Power Generation, Transmission & Distribution 2025

Last Updated July 17, 2025

Mexico

Law and Practice

Authors



Cortés Quesada Abogados, S.C. is a Mexico City-based law firm specialising in the energy, infrastructure and sustainability sectors. Serving both international and domestic clients, the firm delivers innovative, strategic legal advice grounded in international best practices, with a strong focus on business-oriented solutions. Leveraging the extensive expertise of its team, Cortés Quesada combines deep sector knowledge with the capabilities of a full-service law firm, providing comprehensive legal support across diverse industries within the Mexican market, offering a truly comprehensive service for international and local clients. The firm has a proven track record in representing energy producers, marketers and key off-takers of energy products in Mexico in a broad range of transactions, for the development, construction and/or operational phases of their projects. Currently, the firm is led by two partners and supported by a dedicated team of more than ten associates and paralegals.

The Mexican power sector is open for (limited) private participation in specific areas, namely generation, storage and marketing activities. In contrast, transmission and distribution are exclusively reserved to the Mexican State.

The sector underwent significant transformation in 2024 as a result of a constitutional reform passed by Congress. This reform reversed key elements of the 2013 reform, now imposing certain limitations on the participation of private investors in generation and marketing activities, and transforming the Federal Electricity Commission (CFE), the State-owned power utility, into a vertically integrated monopoly with preferential rights in power generation and marketing activities.

Under the new framework, private participation in generation activities is capped at a maximum of 46% of the relevant market, and the Mexican State reserves the remaining 54%, either through CFE or other State-affiliate mechanisms. Other activities were maintained as being exclusively reserved for the Mexican State, such as nuclear power, transmission and distribution.

The National Electric System (NES), integrated by the National Transmission Grid and the General Distribution Grids, continues to be owned by CFE and operated by the National Centre of Energy Control (CENACE), as the independent system operator under government oversight.

CENACE also manages the Wholesale Electricity Market (WEM), created in 2014 to foster competitive mechanisms for power trading based on a so-called “economic dispatch” model. The model prioritised low variable cost generation in the dispatch process to the NES; however, rules were changed with the 2024 reform in order to introduce the concept of a “load economic dispatch” mechanism that factors in not only variable costs but also operating, safety and reliability restrictions. This adjustment results in a limiting effect on the previous preferential dispatch model of renewal energy sources, considering their variable generation profiles.

On the administrative front, another constitutional reform in 2024 resulted in an institutional restructuring that replaced the Energy Regulatory Commission with the National Energy Commission (CNE), which is integrated into the Ministry of Energy (SENER) and assumes the authority for regulating activities in the power industry. This marks a departure from the previous legal framework, intended to allow for a technical and independent regulatory co-ordinated agency.

The main statutes governing the Mexican power industry are:

  • the Electricity Sector Law (LESE);
  • the Energy Planning and Transition Law (LPTE);
  • the Law of CFE (LCFE); and
  • the Law of the CNE (LCNE).

CFE is the main State-owned entity which, after the 2024 constitutional reform, now operates as a vertically integrated monopoly. The reform restructured CFE into a single consolidated entity, reintegrating its generation, transmission and distribution assets, as well as basic (residential) supply; previously, these activities were performed by legally and operationally independent State-productive subsidiaries, subject to strict separation rules following the unbundling principles introduced after the 2013 reform.

Despite this consolidation, specific affiliates of CFE have retained independent legal and commercial status. These entities are primarily focused on industrial (qualified) electricity supply, natural gas marketing and representation of legacy assets. They will continue to operate as separate commercial entities, albeit under CFE’s corporate umbrella.

A key development in 2023–2024 was the acquisition by the Mexican government of 13 power plants from Iberdrola, with a total installed capacity of 8,539 MW. This acquisition was implemented through Mexico Infrastructure Partners (MIP), an investment management vehicle backed by the Mexican government, which will operate these generation assets. As a result, the Mexican State – through CFE and MIP – has control over 54% of the generation capacity in the country (of 93,788 MW). The divestment represented 55% of Iberdrola’s asset base in the country.

On the supply side, CFE continues to be the main supplier of electricity, with exclusive rights over basic supply subject to regulated rates. Notwithstanding this exclusivity, industrial consumers and large-scale consumers (ie, qualified users) are still able to receive electricity supply from private marketers under competitive, market-based conditions.

Foreign investors and investments in the Mexican power industry are afforded the same rights, obligations and legal protections as their domestic peers. The Mexican legal framework does not impose nationality-based restrictions on private investment; limitations apply on equal terms to both foreign and domestic investors, pursuant to applicable constitutional and statutory provisions. Key restrictions include:

  • a cap on private (including foreign) participation in power generation activities, limited to 46% of the national generation market;
  • priority of the Mexican State in marketing activities; and
  • the complete exclusion of private (and thus foreign) participation in nuclear power, transmission and distribution activities, which remain under the exclusive authority of the State.

Foreign investors benefit from both local and international protections against government actions, such as seizure, confiscation, expropriation or other regulatory measures affecting their assets.

Locally, foreign investors may resort to administrative courts to seek relief. Internationally, foreign investors are (typically) protected under the relevant bilateral investment treaties (BITs) executed and ratified by Mexico, which provide access to investor-state dispute settlement mechanisms. Mexico has ratified more than 40 BITs and has recently ratified its adherence to the ICSID Convention. The protections granted to foreign investors in Mexico under such BITs are usually the same – ie, fair and equitable treatment, national treatment, most-favoured nation clause, performance requirements and expropriation (whether direct or indirect).

Despite not being party to the ICSID Convention until recently, Mexico has been a prominent participant in international investment arbitration, with approximately 22 procedures (most of them governed by Chapter XI of the North American Free Trade Agreement).

The international investment protection obligations assumed by Mexico provide foreign investors a number of benefits and remedies intended to secure the legal certainty of their investments in Mexico; however, the scope and applicability of these protections may vary depending on the specific structure, nationality, and characteristics of each investment.

