trading system. This system is characterised by its high level of hydroelectric power, making the Norwegian market highly renewable and flexible. The unique aspect of Norway’s electricity generation is its capacity to act as a “green battery” for the region, given its ability to quickly adjust production levels from its hydroelectric plants in response to market demands.

Norway’s electricity market is integrated within a broader Nordic electricity market together with Sweden, Finland, and Denmark. The integration extends beyond the Nordics, with Norway connected to the European electricity market through several interconnectors. These connections not only allow for the import and export of electricity but also contribute to the security of supply and the stabilisation of prices through increased market liquidity and competition.

The Nordic integration is facilitated through Nord Pool, which serves as a central hub for electricity trading in the region. The wholesale market in the region consists of several markets where bids are submitted and where prices are determined:

  • the day-ahead market, where electricity prices are determined for the next day;
  • the intraday market, where trading of electricity closer to the time of delivery is done;
  • the balancing markets, where participants in the reserve market trade the power system into balance; and
  • the financial market, where trading in electricity derivatives takes place.

Nord Pool operates a day-ahead market and intraday market. Nord Pool provides the physical trading platform for electricity, where the spot prices are determined. NASDAQ Commodities and EEX offer financial trading instruments that are often based on the prices set at Nord Pool, allowing participants to manage price risk. Almost all physical trading of electricity takes place through Nord Pool; however, bilateral power purchase agreements, especially long-term contracts, are also common. These bilateral agreements often use reference prices set at the power exchanges.

Price Formation

In the Norwegian wholesale electricity market, the price of electricity is determined by the interplay of supply and demand, with a strong emphasis on competitive offers from generators. The Norwegian market is liberalised without heavy regulation or state intervention. Electricity producers submit their offers to the Nord Pool market, specifying how much electricity they are willing to supply and at what price. These offers are typically based on the producers’ operational costs and the availability of resources, such as water levels in reservoirs for hydroelectric plants, which dominate Norway’s energy mix.

On the demand side, retailers, industries and other consumers submit bids indicating how much electricity they are willing to purchase at various price points. Nord Pool’s role is to match these offers and bids and calculate the spot price.

The Norwegian wholesale market consists of five bid zones due to transmission constraints and bottlenecks. Nord Pool therefore calculates zonal prices that reflect local supply and demand. Norway’s extensive interconnection with neighbouring countries helps stabilise prices by allowing excess electricity to be exported or shortages to be mitigated through imports.

Structure of the Wholesale Electricity Market

The participants in the Norwegian wholesale electricity market are generator, suppliers, traders and brokers, large consumers, the Transmission System Operator (Statnett) and Distribution System Operators. These participants participate at Nord Pool, NASDAQ Commodities and/or EEX. The market is divided into five bid zones and is also highly connected to neighbouring countries through several interconnectors.

The Norwegian electricity market is part of the Nordic and European power market. Most of the Norwegian power production comes from hydropower. Norway is a power surplus country, meaning that in a normal year Norway exports power to its neighbouring countries.

Norway’s international electricity interconnectors (all interconnectors) consist of a total of 17 cables, both overland power lines and subsea cables. Norway has a total of seven undersea power cables to other countries. Four of these go to Denmark. These are old and have a much lower capacity than the new “highways” that have been built to the UK and Germany. The total installed capacity of the interconnectors is over 9,000 MW as of 2022, according to the Norwegian Energy Regulatory Authority (NVE-RME). This gives a theoretical potential to transfer approximately 80 TWh/year between Norway and other jurisdictions. Norway has a total theoretical capacity to transfer around 30 TWh/year to countries outside the Nordic countries: the Netherlands, Germany, and the UK.

The division between import and export of electricity to and from Norway varies from year to year based on weather conditions etc. In the period 2003 to 2019, the average annual import was 8.4 TWh, while the annual export was 15.2 TWh. In 2020, there was a lot of precipitation and full power reservoirs in Norway. In total, Norway exported 25 TWh of electricity in 2020 and imported 8 TWh. In 2021, the situation was quite the opposite, especially in southern Norway in the second half of the year. There was little wind and precipitation, extreme gas and coal prices, and a doubling of CO₂ quota prices. Despite lower reservoir levels, power exports increased by 3.4% compared to the previous year.

Power exchange with other jurisdictions is handled by the Norwegian TSO Statnett. Power exchange requires a separate foreign trade licence. There is a joint licence for the Nordic countries, which also covers new connections and capacity increases. The connections to the Netherlands, Germany and the UK each have their own licence. Licences are granted pursuant to the Energy Act.

In 2023, Norway’s total electricity production was 157.8 TWh (installed capacity 40,077 MW). The supply mix was as follows.

  • Hydropower– The average annual production was estimated at 137.3 TWh, of which small power plants account for 12.1 TWh. The installed capacity was 33,852 MW. In 2023, this accounted for about 87% of  total production.
  • Wind power– The average annual production was estimated at 16.9 TWh, installed capacity was 33,852 MW. In 2023, this accounted for about 11% of total production.
  • Thermal power plants– With a production of 3.1 TWh and installed capacity 538 MW, in 2023 this accounted for about 1.96% of total production.
  • Solar power plants (grid connected) – With a production of 0.5 TWh and installed capacity of 604 MV, in 2023 this accounted for about 0.3% of total production.

There are no limits with respect to the percentage of electricity supply controlled by any one entity in the Norwegian electricity supply market. However, Norwegian competition authorities encourage competition amongst the power producers as this is an important mechanism to achieve reasonable pricing for consumers of electricity. Producers compete based on their ability to deliver electricity. To ensure well-functioning competition, it is therefore important that individual players do not have too large a share of the total power production. General competition law, which prohibits anti-competitive behaviour, applies to the electricity market.

