Construction Law 2026 Comparisons

Last Updated June 04, 2026

Law and Practice

Authors



VPB Studio legale associato is an independent law firm based in Milan, with offices in Rome and Hong Kong. The firm assists Italian, foreign and multinational companies, focusing particularly on small and medium-sized enterprises operating in international markets, foreign companies with current or prospective interests in Italy, and private clients investing in real estate projects in Italy, including construction, renovation and refurbishments. VPB offers expertise across numerous areas, including corporate transactions and disputes, contract law, conflict prevention and dispute resolution. The firm’s lawyers have managed complex litigation across corporate, M&A and contractual matters. In construction, the firm has advised Italian and international companies and consortia in litigation and arbitration proceedings in Italy and abroad relating to both construction contracts and the relationship between members, in industries such as hospitality and energy. Partners of the firm have acted as arbitrators in ad hoc and administered construction cases.

Italy’s construction market is framed by five core statutes.

  • Private construction contracts are governed by the Civil Codeappalto rules (definition, pricing, variations, testing/payment, termination) and the decennial liability for rovina o gravi difetti under Article 1669.
  • For public works, the current Public Contracts Code (D.Lgs. 36/2023) governs programming, digitalised tendering, awards, contract execution (including subcontracting), and oversight/remedies for works, services and concessions.
  • For planning and building permits, the Consolidated Building Act (DPR 380/2001) sets zoning titles, permitting, controls, sanctions and supervisory powers, and is to be read in conjunction with local plans.
  • Site health and safety are regulated by the Safety Consolidated Act (D.Lgs. 81/2008), which assigns duties to the employer/works responsible, requires co-ordinators for design/execution, and mandates prevention measures for temporary/mobile sites.
  • Environmental aspects (EIA, water, waste, emissions, soil) affecting projects are dealt with under the Environmental Code (D.Lgs. 152/2006).

There is no statute mandating FIDIC/NEC or any private sector standard form in Italy. Private projects typically use bespoke contracts. International sponsors sometimes adapt FIDIC (mainly EPC/design–build) for employer–contractor relations, while designer and subcontractor appointments are usually bespoke or project-tailored. None are legally compulsory.

In the public sector, the Public Contracts Code (D.Lgs. 36/2023) entrusts the National Anti Corruption Authority (ANAC) to issue standard contractual documents (bandi‑tipo, capitolati‑tipo and contratti‑tipo) to standardise procurement documents. These serve as regulatory templates and guidance for contracting authorities; they are influential but are not generally mandatory clauses, unless the specific template is expressly made binding.

These kinds of documents can be found (also in English) on the website of the authority.

In private projects, the employer (committente) is typically a company that owns or develops the site, such as property developers, special purpose vehicles, housing co-operatives or condominium associations. In public projects, the employer is a contracting authority or entity (stazione appaltante) governed by the Public Contracts Code (Legislative Decree 36/2023).

Italian construction contracts are appalti, where the contractor delivers works for a price; this frames the employer’s duties to pay, co-operate, provide access/permits, and manage variations per contract. The employer is entitled to receive conforming works and to enforce defect liability, including for serious defects of buildings (ten‑year liability), under Articles 1667 and 1669 of the Civil Code and, on public works, the Public Contracts Code’s cross‑references. They are also entitled to do the following.

  • Ensure procurement compliance (public sector) and project governance, and appoint designers/supervisors as required by the project and safety laws. The employer typically bears costs for water/electricity supply to the site, administrative authorisations, occupancy permits for public land, and professional fees for project designers and safety co-ordinators.
  • Exercise inspection, testing and acceptance rights before final payment and close‑out. Typical acceptance procedures require the employer (or works director) to conduct final verification within 15 to 30 days of completion notice, issuing a written acceptance report – either unconditional, with reservations for defects, or as non-acceptance with stated reasons. If verification is not conducted within 30 days without justification, the works are deemed accepted by operation of law (tacit acceptance).

The employer contracts with the main contractor and usually has no direct contractual link with subcontractors; claims ordinarily flow through the contractor. In public projects, subcontracting is permitted but regulated by Decree 36/2023 (qualification, notices and controls). In private contracts, subcontracting typically requires the employer’s prior written consent, with the contractor remaining jointly liable with subcontractors for performance. Subcontracting cannot be invoked as grounds for excusing delays, defects or non-performance.

Financiers typically fund the employer/SPV and take security over project assets and receivables. In structured deals, they may obtain step‑in rights and direct agreements to protect funding during contractor default; these arrangements align with project finance and PPP tools recognised by the Public Contracts Code.

The following typically act as contractor:

  • general contractors (impresa edile/costruttore) delivering works under an appalto, organising means and labour and bearing business risk – this distinguishes appalto from labour supply; and
  • consortiums or temporary groupings (consorzi/RTI) formed to pool qualifications for larger projects, especially in public works under the Public Contracts Code (D.Lgs. 36/2023).

The contractor’s main rights and obligations are as follows.

  • Core execution and compliance duties – the contractor must organise means and personnel, perform the works a regola d’arte, supply compliant materials, and meet programme dates. The Italian Civil Code frames this role and places liability for defects on the contractor, with ordinary remedies and a ten‑year liability for ruin or serious structural defects. Site safety duties include drafting and applying the POS, co-ordinating with the PSC, and managing workers and subcontractors in compliance with D.Lgs. 81/2008.
  • The contractor may raise issues found during works, and is entitled to price/time adjustments for unforeseen difficulties within statutory and contractual limits. The employer may inspect and order variations; the contractor must follow reasonable instructions from the works supervisor while retaining execution risk. These allocations are standard and echoed in private agreements in the vault (insurance, waste disposal, sub‑contracting controls, indemnities).
  • On delivery, the employer verifies the works, and the contractor must remedy defects or reduce the price, as applicable. For serious structural defects, liability extends for ten years. Contractual tools typically add delay penalties, retentions and insurance to secure performance, consistent with Italian practice.

The relationships between contractors, employers, subcontractors and financiers are as follows.

  • Contractor–employer: a bilateral appalto. The contractor organises means and assumes risk and liability for defects within statutory limits.
  • Subcontractors are engaged by the contractor. The employer’s consent and statutory/public procurement limits may apply in public works. Payment flows and liability remain primarily with the contractor, unless step‑in or direct payment mechanisms are agreed.
  • Insurance obligations: contractors are typically required to maintain civil liability insurance (RCT/RCO) with minimum coverage ranging from EUR1.5 million to EUR10 million, depending on project scope, and in some cases a decennial posthumous policy. Insurance must cover damages to the employer, third parties and their property arising from any operations connected to the works.
  • Financiers are typically protected via security and direct agreements allowing step‑in, the assignment of receivables, or control of project accounts. In public contracts, such arrangements operate alongside the Code’s rules.