The sale of power assets or businesses is subject to regulatory authorisations, as well as pre-merger control clearance. The LESE (and its relevant regulations) governs the transfer of permits, while the Federal Law of Economic Competition (LFCE) establishes the relevant rules and procedures on merger control.

From a regulatory standpoint, the CNE has authority to approve or deny the assignment of power generation, storage or supply permits, or changes of control within permit holders. It is worth noting that power activities (including fuel supply) are subject to strict legal separation requirements, which are designed to prevent vertical integration that could distort market dynamics and free competition principles.

On the antitrust front, the sale of power assets may be subject to approval by the federal antitrust agency. Thresholds are determined based on the value of the transaction and/or the parties’ market power, as established in the LFCE.

The Mexican legal regime on economic competition is also undergoing material changes due to the replacement of the Federal Economic Competition Commission (COFECE) (as an independent antitrust agency) with a new public instrumentality under the Ministry of Economy, which will have authority on economic competition matters. These changes are also expected to bring about substantive amendments to the rules governing monopolistic practices, pre-merger control procedures, investigations and sanctions against market participants.

SENER is the policy maker in charge of strategic planning in the Mexican power sector.

SENER’s planning authority has assumed a central role in the development of energy projects as a result of the 2024 constitutional reform. The LESE and the LPTE introduce the concept of “mandatory planning”, which requires both regulatory authorities and market participants to adhere to the official strategies, programmes and objectives of the government through SENER for the construction, installation and improvement of power infrastructure. These are outlined in the Development Plan of the Power Sector (PLADESE).

The PLADESE is issued by SENER each year with a 15-year outlook for the national electricity system, and contains three to five-year investment programmes for the development of generation, transmission and distribution infrastructure, in order to ensure reliability and continuity in the NES.

CFE, the CNE and CENACE are required to comply with the planning directives established in the PLADESE, and new investments in the sector (including private investments) must also comply with the planning criteria established therein. The granting of permits and the regulatory assessment of business plans for new infrastructure are now tied to the consistency of such projects and the goals and priorities outlined in the PLADESE.

As mentioned in 1.1 Law Governing the Structure and Ownership of the Power Industry, the Mexican government introduced two major constitutional reforms in 2024, which substantially changed the legal regime of the power sector in Mexico: the reform on strategic industries and areas and the organisational simplification reform.

The approval of these reforms by Congress gave rise to the enactment of the LESE, LCFE, LPTE and LCNE (among others) in March 2025. The main foundational changes of the 2024–2025 energy reform on electricity matters include the following.

  • Transformation of the legal nature of CFE (formerly a State-productive company) into a vertically integrated State-public company. This change consolidated its role across the generation, transmission, distribution and basic supply segments of the electricity value chain.
  • Clear preference of CFE and other State-owned generation companies over private participants. This includes a mandate to ensure that the State controls at least 54% of the electricity delivered to the grid (thereby limiting private sector participation to a maximum of 46%).
  • New regulatory rules for generation activities.
  • Creation of the CNE and broader authority of SENER, expanding the federal government’s purview over sector planning, market oversight and regulatory enforcement actions.

In short, these reforms signal a decisive shift toward greater State control and centralisation in the Mexican power industry, with significant implications for public and private sector stakeholders alike.

At the time of writing, the government is in the process of drafting and publishing regulations to the LESE and ancillary laws, which will further expand on the new rules and structure of the Mexican power industry brought about by the 2024 energy reform. These regulations are expected to provide guidance on the new legal and institutional framework for the electricity industry, defining operational, technical and procedural rules governing market participation, permitting and infrastructure development across the sector.

Once these regulations are issued, other administrative instruments will need to be enacted and/or amended. These include the WEM market rules and operating provisions, as well as regulations on storage, distributed generation, inside-the-fence projects, and reinforcement and improvement of the NES.

Together, these regulatory developments will shape the evolving landscape of the Mexican power sector and confirm how public and private stakeholders can operate pursuant to the principles already enacted under the new regime.

Government business plans and public presentations have shown that private investment in power infrastructure is critical to meet the country’s increasing demand. This is underscored by the country’s strategic position as a nearshoring investment destination, which drives economic growth but demands incremental energy consumption.

The government has announced investments to increase generation capacity by approximately 29,074 MW by 2030, with 22,674 MW expected to be installed by CFE and 6,400 MW by private sector participants. In addition, investments will target a critical expansion of transmission capacity in the order of 15,729 MVA and distribution capacity of 3,045 MVA. The total projected investment in the power sector for the next six years is estimated to be around USD32 billion.

In the current political environment, with President Sheinbaum’s political party and allies controlling the qualifying majority of the vote of Congress, it is anticipated that the principles introduced by the energy reform of 2024 will remain stable for the foreseeable future. This continuity should provide a measure of legal certainty for private investors operating under the new regulatory and market rules.

Note, however, that the procurement of energy and ancillary products by CFE (as the main supplier) no longer includes the obligation to perform long-term auctions. Therefore, long-term Power Purchase Agreements (PPAs) awarded in such tenders (which anchored clean energy generation facilities) are no longer part of CFE’s investment strategy for the time being.

The energy reform of 2013 established the operation of the WEM, designed to promote competition and efficient electricity trading. While the 2024 constitution did not eliminate the WEM, its operation is expected to materially change as a result of CFE participating as the constitutionally authorised monopoly, with priority over private market participants.

The WEM, operated by CENACE, considers the following transactions:

  • electricity (short-term spot markets);
  • capacity;
  • associated products, such as Clean Energy Certificates (CELs); and
  • ancillary services (eg, operating reserves, frequency regulation, emergency start and voltage regulation).

Electricity prices in the WEM are determined based on local marginal prices, which (currently) factor in the cost of energy, technical losses and transmission congestion. For such purpose, the government is transitioning toward a “Load Economic Dispatch” model, which adds operational, safety and reliability considerations to dispatch decisions and, potentially, alters the criteria for energy injections to the NES and the local marginal price calculations for the short-term spot market.