Norway has, as of early June 2024, not implemented Regulation (EU) No 1227/2011 on wholesale energy market integrity and transparency (REMIT). As regards the Norwegian implementation work with REMIT, a consultation has been initiated by the Ministry of Energy on 17 March 2023, with a consultation deadline of 28 April 2023. It is not known when REMIT will formally be implemented into Norwegian law (as of June 2024). Even though REMIT is not yet formally implemented, many of the provisions from REMIT are, per se, implemented through the Energy Act and its regulations, as well as through private law regulations in the marketplaces.

Regulation on network regulation and the energy market (“Forskrift om nettregulering og energimarkedet”, or NEM)) contains provisions on market behaviour and transparency in the power market.

NVE-RME is closely integrated with the NVE, which also oversees the physical distribution of power, as well as the neutrality of grid companies. Pursuant to the NEM Regulation, the NVE-RME oversees market behaviour and ensures transparency in the wholesale electricity market, especially concerning the trading of physical power. The NVE-RME may, pursuant to the NEM Regulation, for example:

  • demand the delivery of all data, information and documentation from market participants and the TSO necessary to perform its supervisory function;
  • mandate the immediate cessation of any unlawful activities;
  • issue coercive fines for violations; and
  • also request information and data from the concessionaire of an organised marketplace for physical delivery of electricity, including, but not limited to, information about orders and transactions taking place at that marketplace.

Violations of the Energy Act and NEM Regulation may also lead to criminal liability and can be reported to the prosecuting authorities. NVE-RME may also impose an infringement fee on anyone who intentionally or negligently violates some of the rules in the NEM Regulation.

The financial power market is monitored by the Financial Supervisory Authority of Norway (“Finanstilsynet”), which ensures compliance with financial market regulations. This includes EU financial market regulations, such as MiFID II and MAR. The Financial Supervisory Authority’s supervisory powers are similar to those of NVE-RME, allowing it to effectively monitor financial activities. Additionally, the Norwegian Competition Authority has an overarching responsibility to ensure effective competition, including in the power market, and has a broad range of powers to enforce the Competition Act. Meanwhile, the Consumer Authority is responsible for regulating aspects related to the sale and marketing of energy to consumers. In addition, private law regulations prohibiting market manipulation and insider trading apply to participants in the marketplaces for power trading.

The principal laws that govern the construction and operation of generation facilities are as follows.

The Waterfall Rights Act (“Vannfallrettighetsloven”)

The developer must have the proprietary rights to the waterfalls used in energy production. For others than the state, a licence is required for the acquisition of such rights. The Act does not apply to small-scale hydropower.

Licences under the Waterfall Rights Act can only be granted to public entities. Public entities cover Norwegian municipal, county or state corporations, and companies in which such corporations hold at least two thirds of both the capital and the voting rights, provided that such companies are clearly publicly owned. Private companies may possess proprietary rights in such companies up to one third of the shares.

Leases of hydropower plants subject to licensing under the Waterfall Rights Act are regulated in the more detailed Regulations on the Lease of Hydropower Plants Act. The regulations lay down certain requirements for the content of the agreements. Agreements must be approved by the Ministry of Energy.

The Water Resources Act (“Vannressursloven”)

The purpose of the Act is to ensure socially responsible use and management of watercourses and groundwater. Small-scale hydropower plants, not covered by the Watercourse Regulation Act, may need a licence under the Water Resources Act. There are no ownership restrictions.

The Watercourse Regulation Act (“Vassdragsreguleringsloven”)

When a regulation or transfer of water increases the quantity of natural horsepower in one or more waterfalls affected by 500 natural horsepower or more, or in the river system as a whole by 3,000 natural horsepower or more, or if the regulation affects the environment or public interests to considerable extent, a licence pursuant to the Watercourse Regulation Act is required.

The Energy Act (“Energiloven”)

The Energy Act establishes the framework for how electricity supply is organised. The purpose of the Energy Act is (see Section 1-2) to ensure that the production, conversion, transmission, sale, distribution and use of energy is carried out in a societal, rational manner, considering the public and private interests affected. The building, owning and operating of electrical facilities (including generators, transformers and transmission lines) requires a licence pursuant to the Energy Act.

The Planning and Building Act (“Plan- og bygningsloven”)

Following legislative amendments to the Act in 2023, a local planning decision is required for onshore wind plants. See further 1.6 Recent Changes in Law or Regulation. This does not apply for other generation facilities.

The Expropriation Act and the Expropriation Compensation Act

(“Oreigningslova” and “Ekspropriasjonserstatningsloven”)

All developers need to get hold of necessary rights to conduct their projects, such as land use and waterfall right. Should such rights not be obtained through agreements, the company may apply for a permission to expropriate. Expropriation is regulated in the Expropriation Act. Measuring of compensation for acquiring such rights is subject to the Expropriation Compensation Act.

The Offshore Energy Act (“Havenergiloven”)

The Act governs offshore renewable energy production. Offshore renewable energy production requires that:

  • an area is opened for offshore wind by the Norwegian government;
  • a company is exclusively awarded an area for offshore wind development; and
  • the company is awarded a licence and a detail plan for offshore wind production according to the Offshore Energy Act.

The Application Process

The licence process starts with a notification to the NVE. The Planning and Building Act requires an environmental impact assessment (EIA) to be conducted if a project may have significant effects on the environment. The purpose of the EIA is to ensure that all possible effects of the project are taken into account during the preparation of plans and measures. Wind power plants exceeding 10 MW and hydropower plants with an annual production of 40 GWh or more, always require an EIA.

In the notification, the developer describes the technical plans and the effects known at the time of notification. The NVE will submit the notification to affected parties for consultation, including local municipalities.