Subcontractors are usually specialist trade firms, handling structural concrete and steel, MEP (HVAC, electrical, plumbing, fire), façades and roofing, geotechnical and earthworks, scaffolding, roadworks, and landscaping. In public works, they must meet qualification and authorisation requirements set by the Public Contracts Code (D.Lgs. 36/2023), including disclosure of the subcontract’s scope and value to the contracting authority.

Subcontractor Rights and Obligations

Rights include timely payment per the subcontract, and, in public works, protections linked to verification and possible direct payment mechanisms defined by the Code.

Core obligations are to execute the works in conformity with the main contract and site rules, comply with HSE and workforce regulations, and co-ordinate with the contractor and site management.

For labour costs and social contributions, Italian law imposes joint liability up the chain for a limited period, which shapes subcontractor documentation and compliance practices.

Relationships With Employer, Contractor and Financiers

The subcontract is with the contractor; there is generally no direct contractual link to the employer, save for public law controls and any agreed direct payment procedures. Subcontractors interact with financiers only indirectly: lenders typically secure step‑in and control at the project level, while subcontractors’ obligations flow down from the main contract and procurement rules. Site supervisors and the contracting authority monitor authorised subcontractors’ presence and performance on public works. The main contractor remains fully liable for subcontractors’ performance and must hold the employer harmless from any costs, damages or liabilities arising directly or indirectly from subcontracting.

Typical financiers include:

  • banks (Italian and international), often alongside financial intermediaries registered under Article 106 of the Consolidated Banking Law (TUB); and
  • asset managers and investment funds (SGR, SICAV/SICAF) providing project or development finance and subscribing debt instruments.

Financiers’ Rights and Obligations

Financiers are usually not parties to the construction contract. Their rights arise under finance and security documents governing conditions precedent, covenants, security over receivables and accounts, and “direct agreements” with the employer/contractor in PPP or project finance structures, including step‑in. They must fund according to agreed drawdowns and comply with supervisory and customer protection rules applicable to banks and intermediaries. Receivables from the works can be assigned to financiers under Italian assignment‑of‑trade‑receivables law to support payment controls.

Relationship With Employer, Contractor and Subcontractors

  • Employer and contractor: financiers contract with the employer/sponsor and may enter direct agreements with the contractor to receive notices, consent to variations, and exercise step‑in upon default in PPP/public contracts.
  • Subcontractors: there is normally no privity. Payment remains via the contractor unless the finance package or public law mechanisms allow direct payment of certified receivables. Assignments and account controls are used to ring‑fence cash flows.
  • Overall governance: lenders monitor progress, budget and compliance through reporting and site inspections tied to drawdowns. These controls supplement, but do not replace, the employer’s contract‑administration role.

Design is delivered by individual architects and engineers, multidisciplinary studios, engineering companies and società tra professionisti (STP). Foreign EU providers and co-operatives can also offer engineering/architecture services if qualified. These categories are expressly recognised among providers of engineering and architecture services in Italy.

Designer rights and obligations are as follows.

  • Rights commonly include agreed fees, variation compensation where the scope changes, and recognition/transfer of design documents per contract. In public works, payment typically entails the acquisition of design ownership by the employer.
  • Core duties are to produce compliant designs, co-ordinate disciplines and support permitting. Designers must also address construction safety by co-operating with, or taking the role of, the safety “co-ordinator for design”, when appointed.
  • Liability can extend to serious defects affecting stability or essential functions. Italian case law applies Article 1669 civil liability not only to contractors but, in appropriate cases, also to designers and site supervisors.

Relationship With Employer and Contractor

The designer typically contracts with the employer (client). In design–build, the designer is engaged by the contractor, with roles kept distinct from the contracting authority’s project manager and the works director under the Public Contracts Code. Co-ordination and variation management follow the Code’s governance and role separation rules.

The scope of works is defined by the contract and its technical documents.

In private contracts governed under the Civil Code, the appalto (construction contract) defines the expected result. The scope of works is typically set by the employer’s requirements, drawings, specifications, and bills of quantities or unit‑rate schedules. Price may be lump‑sum or re‑measurement; if not determinable, courts may fix it by reference to tariffs or usages. Risk of loss before acceptance and rules on variations/quality are governed by the Code and the agreed technical documents.

In public works, the scope flows from the approved design levels – Progetto di fattibilità tecnico‑economica (PFTE) and Progetto esecutivo. The contract incorporates the specifications, the drawings, the metrical computations and the price list, and any Building Information Modelling requirements, where mandated. Technical specifications detail performance, materials, methods, testing and acceptance criteria. The Director of Works enforces compliance with these documents. Variations must follow the Code’s limits.

In private works, the employer may order variations that do not substantially change the nature/quantities and whose cost does not exceed one‑sixth of the contract price. The contractor is entitled to corresponding price adjustment, typically by agreed rates or new rates. Beyond that, consent is required. Time may be extended where delay is not the contractor’s fault. In public works, variations/modifications without retendering follow D.Lgs. 36/2023 Article 120. Pricing is normally by contract rates – for new items, by regional price lists or, failing that, Chambers of Commerce/market prices per Article 41. Time effects are addressed via formal time extensions.

As regards contractor‑requested variations in private works, unilateral changes are prohibited; the contractor needs written authorisation (Article 1659). “Necessary” variations (eg, to execute the works properly) are at the employer’s cost; if they exceed one‑sixth of the total price, the contractor may withdraw. In public works, the contractor’s proposals must follow the Code’s modification grounds and require approval. The pricing/time adjustments mirror the employer‑ordered path under Article 120.

Time‑related costs – if employer‑ordered changes or necessary variations cause delay in private works, the contractor may obtain an extension of time and damages for resulting prejudice under general civil code rules. In public works, suspensions/changes can justify an extension of time. Where suspensions exceed thresholds, the contractor is entitled to additional on‑costs per Article 121 and criteria in the Code’s annex.

The allocation of responsibilities depends on the delivery model and mandatory roles.