The “54%– 46%” electricity generation rule may also influence the determination of energy dispatch and prices, since this requirement operates over energy delivered to the NES during a relevant year. Therefore, dispatch order for years to follow could be affected if the Load Economic Dispatch distorts the proportion of energy delivered in order to preserve the mandated energy mix balance.

CENACE also operates an annual Balancing Capacity Market, in which Load Serving Entities (suppliers) must procure capacity through transactions with generators to cover the consumption of the loads they represent during the “100 critical hours” of the NES – ie, the most stressed periods of the year for generation reserves.

The Rules of the WEM also consider the operation of the CELs market, which requires Load Serving Entities to credit CELs (which evidence production from clean sources) before the CNE in proportion to the electricity consumed by their loads (currently at 13.9%). Generators can earn one CEL per MWh of power output stemming from clean sources.

To hedge against potential price volatility, market participants may enter into Electric Hedging Agreements (EHAs) for energy products. Those EHAs may also consider bilateral financial transactions in order to assign the receivables or accounts payable from WEM operations.

CFE’s regulated services (including basic supply, transmission and distribution) continue to be subject to regulated rates, determined annually by the CNE under the rules established in the previous regime.

High-load consumers are still eligible to act as “qualified users” – a status that allows off-takers to receive electricity supply from “qualified suppliers” (public or private) under free-market conditions. Qualified suppliers must meet rigorous compliance, reporting and risks management requirements before CENACE, including posting financial guarantees and minimum hedging obligations.

In some cases, major consumers may also register as market participants and transact directly in the WEM, including executing EHAs with generation companies to optimise procurement strategies and manage risk exposure.

Cross-border transactions of electricity are permitted under the LESE, subject to prior authorisation from SENER for imports and exports of power.

The NES currently has seven interconnection ties for cross-border transactions, with three neighbouring countries:

  • one with Belize;
  • one with Guatemala; and
  • five with the US (three connecting with Texas and two with California).

Market rules allow cross-border transactions for commercial purposes and for emergency or reliability support. Notably, export and import activities are not subject to capacity reservation requirements (except for reliability/emergency transactions, which are given certain preference), so each foreign trade transaction is scheduled and confirmed based on market rules.

In addition, power plants located abroad but exclusively interconnected to the NES may inject power output to the grid based on certain specific rules applicable to interconnection and dispatch.

The NES is heavily reliant on combined-cycle power plants (predominantly controlled by the Mexican State), representing over 58.46% of the energy delivered to the grid. The rest of the generation mix is composed as follows:

  • thermal: 8.63%;
  • wind: 5.89%;
  • hydro: 5.86%;
  • solar: 5.16%;
  • coal: 4.05%;
  • nuclear: 3.42%; and
  • others (turbogas, cogeneration, geothermal, distributed generation): 8.53%.

This composition reflects a generation mix still dominated by fossil fuels, albeit complemented by a growing share of renewable and alternative energy technologies. The relative dominance of State-owned generation assets – particularly in combined-cycle and hydroelectric plants – underscores the strategic role of the public sector in shaping energy supply, bolstered by the changes implemented in the 2024 reform.

The reform of 2024 and the LESE formalise the predominance of State-owned assets over private projects in both the generation and marketing of electricity.

On the generation side, this principle is implemented through a mandatory quota, requiring at least 54% of the electricity injected into the NES on an annual basis to originate from State-controlled generation. Subject to upcoming regulations to be issued, this figure is understood to encompass not only electricity generated and delivered directly by CFE (or MIP), but also production from joint ventures or public-private projects in which CFE holds equity or operational involvement.

Notably, however, the LESE does not provide a consequence if electricity delivered by private generation companies exceeds the 46% cap. The pending Regulations to the LESE and other administrative instruments to be enacted as a result of the 2024 energy reform are anticipated to further elaborate on how the quota is expected to be monitored and enforced, as well as how to construe the State’s predominance in marketing activities.

From an economic competition perspective, rules on market concentration may also apply, pursuant to the LESE and LFCE (but they will not apply to CFE, as a constitutional authorised monopoly).

Market concentration is not deemed an anti-competitive behaviour in and of itself (per se), unless it results in harm to the competitive process from an economic agent with substantial market power engaging in exclusionary conduct.

As outlined in 1.4 Sale of Power Industry Assets, the Mexican antitrust framework is undergoing significant structural changes due to the removal of COFECE and the creation of a new public entity under the Ministry of Economy, called the National Antitrust Commission (CNA), which will have authority on economic competition matters. While COFECE continues to exercise transitional powers, the CNA will eventually assume full jurisdiction and authority over all economic competition procedures and investigations (overseeing all markets, including the electricity sector) which, jointly with the new legal framework, will result in changes to:

  • investigations into monopolistic practices;
  • market dominance assessments;
  • pre-merger control thresholds and procedures; and
  • the imposition of sanctions.

Once COFECE is replaced, the CNA will be the federal agency tasked with monitoring the Mexican power market on antitrust matters, particularly with respect to private economic agents.

The LFCE classifies punishable exclusionary conducts in two categories:

  • absolute monopolistic practices, (including price fixing, bid rigging and unlawful exchanges of information); and
  • relative monopolistic practices, which are performed by economic agents with substantial market power, aiming to affect the competitive process.

The enforcement of anti-competitive rules usually involves formal investigations, an administrative adverse procedure (in the form of a trial), and the imposition of substantial economic fines, potentially amounting to as much as 10% of the annual revenue of the economic agent.

The construction and operation of generation facilities are mainly governed by the LESE and the General Law of Environmental Protection and Ecological Equilibrium (LGEEPA).

The LESE and regulations stemming therefrom, such as the WEM Rules, operating provisions and CNE-issued regulations on generation permits, specifically regulate the development and operation of generation facilities, and address their social impacts (whether for small, medium or large-scale operations). The LESE currently provides three distinct regulatory types for power generation, as follows.