When the licence application is prepared, it is submitted to affected parties for consultation. In order to be granted a licence, the advantages of the project to society must outweigh the disadvantages.

For large hydropower, NVE submits a recommendation to the Ministry of Energy. The NVE’s recommendation is subject to a (limited) consultation before the Ministry presents the case before the Royal Council, which makes the final decision. Projects that comprise more than 20,000 natural horsepower, or projects that are considered particularly controversial, must be handled by the National Assembly before the Royal Council makes the (formal) decision.

The NVE has the authority to grant licences for installations according to the Energy Act, such as onshore wind plants and solar power plants. Prior to the NVE’s handling of a licence application on an onshore wind power plant project, a positive local planning decision from the local municipality according to the Planning and Building Act is needed. This does not apply to any other power plants. The local planning decision follows the procedures according to the Planning and Building Act. A licence decision made by the NVE can be appealed to the Ministry of Energy, which makes the final decision.

For smaller hydropower, ie plants with less than 10 MW installed capacity and limited regulation, the licensing procedures are simplified. After receiving a licence application, the NVE sends out a consultation letter to affected parties. In order to be granted a licence, the advantages must outweigh the disadvantages. The decision from the NVE may be appealed to the Ministry, which in turn makes the final decision.

Typical Terms and Conditions

A licence for acquisition of waterfall rights (see the Waterfall Rights Act) typically includes conditions on licence fees and mandatory sales of power to the municipalities where the waterfalls are located.

Licences granted under the Watercourse Regulation Act contain manoeuvring regulations that establish parameters for water levels and releases. These include detailed provisions regarding the control mechanisms and procedures for reservoir drainage. Conditions stipulating minimum water flow in rivers and streams are determined based on a targeted assessment. Further, requirements for establishing a business development fund within the municipality where the development occurs may be imposed. The licences also contain conditions of licence fees and mandatory sales of power to municipalities.

Licences under the Water Resources Act and the Energy Act also state conditions and rules of operation. These conditions may include measures to secure a rational energy supply from the plant, provisions on the timing of initiation, construction, technical operations, terms of exploitation of the individual work, and conditions aiming at preventing or minimising damage to natural and cultural heritage. Individually adapted measures and conditions may be imposed if considered necessary.

The Process to Obtain an Amendment or Relaxation of a Term/Condition

The process is as follows.

  • The Energy Act– In special cases, the stipulated conditions may be changed for reasons of public interest. Consideration shall be given to the costs a change will impose on the licensee and the advantages and disadvantages the change will otherwise entail. Amendments to the terms and conditions may also be made upon application by the licensee.
  • The Waterfall Regulation Act– Upon application from the owner of the watercourse facility, the authorities can amend the conditions of a licence under the Act or previous legislation on watercourse regulations. An application for the alteration of previously determined conditions regarding time limitation and reversion shall be granted if the owner of the regulation facility meets the conditions of public ownership.
  • Waterfall Rights Act– Upon application from the owner of the watercourse facility, the authorities can amend the conditions of a licence.

The process to obtain an amendment or relaxation in licences under regulations mentioned above follows the normal licence application procedures, as far as deemed necessary.

Eminent domain, condemnation or expropriation constitute interference with the right to property. Therefore, the proponent, in lack of an agreement, must apply for expropriation to the authorities. The authorities may only grant the approval if the legal conditions outlined in the Expropriation Act are met; the benefits of expropriation must outweigh the drawbacks.

The application for expropriation is typically submitted alongside the application for a construction and operation licence. The NVE or the Ministry of Energy will evaluate both the application for expropriation and licence application simultaneously.

Every individual or entity subject to expropriation, has a constitutional right to compensation. If an agreed-upon compensation cannot be reached, the compensation will be determined through a specific type of court proceedings. The compensation shall comprise the relinquishment of both the construction and operational work, as well as potential damage or inconvenience on remaining properties. In accordance with the Expropriation Compensation Act, the compensation is determined based on the higher value between the selling price and the service value.

In the case of rights holders being subject to expropriation, such as reindeer gazing districts, the compensation is determined based on the loss suffered, which typically includes factors such as production loss and increased workload.

Hydropower Plants

If the state does not wish to take over a regulation facility regulated by the Water Regulation Act, at the end of the licence period, and no new regulation licence is granted, the owner is obliged by order of the Ministry to remove the facility within a deadline set by the Ministry.

An owner of a watercourse facility regulated by the Water Resources Act has a duty of maintenance and responsibility for safety until the facility is shut down. The decommissioning of a watercourse facility is subject to licensing if it may cause significant damage or inconvenience to public interests. Decommissioning in any other way than removing the entire facility, is always subject to licensing.

Onshore Wind and Solar Power

A wind power plant has a limited lifespan and must be decommissioned when the licence expires. The licence holder must fund the decommissioning. The NVE requires the licensee to submit a proposal for financial security by the end of the twelfth year of the plant’s operation. The security must cover the costs of decommissioning to ensure that society is guaranteed available funds to decommission the power plant. The same conditions apply to solar power plants licences (see licence conditions).

The Norwegian grid system consists of three levels:

  • the transmission grid;
  • the regional distribution grid; and
  • the local distribution grid.

The principal laws that govern the ownership, construction and operation of transmission lines and associated facilities are the Energy Act and the Offshore Energy Act. Additionally, there are supplementary regulations that comprehensively regulate the system based on these legal acts.

The transmission grid is a nationwide system that connects consumers and producers across state borders. According to the Energy Act, only the appointed transmission system operator (TSO) can own and operate the transmission lines and associated facilities. Statnett is the TSO in Norway.