  • In the more traditional scheme (design–bid–build), the employer (committente) appoints the designer(s) to draft the feasibility plan and executive design; the contractor builds per the approved design and technical specifications; the Director of Works (DL) supervises compliance; and the Project Sole Responsible (RUP) manages the procedure for public works. Design levels and responsibilities are codified, with the executive design detailing cost and programme.
  • Design–build/EPC: the contractor assumes design and construction risk (often completing/executing the design), still subject to the Director of Works’ oversight in public contracts.
  • Safety roles (all models with multiple contractors): the employer/works responsible appoints safety co-ordinators – CSP (design) and CSE (execution) – with statutory duties to plan and verify Health, Safety and Environment co-ordination.
  • Testing/certification: structural testing (collaudo statico) is appointed by the employer. Public works also include technical–administrative testing.
  • Liability: serious defects/collapse (Article 1669 c.c.) can engage the contractor and, for professional fault, the designer and/or the Director of Works. Allocation clauses cannot waive this regime against third parties. Public contracts embed these roles and cost items in the project’s economic framework.

In Italy, responsibilities in construction derive from Articles 1655 et seq of the Civil Code and are then shaped by contract, with notable differences between design–bid–build and integrated design and build models.

Under the traditional model, the employer manages design, financing and payment, and may supervise through appointed professionals, but must not encroach on the contractor’s autonomy; liability may nonetheless arise for negligent contractor selection, undue interference or safety breaches. Labour rules also impose joint liability on the employer with contractors and subcontractors for pay and social contributions, which calls for robust compliance controls along the chain.

The contractor organises and executes the works, is liable for non-conformities, defects and third-party damage, and, absent timely warning, may also be liable for design errors.

Subcontractors are primarily liable to the contractor, with possible tort exposure to third parties.

Designers and project supervisors are liable for design errors or inadequate oversight, and concurrent liability may be apportioned among actors, based on causal contribution.

As a rule, the contractor must assess technical feasibility and verify site conditions and the adequacy of the employer’s design, and cannot rely on “geological surprise” for issues that would have been revealed by a diligent investigation. Designers must ensure feasibility of the project on the basis of adequate surveys, and project supervisors may be liable for failures in oversight during execution.

Public works add regulatory steps, including prior certification of site accessibility and the absence of impediments, without relieving the contractor of its verification duty.

Environmental rules shape risk allocation: the contractor manages construction waste and is responsible for contamination generated during the works, while the owner or employer must notify the authorities of contamination and take preventative measures, with remediation generally resting with the polluter.

Contractual risk allocation is permitted, subject to mandatory safety, environmental and structural rules.

Construction requires administrative authorisations under Presidential Decree No 380/2001 and local plans, with the building permit as the principal authorisation for major works after planning compliance checks. Simplified procedures apply to lesser works, including SCIA for certain renovations or structural changes, and CILA for non-structural internal alterations, while some minor activities fall within free building activity.

Responsibility for permits generally rests with the party holding legal title over the property and, in private contracts, is typically assumed by the employer, subject to agreement, without derogating from the regulatory framework. The permit holder, the employer and the contractor may be jointly liable for planning and building compliance, and may face sanctions for unlawful works.

Responsibility for maintenance depends on the project phase and the contract.

During execution, the contractor keeps the works in proper condition until completion and formal acceptance, consistent with the duty to perform and deliver to standard.

After acceptance, ordinary maintenance typically passes to the employer or owner, unless otherwise agreed, without prejudice to statutory liability for defects under Articles 1667 and 1669 nor to potential oversight liability of the project supervisor.

For MEP systems (mechanical, electrical, HVAC), the main contracts include post-commissioning maintenance with term, scope and remuneration. In practice, long-term operation and maintenance services are often placed under separate agreements, especially in infrastructure.

In the traditional model, the contractor executes the works, while financing, operation and management remain with the employer or are contracted separately.

In integrated structures or public-private partnerships (PPP)/concession schemes, the private operator may assume broader responsibilities across design, construction, financing, operations and maintenance for the concession term. Common models include Build–Operate–Transfer and Design–Build–Finance–Operate, grounded, for public projects, in Legislative Decree No 36/2023, with risk and obligations allocated by contract.

The extension of functions is primarily contractual. In public projects, however, it is also subject to the regulatory framework governing concessions and PPPs under the Italian Public Contracts Code (Legislative Decree No 36/2023).       

At completion, the contractor notifies readiness for inspection, and the employer undertakes verification of conformity with the contract, design and technical standards through inspections and functional tests, directly or via the project supervisor and consultants, with the contractor’s co-operation.

Formal testing (collaudo) may follow, performed by the employer or an appointed expert. If the outcome is positive, the employer proceeds with acceptance of the works and payment of the final account settlement. If defects are identified, they must be corrected by the contractor before acceptance.

Acceptance releases the contractor from liability for apparent defects, without prejudice to liability for latent defects, and triggers the contract’s concluding economic effects.

In Italian law, completion, delivery and takeover are connected yet distinct. Completion occurs when the contractor has performed the works in accordance with the contract and project documentation. Delivery occurs when the contractor places the works at the employer’s disposal. Following delivery, the employer may take possession of the works.

Takeover therefore corresponds to the employer assuming control and custody of the works, although it does not itself constitute formal acceptance, which follows conformity checks and concentrates the principal effects, including entitlement to final payment, release from liability for apparent defects and transfer of the risk of loss or deterioration to the employer.

Completion enables verification, delivery allows takeover, and acceptance consolidates legal and financial consequences.

Under the Civil Code’s appalto regime, the baseline rules differ for “ordinary” defects and for “ruin/serious defects” in immovable works.

  • Ordinary defects and non‑conformities: pursuant to Article 1667 of the Civil Code, the employer must denounce defects within 60 days of discovery (decadenza), unless the contractor acknowledged or fraudulently concealed them. The limitation period is two years from delivery.
  • Ruin and “serious defects” of buildings: Article 1669 of the Civil Code imposes a decennial liability where the work (new construction or certain significant works on an existing building) collapses in whole or in part, is in clear danger of collapse, or has serious defects affecting its stability or essential functionality. Liability lasts ten years from completion. The employer must denounce within one year of discovery, and the action must be brought within one year of the denunciation.

Under Article 1668 of the Civil Code, the employer may elect defect elimination at the contractor’s cost or a price reduction; damages are cumulative where fault is present. If the defects render the work wholly unsuitable for its intended purpose, the employer may request termination of the contract.

If the work is incomplete or the breach is more general, the employer may rely on the general law of inadempimento (specific performance, termination, damages: Articles 1453 et seq of the Civil Code).