  • Distributed generation: projects with a capacity of up to 0.7 MW, which do not require a generation permit from the CNE (irrespective of other interconnection agreements with CFE).
  • Self-consumption: generation for the “self needs” of users belonging to the same corporate group, whether connected (or not) to the NES (for back-up purposes). The LESE contemplates a fast-track permitting procedure for self-consumption generation facilities for up to 20 MW.
  • Generation for the WEM: this includes participation of the State and private parties, either individually or through public-private (mixed) vehicles. As for the latter, two types of public-private participation modalities are provided: long-term production (energy is sold exclusively to CFE) or mixed investment (CFE participates directly or indirectly in at least 54% of the power plant).

In addition, storage facilities associated with a power plant or those “isolated” – ie, operating independently to a load point or power plant – are considered generation assets and, therefore, require a permit from the CNE.

From an environmental standpoint, the LGEEPA governs the requirements of the projects, including their environmental impact assessments and authorisations. Other federal laws may apply, depending on the specifications of the generation projects, such as those related to waste management, forestry land use and water resources. Local (state and municipal) environmental and zoning regulations may also be relevant and must be considered.

Key project agreements – including Development Agreements, EPC, O&M, financing agreements, PPAs and EHAs – are subject to commercial and civil contract laws, which generally support freedom of contract and a choice of law doctrine.

Generation facilities are subject to several regulatory requirements at the federal, state and municipal levels. The main governmental authorisations for the construction and operation of power generation facilities include the following.

  • Generation permit: facilities exceeding 0.7 MW of capacity require a generation permit granted by the CNE, the application for which requires the submission of comprehensive technical, financial and legal documentation and information of the project. The LESE now mandates that generation permits align with the PLADESE, so permit applications for projects falling outside the scope of such plan may be denied. The process to obtain currently takes from six to 12 months (depending on the requests for additional information by the CRE). This timeline may change as a result of the enactment of the LESE and its regulations.
  • Interconnection agreement: although the grids of the NES are owned by CFE, CENACE oversees grid operation and interconnection procedures. Any interested party seeking to interconnect its generation facilities to the NES must follow a phased technical process administered by CENACE to determine the necessary grid reinforcement and interconnection requirements. Once the technical studies are concluded, CENACE directs CFE to execute the relevant interconnection agreement with the generation permit holder.
  • Market Participant Agreement: during the operational phase of the project, generation assets are required to execute a market participant agreement with CENACE to represent those assets in the WEM. Financial guarantees shall be posted in order to perform sales of energy products in the WEM.
  • Environmental Impact Authorisation: the construction and operation of power generation facilities require a federal environmental authorisation from the Ministry of the Environment and Natural Resources (SEMARNAT), which evaluates the environmental, safety and health aspects of the project.
  • Social Impact Authorisation: generation facilities are also required to obtain clearance from SENER on the social impacts of the project. Filing this application is necessary to obtain a generation permit, while the operation of the project depends on securing the relevant social impact authorisation.
  • Change of Forestry Land Use: if the project affects protected flora, an authorisation must be obtained from SEMARNAT for the relocation of such species.
  • Archaeological clearance: in specific regions, developers must secure archaeological clearance before commencing construction.
  • Water concession: the use of national waters may require permits or concessions from the National Waters Commission (however, hydroelectric plants of 30 MW capacity may be exempted from water permitting requirements).
  • Local authorisations: construction permits, land use approvals and civil protection authorisations, governed by local regulations, must also be secured prior to construction and operation.

In addition, if the project site is located on lands inhabited or claimed by indigenous communities, SENER is obliged to conduct a prior consultation process to ensure the protection of indigenous rights.

Government-issued authorisations for the construction and operation of generation facilities typically include strict deadlines for meeting key project milestones, such as the start of construction, provisional acceptance (ready for testing) and the commencement of commercial operations. Failure to meet these milestones may trigger administrative procedures to amend relevant permits; otherwise, the effectiveness of the permit may be at risk.

Material changes to projects (such as changes to nameplate capacity, generation technology or site conditions) generally require a formal amendment to the main permits in order to properly reflect the project scope. The amendment process often mirrors the original permitting procedure in both substance and timing, although for minor changes the administrative process only requires an “update” rather than a full permit amendment.

Interconnection agreements also impose firm deadlines for the works covered thereunder, coupled with the posting of financial guarantees to ensure their timely completion. They are also subject to hard deadlines and the posting of collateral to guarantee their completion in time.

In contrast, environmental and social authorisations focus on terms and conditions to monitor the commitments assumed by the generation company.

The LESE recognises the power sector as a matter of public interest and national policy. However, eminent domain for land use and occupation is limited to only hydroelectric and geothermal power plants.

Land use and occupation for hydroelectric and geothermal power plants follow a predetermined process established in the LESE for both private and agrarian land. This process includes mandatory filings and requirements for compensation and payments based on the value of the land.

The LESE also identifies types of real estate rights available for generation projects, including private ownership, lease, easements and usufruct rights.

The PLADESE includes a dedicated section on the decommissioning of generation facilities. Given the binding nature of the PLADESE, decommissioning is expected to proceed in accordance with the requirements provided thereunder.

Generators are also required to notify CENACE of the decommissioning of the generation assets within one year prior to the effective decommissioning date. Importantly, decommissioning is not permitted for power stations still participating in capacity transactions with binding obligations.

CENACE will assess whether the facility plays a role in system reliability. If it does, CENACE notifies the CNE to obtain approval to perform a capacity auction, in which the generator is obliged to participate.

Environmental authorities may also impose requirements for insurance or financial guarantees to ensure that decommissioning activities comply with the conditions imposed on site remediation, including waste management. SENER may also determine specific social commitments upon decommissioning, if applicable.

The construction and operation of transmission lines is governed by the LESE, the LPTE and the LGEEPA. These statutes also regulate associated facilities, such as energy storage equipment associated with the transmission activities.

Transmission services are exclusively reserved to the Mexican State, through CFE. CFE must comply with the General Administrative Provisions on open access and terms of service for transmission and distribution services, as approved by the CNE.

Nevertheless, the LESE and LCFE allow private sector involvement in the construction, installation, financing and improvement of the National Transmission Grid (NTG). In particular, the LCFE provides that CFE may create joint ventures with private entities for the development of the NTG.