To construct and operate a specified installation, the Energy Act states that a licence from the authorities is necessary. This requirement stems from the fact that the electricity grid constitutes a natural monopoly. The licensing process aims to prevent exploitation of the monopoly position and ensure rational development and utilisation of the transmission system in the best interests of society.

When applying for a construction and operation licence, Statnett is required to review the consequences of the construction work and the operation of the power lines and associated facilities, such as transformation stations. Environmental impact assessments (EIAs) play a crucial role in these evaluations. Furthermore, the authorities attach significant importance to the environmental impacts when reviewing an application.

The regulatory process for obtaining the necessary licence for the construction and operation of transmission lines and associated facilities is both time-consuming and comprehensive. It requires, among other things, thorough assessments of environmental impacts (EIA) and public participation and input to the impact assessment and the approval process. The process may be summarised as follows.

  • Statnett notifies NVE of the project and submits a proposal for an EIA programme.
  • A mandatory public consultation on the notification and the proposed EIA is conducted.
  • The NVE establishes an EIA programme.
  • Statnett carries out the EIA programme and provides a comprehensive EIA report.
  • An application for a licence is filed along with the EIA report.
  • A mandatory public consultation on the licence application and the EIA report is conducted.
  • The NVE processes the licence application.
    1. If power lines are below 300 kV or shorter than 20 km, NVE may decide whether to grant the licence or not.
    2. For power lines exceeding these limits, NVE will process the application and provide a recommendation to the Ministry of Energy. The King in Council decides on the application.

When granting a licence to construct and operate a transmission line and associated facilities, the authorities normally impose various terms and conditions. Typical terms and conditions include the following.

  • An obligation to apply for licence renewal within a specified timeframe before its expiration date.
  • A requirement to complete construction, commissioning and put the power lines and associated facilities into operation within a specified timeframe.
  • Being acquainted with the relevant rules and regulations.
  • Responsibility for decommissioning the facilities after being granted permission by the NVE.
  • The authorities may withdraw the licence if Statnett fails to fulfil the obligations set forth in the licence.
  • Various requirements aimed at preventing or limiting negative environmental impacts, hereinunder impacts on cultural heritage.

The authorities may add additional terms and conditions to the approval at a later stage if deemed necessary due to fundamental interests.

The TSO, Statnett, may apply for an amendment or relaxation of a term or condition. The general rule is that the ordinary process for obtaining an approval, as described in 4.1 Regulation of Construction and Operation of Transmission Lines and Associated Facilities and 4.2 Obtaining Approvals for the Construction and Operation of Transmission Lines and Associated Facilities, must be followed. However, if the amendments or relaxation requested are considered minor, the authorities may simplify the process.

Eminent domain, condemnation or expropriation rights are necessary for a proponent to undertake the construction and operation of electricity distribution facilities. The process and methodology for compensating affected property owners and rights-holders are equivalent to those described in 3.4 Eminent Domain, Condemnation or Expropriation Rights.

In Norway, there is only one TSO, Statnett, which is wholly owned by the state. Statnett holds the exclusive right to construct, own and operate the transmission grid, hereinunder provide transmission services. In addition to obtaining a licence, as described in 4.1 Regulation of Construction and Operation of Transmission Lines and Associated Facilities and 4.2 Obtaining Approvals for the Construction and Operation of Transmission Lines and Associated Facilities, Statnett must comply with the regulations in the Public Procurement Act and the Public Procurement Regulation.

Considering the inherent nature of the transmission grid as a natural monopoly, the transmission charges and terms of service are thoroughly regulated. The NVE-RME sets an annual revenue cap for Statnett. The cap is determined so that the generated income over time covers the operational and amortisation costs of the installations, while also allowing for a reasonable return on investments given efficient operation, utilisation and development of the grid system. Further, Statnett is obligated to provide all services on non-discriminatory conditions and in an objective manner, ensuring equal treatment for all parties involved.

Since the ability to own and operate the transmission grid is exclusively held by Statnett as the TSO, all grid services must be offered on non-discriminatory conditions and an objective basis. Consequently, Statnett is legally obliged to provide transmission services to all parties requesting transmission services within the legal framework for such services. This obligation includes, but is not limited to, an obligation to invest in transmission facilities necessary to accommodate the requests.

As set out in 4.1 Regulation of Construction and Operation of Transmission Lines and Associated Facilities, the Norwegian electricity grid system is structured into three levels. The principal laws that govern the construction and operation of electric distribution facilities are the Energy Act and the regulations derived from it, hereinunder the Energy Act Regulation.

To construct and operate electric distribution facilities, the grid company must possess one out of two types of grid licences, and the licence must comprise the relevant installations.

The first type of licence is a general local area licence. Holding such a licence eliminates the need for individual approvals for each installation within the designated area. A general local area licence only applies to installations of 22 kV or lower.

The second type of licence is a licence to construct and operate specified electricity distribution facilities that are not covered by a general local area licence.

The regulatory process for obtaining these licences is similar to the application process for the transmission grid, as described in 4.2 Obtaining Approvals for the Construction and Operation of Transmission Lines and Associated Facilities: the public is invited to participate and give input at several stages of the process, and the grid company is obligated to conduct a comprehensive Environmental Impact Assessment (EIA).

Applications are submitted to the NVE. If the installations are lower than 300 kV or shorter than 20 km, the NVE may process the application. However, for installations exceeding these limits, the NVE provides a recommendation to the Ministry of Energy. The Ministry of Energy processes the application before the King in Council makes the decision.

The timeline for obtaining the necessary licences varies depending on factors such as the magnitude of the installations, the impacted areas and interests, and the thoroughness of the application and the EIA. Consequently, the timeline can range from a few months to several years.