The remedies available against the contractor also apply to the designer and the project manager, provided that the defects are attributable to acts for which they are liable (eg, design defects).

Acceptance without reservations precludes claims for apparent/recognisable defects, unless the contractor acted in bad faith. Acceptance does not exclude the warranty for hidden defects.

Parties may organise contractual procedures for quality control and defect discovery, but cannot derogate from the statutory notice periods.

Once the limitation and decadenza period have expired, the employer loses the right to bring an action against the contractor. However, if sued for the price, the employer may still raise defects defensively, provided the 60‑day denunciation was made.

Pricing methods typically used include the following.

  • Lump sum (a corpo) – a fixed overall price for the completed works. The risk of quantities lies largely with the contractor. This is frequent in private agreements, and is also standard in public works practice.
  • Unit rates (a misura) – the price is calculated by applying agreed unit prices to measured quantities. The final price varies with actual measurements.
  • Mixed structures – complex jobs often combine a corpo portion (eg, core works) with measured or open‑book items for finishes or allowances.

The contract price is typically made up of the following.

  • Works and services scope, including materials, transport, disposal, site preliminaries and general requirements.
  • Health and safety costs (oneri sicurezza), stated separately and not subject to discount.
  • Taxes (VAT) and withholdings/retention, with any price revision rules set expressly.
  • Payment practice and milestones.
  • Advance and SAL payments are standard. The contract agreements commonly provide an upfront advance at signing, interim payments a stato di avanzamento lavori (monthly or by milestones), and a final balance after testing/collaudo, often releasing a retained 5–10%. Public templates mirror this SAL approach and may reference statutory price revision clauses (now under the 2023 Code).

Practical Takeaways

Choose lump sum when the scope is well‑defined; use unit rates or mixed pricing for variable quantities.

Specify safety costs, retention, change/variation pricing and any revision formula upfront; align SAL checkpoints with measurable deliverables and certification by the works director.

Use of Price Indexation in Italy

  • Public works: price indexation is standard and mandated in public contracts through the “price revision” mechanism of the 2023 Public Contracts Code. Tenders typically state that price revision applies and set the operating rules in the tender documents and contract notice. The legal hook most often cited is Article 60 of Legislative Decree 36/2023, with discipline detailed in the procurement documents.
  • Private construction: in private contracts, automatic indexation is not typical. Many agreements adopt a fixed and non‑revisable price and expressly waive Civil Code remedies on cost spikes (including article 1664 c.c.), shifting cost‑inflation risk to the contractor. This approach is reflected in common practice, where prezzo fisso e invariabile exclude revisione prezzi and/or waive article 1664. Where permitted, adjustments usually occur only via approved variation orders or agreed new unit prices.

Allocation of Large Price Fluctuation Risk

  • Contractor‑heavy allocation: private contracts commonly place inflation and market volatility risk on the contractor, by fixed‑price clauses and express waivers of Article 1664 c.c.
  • Limited rebalancing: some private forms allow targeted re‑pricing where measurable divergences arise (eg, quantity variance thresholds) or by reference to public price lists for extra works These are negotiated on a case-by-case basis and require prior written approval.
  • Public sector balance: in public works, risk is shared through the statutory revision mechanism embedded in the procurement documents, rather than contractor‑only exposure.

Practical tip: if indexation is desired in a private deal, include a clear formula (eg, ISTAT indices), caps/floors and trigger events; otherwise, the default market position is “no automatic revision”.

Managing Late or Non-Payment

  • Contractual protections – private contracts commonly tie invoicing to certified progress (SAL) by the works director; apply a 5–10% retention released after testing/collaudo; and make payments conditional on tax/social security compliance (DURC). Many also allow the suspension of works and termination after formal notice if invoices remain unpaid, and restrict the assignment of receivables.
  • Financial remedies – late payment interest typically follows Legislative Decree 231/2002 (ECB main rate + 8 percentage points, unless higher is agreed), often referenced expressly. This applies to commercial transactions and accrues automatically when due dates are missed.

Advance, Delayed and Interim Payments

  • Advance payments are frequently used (often 10–40%) to mobilise site set-up and procurement. In larger/EPC forms, the advance may require an on‑demand bank guarantee or performance bond.
  • Interim/SAL payments are standard in Italy, commonly comprising monthly or milestone‑based payments against measured or certified progress. This is mandated in public works documentation under the 2023 Public Contracts Code and mirrored in private forms.
  • Final/“delayed” balances – a balance is commonly deferred until acceptance/collaudo, with release of retention thereafter. If the employer delays, interest per Decree 231/2002 applies, in addition to any contractual remedies.

Practical Allocation of Payment Risk

  • The employer controls timing/certification, while the contractor bears cash‑flow risk between SALs and retention.
  • Statutory backstop: Decree 231/2002 shifts the cost of delay to the debtor via automatic default interest, while public contracts embed SAL mechanics to reduce non‑payment disputes.

Typical Invoicing Mechanics

Electronic invoicing is the default in Italy. Invoices are issued in XML “FatturaPA” format and transmitted via the state exchange system (SDI). This is mandatory toward public administrations (DM 55/2013) and, since 1 January 2019, also for B2B/B2C between Italian VAT taxpayers under the e‑invoicing framework (D.Lgs. 127/2015 as amended by Law 205/2017).

Triggers and Certification

In common practice, invoicing typically follows objective triggers:

  • certified progress statements (SAL) approved by the Works Director – invoices are issued only after such approval;
  • specific milestones (eg, design approval, pre‑assembly, delivery to site) in bespoke/furniture scopes; and
  • final invoice after acceptance/collaudo, often linked to release of retention and confirmation of DURC.

Content and Attachments

Invoices commonly reference the approved SAL, measurement records and any approved variations; employers may require attachment of the SAL certificate and current DURC. Public works templates under the 2023 Code also align payments to SAL certification and contract clauses on Fatturazione e pagamenti.

Payment Cadence and Practices

Advance invoices are frequent (sometimes backed by an on‑demand guarantee), followed by monthly or milestone SAL invoices and a deferred final balance.

Payment terms are usually 30–60 days from invoice or month‑end. Late payment interest follows statutory rules if agreed deadlines are missed.

Practical Tips

Align invoice timing with clearly defined SAL/milestone evidence and name required attachments upfront.

For public clients, ensure SDI codes are correct and respect any split‑payment/VAT mechanics indicated in the tender documents.

The planning of construction works is structured primarily through contractual schedules and work programmes defining the sequence of activities and execution timetable.