Private market participants, including generators, exporters, importers and consumers, are allowed to construct and operate private lines for specific uses, such as onsite delivery, interconnection and connection to the grid. These private lines are not considered part of the NTG and are therefore not subject to open access rules. However, the provision of transmission services to third parties via such lines is expressly prohibited.

The PLADESE sets forth the government’s policy for the expansion and improvement of the NTR, which includes references to anchor projects and general specifications for their development.

As the exclusive provider of transmission services, CFE is not required to obtain a specific permit for such purposes. However, transmission must comply with the General Administrative Provisions on open access and for the provision of such services issued by the CNE.

Notwithstanding the exemption from sector-specific permitting, the construction and operation of transmission lines requires environmental, social, local and municipal authorisations (similar to those applicable to generation facilities), as well as government approvals for crossroads, lands and water bodies within the jurisdiction of governmental agencies. These approvals are typically contingent on the acquisition of the corresponding real estate rights.

Note that environmental impact authorisations are not required for transmission infrastructure located in urban, rural, industrial or touristic areas.

Environmental and social authorisations related to the construction and operation of transmission infrastructure include provisions for remediation measures, ongoing monitoring protocols and obligations tied to eventual decommissioning.

Transmission services are deemed to be a public utility and are therefore subject to expropriation under that designation. The LESE expressly grants eminent domain rights for the construction and operation of transmission works.

CFE must follow the land use and occupation procedures outlined by the LESE in order to obtain the necessary real estate rights for the development, construction and operation of transmission infrastructure. These procedures consider the execution and ratification of real estate agreements before civil or agrarian courts, as well as specific compensation concepts.

CFE is the only entity allowed to provide public utility transmission services. The terms and conditions governing these services (including rates) are approved by the CNE (whose rules were grandfathered from the former regulator).

While CFE holds exclusive rights to operate transmission services, the participation of private investment in transmission infrastructure is expected, either under contractor modality or through partnerships. In support of this, the Mexican government recently announced investments of up to USD6.5 billion for the 2025–2030 period, aimed at 158 transmission projects that would reinforce the NTG with 15,729 MVA of capacity.

Transmission rates are issued and approved annually by the CNE. These rates are calculated using methodologies that ensure a reasonable return of investment and cost recovery on the operation, maintenance, financing, investment, improvement, expansion and depreciation of the NTG, as well as accounting for both technical and non-technical losses.

Market participants pay for transmission services through CENACE, which incorporates these rates into the settlement processes of the WEM. Basic supply rates also consider specific transmission costs reflected as part of the variable energy charges.

The CNE is also empowered to issue general terms of service for transmission services, outlining the scope and types of service offered, credit terms, conditions for service suspension, penalties and compensation mechanisms, and procedures for addressing complaints from users.

Open access to the NES is recognised as universal and a public utility service obligation, provided that it is technically feasible and does not compromise the reliability of the system.

CENACE is mandated to ensure that open access obligations are met while safeguarding the operational reliability of the NES.

The legal, financial and technical requirements to allow the interconnection of generation facilities and the connection of load points are established in the Market Rules, which include a dedicated Manual detailing the procedures. The interconnection and connection processes involve several technical studies to identify reinforcement works (which are incorporated in the relevant interconnection or connection agreements), including indicative, system impact and facility studies.

Subject to completion of the relevant studies, CFE is obliged to allow the interconnection and connection of power stations and loads on a non-discriminatory basis. In this regard, CENACE instructs CFE to enter into the agreement with the interested party.

Upon completion of the required infrastructure, verification units certify that the interconnection facilities comply with the technical specifications established in the agreements. Interconnection or connection works may be executed directly and financed by the interested party or integrated into the expansion and improvement works outlined in the PLADESEN.

Distribution services are exclusively reserved to CFE, pursuant to the Mexican Constitution and the LESE.

The operation of General Distribution Grids (GDGs) are governed by the LESE and the General Administrative Provisions on open access and terms of service for distribution services, as approved by the CNE.

As with transmission services, CFE is not required to obtain a specific permit to provide distribution services.

However, the construction and operation of distribution facilities require environmental, social, local and municipal authorisations (similar to those applicable to generation facilities), as well as government approvals for crossroads, lands and water bodies within the jurisdiction of governmental agencies. These approvals are typically contingent on the acquisition of the corresponding real estate rights.

Note that environmental impact authorisations are not required for distribution substations located in urban, rural, industrial or touristic areas.

Environmental and social authorisations related to the construction and operation of distribution infrastructure include provisions for remediation measures, ongoing monitoring protocols and obligations tied to eventual decommissioning.

Distribution services are deemed to be a public utility and are therefore subject to expropriation under that designation. The LESE expressly grants eminent domain rights for the construction and operation of distribution works.

CFE must follow the land use and occupation procedures outlined by the LESE in order to obtain the necessary real estate rights for the development, construction and operation of distribution infrastructure. These procedures consider the

execution and ratification of real estate agreements before civil or agrarian courts, as well as specific compensation concepts.

CFE is the only entity allowed to provide public utility distribution services. The terms and conditions governing these services (including rates) are approved by the CNE (whose rules were grandfathered from the former regulator).

While CFE holds exclusive rights to operate distribution services, the participation of private investment in distribution infrastructure is expected, under contractor modality. In support of this, the Mexican government recently announced investments of up to USD3.79 billion for the 2025–2030 period, aimed at 97 brand new substations, 95 expansion projects for existing substations, 6,875 modernisation works and 42,221 electrification works.

Distribution rates are issued and approved annually by the CNE. These rates are calculated using methodologies that ensure a reasonable return of investment and cost recovery on the operation, maintenance, financing, investment, improvement, expansion and depreciation of the GDGs, as well as accounting for both technical and non-technical losses.

Market participants pay for transmission services through CENACE, which incorporates these rates into the settlement processes of the WEM. Basic supply rates also consider specific distribution costs reflected as part of the fixed capacity charges.