The typical terms and conditions imposed in approvals to construct and operate electric distribution facilities are equivalent to those imposed for transmission grid licences (see 4.3 Terms and Conditions Imposed on Approvals to Construct and Operate a Transmission Line and Associated Facilities).

Eminent domain, condemnation or expropriation rights are necessary for a proponent to undertake the construction and operation of electricity distribution facilities. The process and methodology for compensating affected property owners and rights-holders are equivalent to those described in 3.4 Eminent Domain, Condemnation or Expropriation Rights.

Electricity distribution entities possess, through a licence, exclusive rights to provide distribution services within specified geographical areas. The reasoning is that the electricity distribution grid constitutes a natural monopoly, as construction and operation of multiple power lines and facilities within the same area, along with competition among the relevant distribution entities, would be inefficient.

Charges and terms of service for the electricity distribution system are regulated and established by the same provisions as for the transmission system (see 4.6 Transmission Charges and Terms of Service).

Each distribution entity is assigned an annual revenue cap, which is determined individually by the NVE-RME. The revenue cap decision may be appealed to the Energy Complaints Board.

The distribution entities set the charges consumers must pay for grid system connection. While these charges may vary among entities due to geographical, technical and operational differences, they must be objective and offered under non-discriminatory conditions.

The NVE-RME supervises and enforces compliance with the regulations. It has the authority to issue orders for compliance and impose sanctions, ie, in cases of discriminatory service conditions. Decisions made by RME-NVE may be appealed to the Energy Complaints Board.

General terms and conditions set in legislation are not subject to appeal, and can only be amended through the regular legislative process.

Advokatfirmaet Haavind AS

Postboks 359 Sentrum
0101 Oslo
Norway

+47 22 43 30 00

post@haavind.no www.haavind.no/
Author Business Card

Trends and Developments


Authors



Advokatfirmaet Haavind AS is one of Norway’s leading full-service law firms, with 165 lawyers in total and offices in Oslo and Svalbard. Teams are organised by sector and specialisation as a means of positioning the firm to create added value for customers. The firm’s industry sector focus is particularly directed to renewable energy, construction, real estate, technology, fisheries and aquaculture, and offshore and industry. Haavind’s energy practice, recognised as one of the strongest in the electricity and renewables sector, counts 12 dedicated lawyers who, strongly supported by collaboration with specialised teams focusing on the offshore sector and new energy technologies, advise the largest and most important players in the renewables sector. The team’s lawyers cover every legal aspect of the sector, including regulatory matters, M&A and dispute resolution, and are currently involved in the majority of the largest production (especially hydro and wind) and grid projects.

Introduction

The Norwegian power sector is, in general, highly regulated – particularly when it comes to hydropower activity, which has more than 100 years of history and still forms the backbone of Norway’s power system. Overall, Norway has stable legal frameworks. This is clearly one of the reasons why there have been so many foreign investments within the Norwegian power sector in the past.

For the most part, foreign investors can invest in the Norwegian power sector without specific restrictions – at least when it comes to investments in wind power, small-scale hydropower, grid companies, district heating and other infrastructure relating to the power sector. The main exception to this concerns large hydropower, where non-public entities (including foreign entities) are not allowed to invest in and own more than one third of a company that owns such assets. Public entities, being allowed to own such assets, are defined as entities owned and controlled by public authorities and/or undertakings by at least two thirds.

One important aspect of Norwegian hydropower is that it – to a large extent – is a flexible production method, as it can be stored using water reservoirs. More than 75% of Norwegian hydropower production is flexible through the use of reservoirs, which represent half of Europe’s total reservoir storage capacity. This is a perfect counterbalance to the increasing amount of non-flexible production such as wind power and solar power.

Back in 2021, Norway’s former government issued a White Paper on the long-term value creation from Norwegian energy resources, including – for the first time – both the renewables sector and the oil and gas sector. The White Paper points out that the Norwegian oil and gas industry currently faces major challenges as a result of maturing fields on the Norwegian continental shelf and increasing demands for lower emissions. However, it is emphasised that the oil and gas sector will remain a significant factor in the Norwegian economy in the years to come – albeit not on the current scale. The use of expertise and technology within today’s oil and gas sector to develop new “green” industries and technologies is also an important goal for the Norwegian government, exemplified by the current development of offshore wind power on the Norwegian continental shelf.

The power situation in Norway and nearby markets has become more challenging in recent years, largely due to Russia’s invasion of Ukraine. To ensure security of supply, facilitate energy transition and green industry, the government aims to increase renewable energy production, strengthen the grid and improve energy efficiency. One of the government’s main goals (see the National Budget for 2024) is to continue implementing the green transition and take action to achieve climate goals.

Offshore Wind

In terms of developments, offshore wind is and will continue to be the main focus of attention in Norway. The Offshore Energy Act allows companies to apply for a licence to develop projects in appointed areas. Offshore renewable energy production requires that:

  • an area is opened for offshore wind by the government;
  • a company is exclusively awarded an area for offshore wind development; and
  • the company is awarded a licence and a detail plan for offshore wind production according to the Offshore Energy Act.

The government has appointed the current transmission system operator (TSO) for the Norwegian mainland, Statnett SF, as the TSO for the future grid infrastructure on the Norwegian continental shelf as well. The government has also announced that grid costs related to this future offshore grid will be carried by licensees rather than onshore grid customers.

The current tax regime does not regulate offshore wind specifically, which means that Norwegian companies will be liable to tax in accordance with the general tax rules. On 21 February 2022, the Ministry of Finance proposed a change in the Norwegian Tax Act, widening Norway’s taxation right on the Norwegian continental shelf to also cover foreign companies’ income from production of energy from renewable resources, including offshore wind. The new rules entered into force from 2024, implying that foreign companies generally will become subject to the same tax rules as Norwegian companies.