The employer typically defines the overall project requirements and timetable, often through design documentation, while the contractor is responsible for preparing a detailed work programme setting out the sequencing of activities and the allocation of resources. This programme serves as the primary tool for monitoring progress and verifying compliance with the contractual completion date.

Planning is usually supported through contractual mechanisms designed to track progress, including intermediate milestones linked to specific phases of the works and periodic progress assessments.

Progress is commonly recorded through progress certificates, which confirm the portion of works completed and typically trigger interim payments.

Delays are governed primarily by the contract’s rules on programme control, extensions of time and allocation of time-related costs.

Where a delay occurs, the contractor is generally required to notify the employer and explain its causes. If the delay results from events not attributable to the contractor (such as variations instructed by the employer or delayed approvals), the contractor may request an extension of time.

Time-related costs are typically allocated by reference to the cause of the delay. If the delay is attributable to the contractor, it bears the additional costs arising from prolonged performance. Where the delay results from acts or omissions of the employer, the contractor may be entitled to both an extension of time and compensation.

Italian law does not provide specific rules on concurrent delays. Responsibility is assessed under general principles of causation: where a predominant cause of delay can be identified, responsibility is usually attributed to that cause. Where both parties contribute to the delay, courts may consider their respective contribution and apportion liability accordingly.

If delays occur, the employer may first require proper performance and request that the contractor complete the works within an appropriate timeframe.

The employer may also issue a formal notice to perform, granting a final deadline for performance. If the contractor fails to comply, or if the delay constitutes a material breach, the employer may terminate the contract and claim damages. In practice, however, termination remains a remedy of limited utility: neither party typically benefits, as it leaves works incomplete and triggers complex restitutionary obligations concerning the valuation of works performed, return of materials, and unwinding of subcontracts. These considerations render termination a remedy of last resort.

Construction contracts frequently provide for liquidated damages for delay, calculated as a predetermined amount for each day of delay, allowing the employer to obtain compensation without proving actual loss.

Employers may also rely on contractual safeguards, including suspension of payments linked to progress certificates and the enforcement of contractual guarantees, such as performance bonds.

Extensions of time are governed primarily by the contractual provisions of the construction contract.

Where events arise that may affect the agreed construction schedule, the contractor is generally required to notify the employer and submit a written request identifying the delaying event, its impact on the programme and the additional time required.

Extensions of time are typically granted where delays result from circumstances not attributable to the contractor. Common grounds include variations or design changes requested by the employer, delays in approvals or information, late handover of the site, suspension of the works ordered by the employer or public authorities, force majeure events, and unforeseen site conditions.

The duration of the extension is assessed by reference to the actual impact of the relevant event on the construction programme. Contractors usually support their request with project documentation, such as updated schedules, site records and technical reports.

Assessment is typically carried out by the employer’s technical representatives, while the burden of proof generally rests with the contractor.

Italian law does not provide a specific statutory definition of force majeure. The concept derives from the Civil Code provisions on contractual liability and impossibility of performance. Events typically regarded as force majeure include natural disasters, wars, widespread strikes, epidemics and governmental measures preventing the continuation of the works.

As Italian law does not establish a detailed statutory regime, force majeure is generally governed contractually through clauses defining qualifying events and setting out procedural requirements such as notice and mitigation obligations. The parties may specify, limit or exclude certain events from the scope of force majeure, although they cannot derogate from the general principles governing the supervening impossibility of performance.

Typical consequences include the suspension of contractual obligations, extensions of time and exemption from liability for delays caused by the event. Where performance becomes permanently impossible, the contract may be terminated under the Civil Code rules on supervening impossibility.

Unforeseen circumstances in construction contracts are governed both by statutory provisions of the Civil Code and by contractual arrangements between the parties.

Article 1664 of the Civil Code allows either party to request revision of the contract price where unforeseeable events significantly increase or decrease the cost of labour or materials. The adjustment applies only to the portion exceeding a statutory threshold – generally one-tenth of the agreed price. The same provision also entitles the contractor to equitable compensation where unforeseen geological or hydrological conditions significantly increase the difficulty of performance.

More generally, Article 1467 of the Civil Code may apply to long-term contracts where extraordinary and unforeseeable events make performance excessively burdensome. In such cases, the affected party may seek termination of the contract unless the other party offers to adjust the contractual terms on an equitable basis.

In practice, construction contracts address unforeseen circumstances through clauses on variations, unforeseen site conditions, price adjustment and extensions of time.

Italian law does not recognise “disruption” as a distinct legal category. However, events that interfere with the contractor’s planned method of execution and reduce productivity may give rise to contractual remedies under general contractual liability or specific clauses.

Where disruptive events are attributable to the employer or arise from circumstances not imputable to the contractor, the latter may rely on contractual mechanisms to seek appropriate remedies. These typically include extensions of time, recovery of additional costs, or other adjustments to the contractual framework. Significant and unforeseen increases in the cost of raw materials may trigger the application of Article 1664 of the Civil Code, which grants the contractor a right to an equitable adjustment of the contract price where such increases exceed one-tenth of the agreed consideration.

To establish disruption, the contractor must demonstrate the causal link between the relevant event and its impact on the execution of the works. This is usually supported by project documentation such as updated work programmes, site records and productivity analyses.

The burden of proof generally rests with the contractor.

Liability for wilful misconduct (dolo) or gross negligence (colpa grave) of the obligor or its auxiliaries cannot be excluded or pre‑limited in advance (Article 1229 of the Civil Code).

In standard‑form contracting, any limitation operating as a clausola vessatoria requires specific written approval under Article 1341(2) of the Civil Code in order to be effective against the adhering party. In consumer contexts, the Code of Consumption also polices certain exclusions as null.

Special decennial responsibility for ruin/serious defects (Article 1669 of the Civil Code) cannot be neutralised by contract.

Italian law recognises both concepts across contract and tort. Article 1229 of the Civil Code makes clauses excluding or limiting liability for dolo or colpa grave null. For professionals (including designers), Article 2236 of the Civil Code narrows liability to dolo or colpa grave only when the assignment involves problems of particular technical difficulty; this is a substantive standard, not a waiver.

These are mandatory rules.