The CNE is also empowered to issue general terms of service for distribution services, outlining the scope and types of service offered, credit terms, conditions for service suspension, penalties and compensation mechanisms, and procedures for addressing complaints from users.

Cortés Quesada Abogados, S.C.

Av. Santa Fe 505
Fl. 1 MZ 2B
Santa Fe Cuajimalpa
Cuajimalpa, 05348
Mexico City
Mexico

+52 55 5293 9360

+52 55 5293 9360

contacto@cortesquesada.com.mx www.cortesquesada.com.mx
Author Business Card

Trends and Developments


Authors



Cortés Quesada Abogados, S.C. is a Mexico City-based law firm specialising in the energy, infrastructure and sustainability sectors. Serving both international and domestic clients, the firm delivers innovative, strategic legal advice grounded in international best practices, with a strong focus on business-oriented solutions. Leveraging the extensive expertise of its team, Cortés Quesada combines deep sector knowledge with the capabilities of a full-service law firm, providing comprehensive legal support across diverse industries within the Mexican market, offering a truly comprehensive service for international and local clients. The firm has a proven track record in representing energy producers, marketers and key off-takers of energy products in Mexico in a broad range of transactions, for the development, construction and/or operational phases of their projects. Currently, the firm is led by two partners and supported by a dedicated team of more than ten associates and paralegals.

Power Generation, Transmission and Distribution in Mexico: an Introduction

Constitutional reforms of 2024

Following the 2024 general elections in Mexico, President Claudia Sheinbaum (the first woman to hold the office) and her party Morena and allies secured a supermajority vote in both Chambers of the Congress. This political mandate enables the new administration to amend the Mexican Constitution, ushering in a new political and legal order, with the energy sector emerging as a top priority.

In alignment with the principles proposed by outgoing President Lopez Obrador, the Mexican Congress approved a constitutional reform on strategic areas and companies. This reform had far-reaching implications for the electricity industry, including:

  • a change of the nature of (former) State-productive companies, now transformed into public State companies, covering both Petróleos Mexicanos (the national oil company) and Comisión Federal de Electricidad (CFE – the national power utility company);
  • listing certain activities performed by State public companies as exclusive strategic areas;
  • expanding CFE’s statutory purpose and objectives to include social responsibility, guarantee of continuity and access to electricity services;
  • prioritising the participation of the State (particularly through CFE) over private participants in the activities performed in the Mexican electricity industry;
  • establishing national planning objectives and control of the National Electricity System (NES), such as securing electricity service, the preservation of energy security and self-sufficiency, as well as the provision of electricity services at the lowest possible cost (avoiding profit); and
  • repealing the transitory provisions of the 2013 constitutional reform of energy matters, which fully liberalised power generation and marketing activities.

Separately, in December 2024 Congress approved another constitutional reform on organisational simplification (also inherited from President Lopez Obrador), which impacted the energy sector by dissolving the co-ordinated regulators on energy matters: the National Hydrocarbons Commission (regulator of oil and gas upstream activities) and the Energy Regulatory Commission (CRE), regulator of all power activities, as well as oil and gas midstream and downstream activities.

Implementing legislation

The implementing legislation for both constitutional reforms came into effect on 18 March 2025, commemorating the anniversary of the 1938 oil expropriation. This legislation reshaped the electricity legal framework through the following new statutes and reforms to existing laws, to adapt its provisions to the new constitutional framework of the Mexican electricity sector:

  • the Electricity Sector Law (LESE), which repealed the Electricity Industry Law from the 2013–2014 energy reform;
  • the Law of the State-Owned Company, Comisión Federal de Electricidad (the “New Law of CFE”), which repealed the prior law governing CFE;
  • the Planning and Energy Transition Law (LPTE), which superseded the 2015 Energy Transition Law;
  • the Law of the National Energy Commission (LCNE), creating the National Energy Commission (CNE) as regulator of the power sector, and repealing the 2014 Law of the Co-ordinated Regulatory Agencies on Energy Matters;
  • the Geothermal Law, which repealed the 2014 Geothermal Energy Law; and
  • reforms to the Organisational Law of the Federal Public Administration.

Collectively, the new legal regime institutes a centralised model marked by State planning through the Ministry of Energy (SENER – the constitutional monopoly in certain segments) and the continued operation of a Wholesale Electricity Market (WEM) for the performance of purchase and sale transactions of energy and ancillary products. All of the above occurs under mechanisms that ensure the predominance of the State in the market, particularly through a vertically and horizontally reintegrated CFE.

Key elements of the 2024 energy reform

Generation activities

The LESE establishes a minimum 54% share of State-controlled generation assets (including those of CFE) in total energy injected into the grid, andin the marketing of electricity. The LESE implements three main forms of generation (with different modalities):

  • distributed generation;
  • self-consumption; and
  • generation for the WEM.

The threshold for permit-exempt generation rose to 0.7 MW, which also applies for distributed generation purposes.

For the self-consumption modality, the LESE provides a streamlined permitting process for power plants with a capacity of up to 20 MW. This scheme includes both isolated and interconnected modalities, with the latter requiring back-up conditions for grid reliability purposes.

The WEM allows for participation by both public and private entities for generation purposes, either individually or through public-private (mixed) structures. In the latter case, two types of public-private participation modalities are recognised:

  • long-term production structures involving exclusive sales to CFE; and
  • mixed-investment projects in which CFE participates directly or indirectly in at least 54% of the power plant.

The LESE also introduces a specific modality for cogeneration projects, which are granted a dispatch guarantee to the grid.

Control and operation of transmission and distribution grids

The transmission and distribution of electricity remain strategic activities reserved exclusively to the Mexican State and are entrusted to CFE. Operational control of the NES continues to be assigned to the National Centre of Energy Control (CENACE), which operates as a State-controlled independent system operator.

A new concept introduced under the 2024 reform is the “economic load dispatch”, which replaces the former “economic dispatch” model. This mechanism allows CENACE to determine the injection of electricity into the NES by generation companies, as a mechanism to ensure the State’s predominance in the sector. CENACE also continues to be responsible for managing the interconnection processes of power plants and the connection of load centres.