A “super-profit tax”, also called a “ground rent tax” or “resource rent tax” was introduced for onshore wind with effect from 2023. The current government has stated that it has no intention of introducing any similar tax on offshore wind. (Read more about taxation and financing here: Finance, tax & support schemes - Offshore Wind Insight (haavind.no).)

On 29 March 2023, the government announced the launch of the long-awaited tenders for the first project phase of offshore wind power development in the Utsira North (UN) and Southern North Sea II (SN II) areas. SN II is a bottom-fixed offshore wind project, while UN is a floating project. Both projects will be radially connected to the onshore grid.

Southern North Sea II

SN II’s first project phase will have a maximum developed capacity of 1,500 MW. A monetary auction with pre-qualified applicants was held on 29 March 2024. Ventyr SN II AS, owned by Parkwind and the Ingka Group, won the auction and will be the first to develop offshore wind in Southern North Sea II. The winning bid in the auction was NOK 115 cents/kWh, this forming part of the Contract for Difference (CfD) that later was entered into between Ventyr SN II AS and the Norwegian State on 19 April 2024.

Utsira North

The UN area is divided into three sub-areas, each consisting of 500 MW. The UN project is planned to be awarded through a qualitative competition according to a two-step model in which:

  • the three sub-areas are awarded based on qualitative criteria (the scheduled award initially by the end of 2023, but postponed due to delays in obtaining state aid approval from the EFTA Surveillance Authority); and
  • the companies that have been awarded the three sub-areas will compete for support schemes as part of the further licensing process, and where only two of the projects will be entitled to support.

The Ministry of Energy sent a proposal for a support scheme for UN on public consultation late June 2024.

New offshore wind areas

New areas are expected to be awarded for offshore wind development in 2025 and then regularly going forward. In a report published on 25 April 2023, the Norwegian Water Resources and Energy Directorate (NVE) pointed out several suitable areas for offshore wind.

On 14 September 2023, the government stated that new areas for offshore wind will be opened by 2025. These are the areas Sørvest F and Vestavind F, which are expansions of the initial areas at Sørlige Nordsjø II and Utsira Nord respectively, as well as a new area called “Vestavind B”.

The Norwegian government aims for the SN II and UN projects to enter into operation by 2030 and aims to allocate licences for the production of a further 30,000 MW of offshore wind power by 2040, which is equivalent to Norway’s current total power production.

HSE-regulation

The Ocean Industry Authority (“Havindustritilsynet”) has published a proposal for a new health, safety and environment at work (HSE) regulation covering offshore wind. The proposal was subject to a public consultation, with deadline 1 March 2024. The consulted parties have pointed out deficiencies in the proposal, specifically the lack of comprehensive evaluations concerning the necessity for sector-specific regulation beyond the general Health, Safety, and Environment (HSE). As of June 2024, the future actions of the authorities remain uncertain.

Further information on Norway’s offshore wind production can be found on Haavind’s Offshore Wind Insight portal, which publishes the latest news within the field of Norwegian offshore wind development: Offshore Wind Insight (haavind.no).

Onshore Wind

Changes in the licensing system

As of July 2023, the Energy Act and the Planning and Building Act were amended with an aim of improving the licensing process for onshore wind projects. Prior to NVE concluding on a licence application pursuant to the Energy Act, an onshore wind project will need a positive local planning decision from the local municipality according to the Planning and Building Act that allocates the planning area for onshore wind. The objective is to strengthen the role of municipalities in the licensing process for onshore wind, to reduce the level of conflict, and thereby laying the foundation for further expansion of onshore wind power, including strengthening the power balance and achieving national climate goals. 

The Norwegian government has furthermore, in an attempt to accelerate the processing time of onshore wind projects, adopted new criteria for NVE’s handling of licence applications for onshore wind. According to the new criteria, large onshore wind projects, projects with approved zoning plans in the local municipality and onshore wind projects in Finnmark (the northern parts of Norway) will be prioritised. Additionally, licence applications containing documentation of involvement from reindeer husbandry in the assessments and an agreement on mitigating and compensating measures, will (where relevant) be prioritised in the licensing process over applications lacking proper documentation of these aspects.

Increase in the number of disputes brought before the courts

The onshore wind sector has been facing increasingly frequent litigation, triggered by a growing political opposition to wind power in general. In the authors’ experience, however, few actual delays to wind power development have been caused by legal action.

Nonetheless, the battle over the validity of wind power licences has made its way into the courtroom. In addition to the growing opposition to wind power, there has been a sharp uptick in the number of validity disputes since 2019. Several cases have reached the appellate courts and even the Supreme Court. One of the cases the Supreme Court handled in the autumn of 2022 concerned Fosen wind farm which affects reindeer husbandry. The Supreme Court concluded in this case that the reindeer herders’ right to practise their culture was violated, and that the licence for the project – over time – would be invalid due to this. For this reason, the ruling on the determination of compensation for the interference was denied. Following the Supreme Court’s conclusion, there has been a growing number of protests and disputes from Sámi people against new renewable energy projects and the Fosen case in particular.

The Fosen case was later settled through amicable agreements reached between the reindeer grazing districts and the developer in December 2023 and March 2024. The wind turbines will remain, and compensation will be paid to the reindeer grazing districts. Furthermore, these agreements are designed to support ongoing reindeer husbandry, alleviate operational challenges, and lay the groundwork for sustaining cultural practices from a generational perspective.

Despite the apparent increased willingness to oppose energy projects in court with reference to the Fosen case, the majority of disputes are still resolved amicably.