Subject to the guardrails listed in 6.2 Wilful Misconduct and Gross Negligence, parties frequently:

  • adopt liability caps (often tied to contract price or insurance limits) and exclude certain heads of loss, preserving carve‑outs for dolo/colpa grave and for Article 1669 of the Civil Code;
  • use exclusive remedy constructs for defects (repair/reperformance or price reduction) while allowing damages only for fault (Article 1668 of the Civil Code);
  • agree liquidated damages for delay/performance shortfalls (Article 1382 of the Civil Code), sometimes declaring them the “sole remedy” for the defined breach; or
  • align designers’ exposure with Article 2236 and professional indemnity levels.

Enforceability turns on:

  • compatibility with Articles 1229 and 1341(2) of the Civil Code;
  • the preservation of statutory warranties (especially Article 1669 of the Civil Code); and
  • coherence with the damages framework in Articles 1223–1225 and 2059 of the Civil Code.

Parties commonly use hold-harmless (manleva) clauses to allocate construction risk, but they cannot exclude liability for wilful misconduct or gross negligence, nor for breaches of public order duties; such clauses are null under Article 1229 of the Civil Code.

Typical indemnities cover the following.

  • Third‑party bodily injury and property damage arising from works and site operations (often aligned with insurance). These cannot displace non‑delegable Health, Safety and Environmental duties/sanctions under the Code on Safety and Security on the Workplace (D.Lgs. 81/2008).
  • IP infringement (designs, methods, software, BIM objects) vis‑à‑vis employer and third‑party claims. As a basis, general contractual liability rules apply. Clauses attempting to waive liability for gross negligence remain void (Article 1229).
  • Environmental contamination, waste, water and emissions liabilities, again without excluding public order obligations.
  • Statutory defect/warranty risk allocation, although advance waivers that undermine mandatory regimes (notably decennial liability for rovina o gravi difetti under Article 1669 c.c.) are ineffective.

If indemnities are in standard terms, clauses that limit liability or restrict defences require specific written approval under Article 1341 c.c.

In public contracts, defect liability follows the Public Contracts Code and the Civil Code; indemnities cannot override mandatory defect regimes.

A mix of contractual and statutory guarantees apply.

In Public Works

A mandatory bid bond for tendering (garanzia provvisoria) is required; forms are cash deposit or surety. Regarding performance, a security (garanzia definitiva) at contract signature (typically 10% of price) is also delivered. Methods and issuers are set by the Public Contracts Code (Articles 53, 106, 117). Advance payment is conditioned on an advance‑payment guarantee. Large EPC contracts may require additional performance and termination guarantees.

In Private Works

Parties typically use surety bank or insurance guarantees (fideiussioni) and bank guarantees under Civil Code rules onfideiussione (Articles 1936 ff). Parent company guarantees are also common as contractual sureties.

Insurance

Public contracts may require project‑specific policies per tender. The Code aligns guarantee and insurance policy schemes to ministerial forms. Designers carry professional indemnity insurance, while contractors often hold Contractors’ All Risks/Erection All Risks and third‑party liability.

In contracts concerning residential units “to be built”, mandatory buyer protections apply: the developer must deliver (i) a bank/insurance guarantee securing instalments and (ii) a decennial post‑completion insurance covering Article 1669 c.c. defects due to ruin of the building.

In sum, public sector guarantees are regulatory/mandatory, while private sector guarantees are contractual but anchored in Civil Code surety rules.

In Italian projects, parties usually combine market insurance with mandatory coverage.

  • Contractors’ All Risks/Erection All Risks (CAR/EAR) policies cover sudden/accidental physical loss or damage to the works, materials and site facilities during construction. They often include third‑party liability sections for bodily injury/property damage arising from site operations. In public works, tender documents frequently require such project policies under the Public Contracts Code.
  • Third‑party liability (RCT/RCO) policies cover liability to third parties and employees (operator’s liability arising from site activities). Required levels/clauses are set out in the tender documents for public contracts.
  • Professional indemnity (designers/DL/DEC) policies cover errors/omissions in design and technical services. Liability limits cannot be contractually waived where they would exclude responsibility for design errors in public works.
  • Decennial post‑completion insurance (polizza decennale postuma) is mandatory for sales of new buildings. The developer must deliver a ten-year policy covering material and direct damage (including third‑party damage) resulting from total/partial collapse or serious defects under Civil Code Article 1669.

In private works, parties often include an express termination clause for insolvency (clausola risolutiva espressa, Article 1456 c.c.). However, “ipso facto” effects are limited by the Insolvency Code (CCII). After filing for a pre-emptive arrangement with creditors (concordato preventivo), the counterparty cannot invoke automatic termination for obligations maturing post‑filing; suspension/termination requires judicial authorisation (Article 97 CCII). If bankruptcy occurs (liquidazione giudiziale), pending contracts are stayed until the receiver elects to continue the contract or withdraw; the mere opening of the procedure does not automatically end the contract (Article 172 CCII).

If the employer is insolvent or at serious payment risk, the contractor may suspend performance for non‑payment or deteriorated financial conditions (Articles 1460–1461 c.c.).

In public works, the employer has specific statutory tools. It may resolve the contract on specific grounds (Article 122) or, where viable, may permit succession by another qualified operator in the event of the contractor’s insolvency (Article 120(1)(b)(2)). On termination, the authority can draw on the performance guarantee and recover extra‑completion costs (Article 117). These regimes are mandatory for public contracts.

Overall, insolvency provisions tend to be stricter against the contractor in public contracts, while private contracts rely on negotiated clauses constrained by mandatory CCII/Civil Code rules.

Risk sharing is common and partly mandatory.

  • In public works, contracting authorities must include a price revision clause that adjusts consideration using indices. This allocates inflation/deflation risk between the employer and the contractor per D.Lgs. 36/2023 Article 60 and its Annex II.2 methodology.
  • Contract modifications (eg, necessary variations, unforeseen events) are allowed within strict thresholds – another form of shared risk managed by statute (Article 120).
  • Health and safety – non‑delegable statutory duties of the employer/works responsible (eg, appointment of coordinators) coexist with contractors’ operational duties, creating a regulated, shared responsibility matrix (D.Lgs. 81/2008, Articles 89–90).
  • Labour/wage risk – the employer is jointly liable with the contractor (and, within limits, subcontractors) for workers’ pay and social contributions for up to two years after the contract – an express legal risk‑sharing rule (D.Lgs. 276/2003, Article 29). In private works, parties frequently agree bespoke mechanisms – target‑cost/pain‑gain share, capped remeasurement, and ground‑conditions regimes – subject to general Civil Code limits (eg, no exclusion for gross negligence/wilful misconduct). These sit alongside mandatory decennial defect liability under Article 1669 c.c., which cannot be waived to the purchaser’s detriment. Shared risks are priced through a mix of statutory mechanisms (public works) and contractual economics (private works).
  • Statutory price revision – public contracts must include a price adjustment clause. Adjustments are computed using indices and formulas set out in Annex II.2 to D.Lgs. 36/2023, which define triggers, indices, neutral/parametric components and payment modalities, allocating inflation/deflation between employer and contractor. As regards contract modifications, savings generated by design/contract changes can be used to offset cost increases, tempering the parties’ exposure; thresholds and procedures are set by Article 120. Pricing tools in tenders/contracts include:
    1. unit-rate schedules and remeasurement to share quantity/ground-condition risk;
    2. provisional sums and contingencies for employer-retained risks; and
    3. caps/deductibles in pain-gain or target-cost models (private sector practice).
  • Labour joint liability – in both sectors, employers price the statutory risk of joint liability for wages/social charges (eg, through withholdings, safety checks).
  • Insurance and guarantees – premiums and surety costs are priced into bids to address shared third‑party and defect risks required by procurement documents.