Regarding the development of new transmission and distribution infrastructure, the New Law of CFE allows private participants to “associate” with CFE for the installation, extension and/or maintenance of the National Transmission Grid and the General Distribution Grids.

Marketing

The LESE upholds the principle of State predominance in electricity marketing activities. However, unlike the rules relating to generation, the law does not provide further details on how this predominance will be enforced.

The law designates CFE as the sole and exclusive Basic Services Supplier. This marks a departure from the previous legal framework, which allowed other authorised entities to participate in the provision of basic supply services. Under the new regime, CFE is permitted to enter into Power Purchase Agreements (PPAs) with any generator, using a variety of mechanisms, including competitive tenders.

Qualified supply services, intended for large-scale consumers, are preserved under terms largely consistent with the prior legislation. SENER retains authority to define and periodically adjust the minimum demand threshold required for end users to be registered as qualified users.

WEM

The operation of the WEM is still entrusted to CENACE, which is tasked with establishing the rules for cost registration, the submission of capacity offers, and the representation of assets in the WEM.

In addition, the (new) Economic Competition Agency is designated as the authority responsible for investigating and sanctioning antitrust practices in the power sector. Activities performed by CFE, however, are expressly excluded from economic competition scrutiny.

Storage and electromobility

The new legal framework includes specific provisions on power storage and electromobility matters, granting SENER and the CNE authority to issue the applicable administrative and economic regulations. Electrical energy storage systems are allowed to supply energy to the NES, provided that the entire production is offered to CENACE.

It is important to note that, before the enactment of the LESE and the LCNE, the former regulator (the Energy Regulatory Commission) issued a set of rules on energy storage systems (SAE, for their Spanish acronym) within the WEM. These rules defined five distinct SAE categories based on their purpose.

  • SAE-CE (associated with a power station) requires a generation permit from the CNE and is limited to power stations with “intermittent” production sources. The energy used to charge the SAE-CE must originate from the associate power station, and its charge and discharge operations must follow instructions from CENACE.
  • SAE-CC (associated with a load centre) does not require a generation permit but must be represented in the WEM either by a supplier or independently. The stored energy is used to meet the demand of the corresponding load centre.
  • SAE-AA (associated with isolated supply infrastructure) requires a generation permit and must comply with the same rules (and restrictions) as isolated supply power stations, including the concept of “self needs”.
  • Non-Associated SAEs (not linked to any generation or consumption infrastructure) are treated as firm power stations for regulatory purposes and participation in the Balancing Capacity Market, while being exempt from obligations related to Clean Energy Certificates.
  • SAE-GEs (associated with an exempt producer) are regulated according to the rules applicable to distributed generation.

Clean energy obligations

The LESE continues to recognise Clean Energy Certificates (CELs) as the primary tool to support Mexico’s energy transition. However, unlike before, CELs are now awarded regardless of the ownership or commercial operation date of the applicable Power Stations. SENER is responsible for setting the annual CEL acquisition requirements, which can be traded within the WEM.

Under the new LPTE, SENER will also establish the criteria to certify clean energy producers and grant CELs. These criteria will take into account the actual level of “real” emissions of each technology and permit holder, as well as the use of back-up and ancillary services from fossil-fuelled energy for the operation of clean energy sources.

In addition, the CNE is expected to create a new CEL registry to record ownership of CELs and the relevant transfers, and to track related transactions.

CFE

As a result of the constitutional reforms, the New Law of CFE lays the foundations for the transformation of CFE into a single, consolidated State-owned company. The key features of this new legal regime include the following.

  • Corporate integration: CFE is reorganised into a single entity, eliminating its former structure of State-productive company and subsidiaries.
  • Special legal regime: CFE will operate under a distinct legal framework governing areas such as affiliate companies, procurement processes, asset management, administrative responsibilities, and budgetary and accounting treatment.
  • Exclusion from antitrust oversight: CFE’s activities are expressly excluded from being classified as monopolistic practices (so, in principle, would not be subject to antitrust scrutiny).
  • Supplementary legal framework: while public, civil and commercial laws apply to CFE in a supplementary manner (depending on the nature of the act), it is specified that the content of such laws must be applied as long as they do not oppose the special regime of CFE and, where appropriate, the interpretation that privileges the best performance of the purpose and essence of CFE in accordance with its status as a public company of the State.
  • Contracting and dispute resolution: CFE has contracting procedures (public bid, as a general rule) and a legal framework for agreements entered into by CFE, including governing law for acts during the contracting procedure and for those after the relevant contract is executed, as well as dispute resolution mechanisms (in which federal Mexican courts are the general rule).

Under this new structure, CFE is mandated to perform transmission, distribution, marketing and basic supply of electricity activities directly. For other activities, CFE may operate directly or through affiliated entities.

In addition, all real estate owned by CFE – including land, buildings and related infrastructure – is exempted from property and possession taxes, regardless of its use or purpose.

Following the enactment of the New Law of CFE, the former generation, distribution and basic supply services subsidiary companies were dissolved. CFE assumed all corresponding rights and obligations of these now-defunct entities by operation of law.

The CNE and regulated activities

The newly created CNE replaces and absorbs the former Energy Regulatory Commission, now functioning as a public instrument of SENER. The CNE is in charge of overseeing both the administrative and economic regulation of the power sector, including setting and supervising the applicable rates across the electricity value chain (distribution, transmission, basic supply, etc).

The CNE reassumed legal terms and started operations as of June 2025, except for certain matters (including new generation permit applications and change in control authorisations). Once the Regulations to the LESE are issued, the CNE will be open for all procedures and applications on electricity matters within its scope of authority.

The CNE is governed by a General Director and Technical Committee, both of which have already been appointed. This governing body is authorised to evaluate and grant permits for generation, commercialisation and electricity supply activities. Meanwhile, SENER retains authority over the issuance of import and export permits for electricity.