Changes to the taxation of wind power

A production tax for onshore wind came into force in 2022. The tax is applicable to all onshore wind power farms that require a facility licence pursuant to the Energy Act. The tax is based on production and all producers must in 2024 pay NOK 2.3 cents per kWh.

The production tax is paid to the Norwegian state but is routed to municipalities hosting the wind farms. The tax is applicable to both existing and new wind power plants. The production tax came in response to requests from many stakeholders (including the wind power industry itself), to help increase local acceptance of the projects.

In addition to the production tax, a “ground rent tax” – also called a “resource rent tax” – was introduced with effect from 1 January 2024. The ground rent tax is presented as an investor-neutral cash-flow tax on “super-profits”. Neutrality shall be achieved by the state covering a share of capex equal to the tax rate. For greenfield projects, neutrality shall be obtained by full tax-deduction of capex in the year of investment and the state paying out the tax value of it upon production start.

No payout is available to already existing power plants (brownfield) related to historic capex. However, taxpayers are entitled to a “recapture” of tax depreciations, which includes compensatory interest (“venterente” or “waiting interest”). This interest is added to the balance of tax depreciation and to tax-loss carried forward. The government asserts that such “waiting interest”, despite being calculated at a risk-free rate, offers an “equivalent present value” compared to a direct payout of the tax value.

From 2024, onshore wind power is subject to the ground rent tax at 25%, the production tax at NOK 2.3 cents per kWh and ordinary income tax at 22%. (Read more about the taxation of onshore wind here.)

Hydropower

Even though the vast majority of Norway’s hydropower potential has already been utilised, the NVE calculated in 2020 that the remaining hydropower potential was 23 TWh. Notwithstanding the potential for new builds, it is becoming increasingly important to upgrade existing hydropower plants – as not only is this crucial in order to increase hydropower production in the energy mix, but also to maintain the level of production capacity in existing plants.

The higher electricity prices and the general energy crisis in Europe have led to several companies reassessing possible investments in projects that were shelved in recent decades.

However, the Norwegian government introduced sudden changes to the regulatory framework for hydropower by increasing the resource rent taxation on hydropower from 37% to 45%, with effect from the income year 2022.

At the same time the government also introduced an extra taxation on hydropower – the “high price taxation” (“høyprisbidraget”). The government stated that the high price taxation was due to the extraordinarily high energy prices in Europe. The high price taxation was removed with effect from 1 October 2023. The resource rent taxation on hydropower is still 45% in 2024. The taxation applies to plants with generators of at least 10 MVA.

Another issue relating to hydropower in Norway has been the discussion surrounding the impacts of the taxonomy emerging from the EU’s Green Deal. In the initial discussion of consequences for the hydropower industry, concerns were raised regarding the risk of Norwegian hydropower being classified as non-sustainable and therefore less eligible for access to capital – partly owing to criteria being based on experience from hydropower development in other countries that are not necessarily relevant to how this business is conducted in Norway.

A key factor here is the link to the EU’s Water Framework Directive, which will contribute to improving the environmental conditions of watercourses throughout Europe. Following a consultation process in which Norway was awarded the opportunity to comment on the impact of suggested criteria for categorisation, the criteria – although far from perfect – now seem to be at a level that Norwegian hydropower players overall find acceptable.

Grid

Grid connection

In recent years, there has been a significant increase in demand for grid connection. This is partly due to the transition to a low-emission society, increased electrification and the establishment of new power-intensive industries.

In April 2023, the government presented a plan for faster grid development and better utilisation of the grid (see the National Official Report (NOU) “Grid on time”). The plan aims to speed up the processing of licences by the energy authorities, more efficient connection to the electricity grid and better utilisation of current grid capacity.

On 7 May 2024, the Ministry of Energy proposed amendments in the Regulation on Network regulation and the Energy Market, to ensure better use of the grid capacity. The Ministry proposes that the grid companies shall be required to take the project’s maturity into account when assessing requests for connection and increased capacity above 1 MW. The deadline for the public consultation has been set to 7 August 2024.

The Norwegian Energy Regulatory Authority (RME) proposed, on 28 May 2024, further regulatory changes to incentivise faster grid connection of customers.

  • In local distribution grids – The objective is to offer financial incentives to grid companies that enhance capacity and connect additional customers. This is proposed to be managed through revenue regulation, which boosts the industry’s overall income. RME suggests that this scheme should continue for up to five years.
  • At higher grid levels – It is proposed that grid companies shall be compensated for the costs incurred during preliminary grid studies. This compensation reduces the financial risks associated with evaluating grid development.

Further unbundling requirements

On 24 March 2023, the Norwegian government sent a proposition to Parliament concerning changes to the Energy Act that would raise the threshold for the legal unbundling of distribution system operators to a minimum of 100,000 grid customers. The changes to the unbundling requirements were passed in Parliament in June 2023, and put into force on 1 July 2023.

Interconnectors

Through its hydropower reservoirs, Norway manages approximately half of Europe’s regulation capacity. As the energy mix becomes increasingly non-regulated as a result of the addition of wind and solar power, the need for – and the commercial aspect of – regulated hydropower is ever-more important.

With existing and forthcoming interconnectors between Norway, other Nordic countries and the UK, Norway exchanges both power and regulation capacity. Given this structural position, it has been postulated that Norway can act as “Europe’s green battery” – much to the excitement of some stakeholders in Norway and the concern of others. As seen with the proposed NorthConnect project between Norway and Scotland (capacity of 1,400 MW), the export of power remains a hotly contested political issue and the government decided to reject the licence application for this project on 16 March 2023.

One of the key issues behind the political debate is the idea that Norway’s power-intensive industry and consumers benefit at large from Norway’s low electricity prices, in comparison with other European countries.