Overall, public contracts rely on mandatory indexation and regulated variations, while private contracts use negotiated mechanisms layered over Civil Code risk allocation.

Compliance framework contracts typically place full responsibility for the hiring, management, pay and discipline of site personnel on the contractor. The contractor determines compliance with employment, social security and insurance rules (INPS/INAIL), and applies the sector’s national collective bargaining agreement (CCNL). Safety obligations mirror Legislative Decree 81/2008, with co-ordination through the risk assessments and interference risk documents prepared by the parties. Workers must carry an identification badge on site, showing employer and personal data.

Core Obligations Found in Common Practice

  • Personnel standards: use of suitably qualified employees; training, PPE and medical surveillance; immediate reporting of accidents to the employer’s representative.
  • Labour compliance and DURC: timely payment of wages and contributions; delivery on request of supporting records and a valid Documento Unico di Regolarità Contributiva (DURC).
  • Control and co-operation: adherence to the employer’s site rules and directions (director of works/co-ordinator); continuous staffing and no unilateral suspension of services.
  • Subcontractor pass‑through: flow‑down of all personnel, wage and safety duties to subcontractors; main contractor remains liable.
  • Badging and site conduct: display of photo‑ID badges; right of the employer to demand removal/replacement of unsuitable or non‑compliant personnel.
  • Indemnities and set‑off: indemnification for breaches (eg, safety or payroll); ability for the employer to set off sums paid directly to workers against amounts due to the contractor.

These provisions align legal compliance with practical site control, reducing stoppages and liability exposure.

Under Italian private works contracts, subcontracting is generally permitted if expressly authorised by the employer/client and within defined boundaries. Most bespoke construction agreements condition any subletting on prior written consent, prohibit “total” delegation of the contract, and keep the main contractor fully liable for the works and safety obligations throughout. Market practice also requires the contractor to “flow down” all relevant duties to approved subcontractors (health and safety, site rules, insurance, privacy/confidentiality) and to indemnify the client against any third‑party claims arising from the subcontract. These mechanisms appear consistently across the attached forms (eg, prior consent, pass‑through obligations, continued responsibility, and indemnities).

In addition, Italian health and safety rules require specific co-ordination and documentation in multi‑employer worksites, including DURC checks and the management of interference risks; these duties apply also in cases of subappalto. Clients commonly condition consent on evidence of regulatory compliance (DURC, technical capability) and reserve remedies for unauthorised subcontracts (removal from site and/or termination for cause). Where relevant, anti-mafia and integrity verifications may also be required before approving subcontractors, especially on public or publicly supported projects. These public law filters often inform private contracts as good practice.

Best Practice Clauses

  • Prior written consent; list of approved scopes/subs; ban on further subletting.
  • Pass‑through of all contractual, HSE and insurance obligations; audit rights.
  • Ongoing main‑contractor liability; comprehensive indemnities; step‑in/removal for breaches.

Private construction contracts in Italy typically allocate IP to enable life cycle use of the works while protecting confidential know‑how. In tailored works (fit‑out, bespoke furniture, specialist systems), it is common either to:

  • assign ownership of project documents, models, designs and as‑built deliverables to the client; or
  • grant the client a perpetual, royalty‑free licence (often with sublicensing rights for operation, maintenance, refurbishment and regulatory filings).

The attached agreements reflect both approaches: some vest “every work of the mind” (drawings, designs, technical solutions) in the client with broad usage rights, while others give an express perpetual licence to the client and affiliates. Contractors are usually barred from promotional use (eg, site photos) without consent, and must return or deliver all IP materials at handover.

From a risk perspective, contracts commonly include warranties and indemnities that the contractor’s deliverables do not infringe third‑party rights, plus confidentiality covenants covering any owner‑provided know‑how. Where public law regimes apply (eg, HSE co-ordination documents), contractual IP terms coexist with statutory duties to retain and share safety documentation, but do not dilute infringement liability. These patterns align with standard Italian practice and are compatible with general IP and contract principles; see examples of confidentiality and IP ownership/return obligations in Italian construction forms, and safety documentation duties under D.Lgs. 81/2008.

In the event of a breach of the works contract, Italian law provides for various remedies for the different parties involved – ie, employer and contractor (the designer and project manager are not usually parties of the construction contract).

Employer

  • Powers to control works and set terms during execution (Article 1662 of the Civil Code). If the contractor fails to comply, the contract can be terminated.
  • Special warranty remedies: the employer may elect defect elimination at the contractor’s cost or a price reduction; damages are cumulative where fault is present. If the defects render the work wholly unsuitable for its intended purpose, the employer may request termination of the contract (Article 1668 of the Civil Code).
  • Termination of the contract on the grounds of material breach, non-conformity or defects in the work (Articles 1453, 1668 and 1669 of the Civil Code).

Contractor

  • Payment for work duly performed and for additional work or agreed variations.
  • Suspension in case of the employer’s non‑performance (Article1460 of the Civil Code) and/or for deteriorated credit risk (Article 1461 of the Civil Code).
  • Termination/damages for employer’s breach (Articles 1453 et seq of the Civil Code).

Contracting parties enjoy broad freedom to shape remedies (Article 1322 of the Civil Code), including capping damages, agreeing liquidated damages (clausola penale, Article 1382 of the Civil Code), limiting consequential heads, or structuring step‑in/rectification regimes. For instance, parties can:

  • extend or restrict the powers to make changes beyond the limit of one-sixth of the agreed price (Article 1659 of the Civil Code);
  • agree rules on economic contingencies, including by excluding price revision; and
  • regulate the procedures of the employer’s powers of control, and limit their exercise.