The LESE includes principles of legal separation of the performance of generation, marketing and supply feedstock (eg, fuels) activities. However, these principles are no longer applicable to CFE.

The law also grants SENER broad intervention powers under certain circumstances. For instance, SENER may assume control of sector participants or mandate structural measures, such as accounting, operational or functional separation of members of the power sector. If such measures are deemed insufficient, SENER may even order the divestiture of assets, rights, equity interests or shares, to ensure compliance with sectoral regulation.

Land use and occupation, promotion of the national industry, and social impact

The execution of instruments related to the use and occupation of land for the performance of activities of the power industry is subject to the completion of specific administrative and judicial procedures, particularly those involving transmission, distribution and generation activities using geothermal deposits and hydraulic resources.

As a general rule, activities of the electricity industry are deemed to be of public utility, which enables the government to exercise expropriation and eminent domain in some instances.

In addition, requirements and methodologies are introduced on national content obligations. The new legal framework also incorporates the concept of “Energy Justice” and “Sustainability”, aimed to foster access to energy infrastructure across the entire population, with responsible resource management.

Energy planning and transition

The new legal framework introduces certain command economy principles through the concept of “mandatory planning” for the WEM. This planning mechanism is intended to aim investment decisions in the sector across different regions of the country, while ensuring the State’s predominant role in the injection of energy into the national grid.

Under the LPTE, several key planning instruments are established with medium (15 years) and long-term (at least 30 years) horizons:

  • the National Strategy of Energy Transition;
  • the Power Sector Development Plan;
  • the Hydrocarbons Sector Development Plan; and
  • the Plan for the Energy Transition and Energy Sustainable Use.

The National Strategy must be issued at the beginning of each new Presidential Administration and will set forth clean and renewable energy targets, based on minimum percentages with respect to the total power generation in Mexico.

In addition, the LPTE provides for the management of the Energy Information System, and contemplates the issuance of acknowledgements and agreements related to energy efficiency.

Grandfathered projects and migration

Permits and agreements issued under the former legal framework (the Law of the Public Service of Electric Energy, repealed in 2014, and the Electricity Industry Law, repealed in 2025) will remain in force under their current terms. However, the new legal regime under the LESE provides the option for relevant participants to migrate to the new modalities under the LESE.

All agreements entered into by CFE’s subsidiary productive companies will be transferred to the restructured CFE entity. While CFE is now integrated as a single company, the framework preserves conditions of the separation of activities in terms of nominations and offers for the WEM.

The 2024 energy reforms and the laws stemming therefrom are still being implemented at an administrative level, with the creation of the CNE and the drafting of new regulations; the issuance of regulations and amendments to existing provisions are yet to fully implement the constitutional and legal principles set forth in the corresponding federal statutes.

The administrative implementation of the energy reform of 2024 and its implementing legislation is of utmost relevance since several key elements remain pending, which will be crystalised by the issuance of the applicable instruments by SENER and the CNE. These include:

  • market rules;
  • determination and calculation of the energy injected into the grid by CFE to confirm its legal predominance in the sector;
  • rules for transactions between entities of the same “Economic Interest Group”;
  • rules for the legal, functional and accounting separation of participants of the electricity industry; and
  • rules on energy storage and electromobility.

Recent investment announcements

On 9 April 2025, the Mexican government announced a comprehensive public investment plan for the power sector, outlining an estimated USD32.6 billion in investment over the 2025–2030 period. The plan focuses on strengthening the generation, transmission and distribution infrastructure, with the following key measures.

  • Generation capacity expansion: a target of 29,047 MW of new installed capacity (22,674 MW by CFE and 6,400 MW by private entities), including the bidding and commissioning of eight new combined-cycle power plants, eight hydroelectric plant, and two photovoltaic park expansions.
  • Reinforcement of the National Transmission Grid: implementation of 158 projects to reinforce grid capacity by an additional 15,729 MVA.
  • Distribution infrastructure development: construction of 97 new substations and expansion of 95 existing facilities to support improved network reliability and coverage.
Cortés Quesada Abogados, S.C.

Av. Santa Fe 505
Fl. 1 MZ 2B
Santa Fe Cuajimalpa
Cuajimalpa, 05348
Mexico City
Mexico

+52 55 5293 9360

+52 55 5293 9360

contacto@cortesquesada.com.mx www.cortesquesada.com.mx
Author Business Card

Law and Practice

Authors



Cortés Quesada Abogados, S.C. is a Mexico City-based law firm specialising in the energy, infrastructure and sustainability sectors. Serving both international and domestic clients, the firm delivers innovative, strategic legal advice grounded in international best practices, with a strong focus on business-oriented solutions. Leveraging the extensive expertise of its team, Cortés Quesada combines deep sector knowledge with the capabilities of a full-service law firm, providing comprehensive legal support across diverse industries within the Mexican market, offering a truly comprehensive service for international and local clients. The firm has a proven track record in representing energy producers, marketers and key off-takers of energy products in Mexico in a broad range of transactions, for the development, construction and/or operational phases of their projects. Currently, the firm is led by two partners and supported by a dedicated team of more than ten associates and paralegals.

Trends and Developments

Authors



Cortés Quesada Abogados, S.C. is a Mexico City-based law firm specialising in the energy, infrastructure and sustainability sectors. Serving both international and domestic clients, the firm delivers innovative, strategic legal advice grounded in international best practices, with a strong focus on business-oriented solutions. Leveraging the extensive expertise of its team, Cortés Quesada combines deep sector knowledge with the capabilities of a full-service law firm, providing comprehensive legal support across diverse industries within the Mexican market, offering a truly comprehensive service for international and local clients. The firm has a proven track record in representing energy producers, marketers and key off-takers of energy products in Mexico in a broad range of transactions, for the development, construction and/or operational phases of their projects. Currently, the firm is led by two partners and supported by a dedicated team of more than ten associates and paralegals.

Compare law and practice by selecting locations and topic(s)

{{searchBoxHeader}}

Select Topic(s)

loading ...
{{topic.title}}

Please select at least one chapter and one topic to use the compare functionality.