After some political back-and-forth, Statnett SF – the current Norwegian transmission system operator for the Norwegian mainland – has been granted the exclusive right to own and operate all interconnectors.

New Technologies and Innovation

Further digitalisation of the power sector

Digital innovations in the power sector are consistently enhancing operational efficiency, system maintenance, power supply reliability, and preparedness. The advancement of digitalisation and the acquisition of higher-quality data not only refine the evidence base for investment decisions but also facilitate the automation of numerous decision-making processes. This shift necessitates the development of new regulations, business models, and adaptations by customers. A prime example of this is the widespread implementation of smart metering, which has led to the installation of new equipment in approximately 99% of all metering points across Norway.

Hydrogen

The Norwegian government is actively working with its national hydrogen strategy, focusing on subsidising new hydrogen technology and initiatives. In the short term (ie, by 2025), the government – in co-operation with private stakeholders – wishes to:

  • encourage the establishment of five hydrogen maritime hubs;
  • establish one or two industrial production projects; and
  • establish five to ten pilot projects for the development and demonstration of new and more cost-effective hydrogen solutions and technologies.

In the medium term (ie, by 2030), the Norwegian government’s ambition is that hydrogen will be established as a real alternative within the maritime sector, with prospects of market-based developments. By 2050, the goal is to have established a market for the production and consumption of hydrogen. In terms of the EU’s environmental goals towards zero carbon emissions and its focus on hydrogen, Norway’s structural advantage within green hydrogen based on renewable energy production may be particularly beneficial.

Norway is specifically looking at how to utilise hydrogen to cut the country’s second-largest emission producer, the transport sector. Its aim is to halve the current emissions from the transport sector and maritime transport by 2030. Hydrogen will be an important factor in achieving this goal.

Carbon capture and storage

The government’s carbon capture and storage efforts (CCS) are still to a large extent focused around the “Longship” project. Longship is a full-scale CCS demonstration project, which encompasses carbon capture from Norcem’s cement factory (400,000 tonnes of CO₂ per year).

Through the Longship project, Norway anticipates that carbon removal will facilitate a reduction of emissions exceeding 1 million tons between 2025 and 2030. Concurrently, the European Commission’s proposed revisions to the accounting of “negative emissions” within the EU Effort Sharing Agreement (the ESR) may lead to the exclusion of carbon removal contributions from Norway’s targets under the ESR framework.

Despite the prevailing uncertainties, the Norwegian Ministry of Energy has declared the opening of two new areas in the North Sea for CO₂ injection and storage applications. The Norwegian government is committed to enabling the socio-economically viable sequestration of CO₂. In response, various bidders are actively participating in the continuous development of CCS initiatives on the Norwegian continental shelf.

Concluding Remarks

The Norwegian energy sector is developing fast, with increasingly blurred lines between the traditional power/electricity sector and the oil and gas sector. This development is driven by strong political goals of both further electrification (including of oil and gas installations) and also developing new and profitable industries such as (floating) offshore wind, hydrogen and CCS as part of the necessary transition of Norway’s oil and gas industry. Norway has considerable ambitions within these new industries. The high electricity prices the recent years, combined with the energy crisis in Europe, are also contributing to even faster development and more investments.

The European shift from dependency on Russian gas has significantly accelerated the investments and timeline for the transition to renewable energy in Europe (see the EU’s RePowerEU plan from 2022). The US Inflation Reduction Act (IRA) on 16 August 2022 has sped up the US shift towards renewable energy. The EU responded to the IRA with its “Green Deal Industry Plan” on 1 February 2023. The Green Deal Industry Plan included a softening of state aid rules until the end of 2025, making it easier for EU and EEA states to provide support schemes for renewable projects.

Altogether, there are strong indications that the development that is unfolding today will be further strengthened in the years to come.

Advokatfirmaet Haavind AS

Postboks 359 Sentrum
0101 Oslo
Norway

+47 224 330 00

post@haavind.no www.haavind.no/
Author Business Card

Law and Practice

Authors



Advokatfirmaet Haavind AS is one of Norway’s leading full-service law firms, with 165 lawyers in total and offices in Oslo and Svalbard. Teams are organised by sector and specialisation as a means of positioning the firm to create added value for customers. The firm’s industry sector focus is particularly directed to renewable energy, construction, real estate, technology, fisheries and aquaculture, and offshore and industry. Haavind’s energy practice, recognised as one of the strongest in the electricity and renewables sector, counts 12 dedicated lawyers who, strongly supported by collaboration with specialised teams focusing on the offshore sector and new energy technologies, advise the largest and most important players in the renewables sector. The team’s lawyers cover every legal aspect of the sector, including regulatory matters, M&A and dispute resolution, and are currently involved in the majority of the largest production (especially hydro and wind) and grid projects.

Trends and Developments

Authors



Advokatfirmaet Haavind AS is one of Norway’s leading full-service law firms, with 165 lawyers in total and offices in Oslo and Svalbard. Teams are organised by sector and specialisation as a means of positioning the firm to create added value for customers. The firm’s industry sector focus is particularly directed to renewable energy, construction, real estate, technology, fisheries and aquaculture, and offshore and industry. Haavind’s energy practice, recognised as one of the strongest in the electricity and renewables sector, counts 12 dedicated lawyers who, strongly supported by collaboration with specialised teams focusing on the offshore sector and new energy technologies, advise the largest and most important players in the renewables sector. The team’s lawyers cover every legal aspect of the sector, including regulatory matters, M&A and dispute resolution, and are currently involved in the majority of the largest production (especially hydro and wind) and grid projects.

Compare law and practice by selecting locations and topic(s)

{{searchBoxHeader}}

Select Topic(s)

loading ...
{{topic.title}}

Please select at least one chapter and one topic to use the compare functionality.