In public contracts, the public employer can restrict the use of subcontracting and other remedies, provided that the restriction is justified on technical grounds and assessed on a case-by-case basis. In any case, two hard stops apply:

  • clauses excluding/limiting liability for wilful misconduct or gross negligence are null (Article 1229 of the Civil Code); and
  • “vexatious” limitation clauses in standard terms require specific written approval (Article 1341(2) of the Civil Code) to be enforceable.

Partial nullity operates under Article 1419 of the Civil Code so that an invalid limitation normally does not void the whole contract.

Sole remedy clauses are not commonly used in Italian construction contracts. Such clauses are enforceable if:

  • they are not used to exonerate wilful misconduct or gross negligence (null under Article 1229 of the Civil Code);
  • they pass any form control applicable to standard terms (specific signature under Article 1341(2) of the Civil Code for limitations of liability/exceptions); and
  • they remain compatible with mandatory special warranties (eg, Article 1669’s decennial responsibility cannot be neutralised).

Courts also tend to preserve the contract by severing only the offending part (Article 1419).

Market practice (subject to the limits outlined in 9.3 Sole Remedy Clauses) often excludes or caps:

  • indirect, consequential or special damages and loss of profit, business interruption, loss of production and loss of contracts; and
  • punitive or exemplary damages (which the Italian system does not ordinarily recognise – damages follow Articles 1223–1225 of the Civil Code and non‑pecuniary recovery follows Article 2059’s restricted gateways).

Liquidated damages for delay/under‑performance are frequently used. Unless the parties agree danni ulteriori, Article 1382 of the Civil Code limits recovery to the agreed penalty.

Retention

Retention is typically excluded – and largely unnecessary – because the contractor has no retention over the employer’s immovable to begin with; retention under the Civil Code is a narrow, possession‑based remedy over movables. Contractual confirmations of “no retention over the works/site” are generally valid. In private works, financial retention (withholdings on interim payments) is a matter of agreement. Parties could contractually waive it, but if retention is embedded in standard terms, effectiveness may depend on Article 1341 of the Civil Code formalities to the extent it limits the counterparty’s rights.

Suspension

In public contracts, the power to suspend belongs to the administration (RUP/Direttore dei Lavori) and is regulated by the Codice dei contratti pubblici (D.Lgs. 36/2023) and its implementing rules.

Suspension is ordered by the administration for specified causes; if illegitimate or excessively prolonged, compensation or even termination protections apply (now Article 121 of D.Lgs. 36/2023; the DL 2018/49 also details the role and liability of the director of works in case of illegitimate suspensions). The Code now states expressly that a request to renegotiate (rinegoziazione) does not by itself justify suspension of execution – so self‑help suspension by the contractor for this reason is excluded.

In private works, parties often include “continue‑and‑claim/no‑suspension” wording. Such clauses are generally effective, but cannot override the core protections of Articles 1460–1461 when, in the concrete case, enforcing a ban on suspension would breach good faith (eg, serious non‑payment or clear insolvency risk).

Timing structure also matters: where the contract structures interim payments as autonomous obligations (SAL/acconti) independent of final acceptance, the employer’s failure to pay them may itself block reliance on exceptio by the employer and strengthen the contractor’s position.

For Breach

Under Articles 1453 ff, the aggrieved party can seek specific performance or terminate for material breach, with damages. Parties often add an express termination clause (Article 1456 of the Civil Code) for defined defaults or use a diffida ad adempiere (Article 1454 of the Civil Code). Liquidated damages may coexist.

Employer’s Free Termination (Recesso ad Nutum)

Article 1671 of the Civil Code allows the employer to withdraw even after performance starts, provided the contractor is indemnified for expenses, the value of work done, and lost profit. This is not “for breach”, so the contractor’s indemnity (including reasonable profit on unperformed works) typically applies unless the employer also proves contractor default justifying different remedies under the general regime.

Other Appalto‑Specific Levers

Variations (Articles 1660–1661 of the Civil Code) and unforeseen difficulties/price revisions (Article 1664 of the Civil Code) can be relief valves short of termination; Article 1662 of the Civil Code enables the employer to set corrective terms during execution, after which termination may be sought for non‑compliance.

If the performance of the work becomes impossible for reasons not attributable to the parties, the contract is terminated and the contractor is entitled to payment for the part of the work already performed (Article 1672 of the Civil Code).

The termination for breach of the construction contract results in the termination of the mutual obligations between the parties, with retroactive effect in accordance with the general rule laid down in Article 1458 of the Civil Code.

Unless the parties have agreed otherwise within the limits provided for by law (eg, by providing for the applicability of penalty clauses), the following applies.

  • In case of termination due to the employer’s breach, the parties must return any services already received, without prejudice to the contractor’s right to payment for work already carried out nor to compensation for any other damages.
  • In case of termination due to the contractor’s breach, the contractor must refund any advance payments unduly made by the employer and is liable to pay compensation for damages, comprising both actual damages and loss of profit, including the costs of finding a new contractor and for demolition and reconstruction of works carried out incorrectly, without prejudice to the right to payment for work duly carried out and from which the contractor has benefitted.

Termination does not affect the warranty for defects and non-conformities in the work (Article 1667 of the Civil Code), which remains enforceable for works commissioned and carried out up to the date of termination.

With reference to public contracts, termination results in the withdrawal of the contractor’s qualification certificate, and the contractor is required to reimburse the additional costs incurred by the contracting authority in awarding the works to another firm (Article 103 of Legislative Decree No 50/2016).

Italy channels construction disputes to different fora, depending on the claim and counterparty.

  • Ordinary civil courts: trial courts (Tribunale) and Courts of Appeal hear first and second instance contract/tort claims between private parties, respectively (and, where the ordinary judge has jurisdiction, some procurement-related claims). At the apex, the Corte Suprema di Cassazione ensures uniform interpretation of law.
  • Administrative courts: Regional Administrative Courts (TAR) and the State Council (Consiglio di Stato) hear challenges to public procurement measures via the accelerated procedures set forth under Article 120 of the Code of Administrative Procedure (shorter filing/decision timelines and specific rules).
  • Arbitration: private disputes may be deferred to arbitration under the Code of Civil Procedure (Articles 806 ff) if the parties so agree in an arbitration clause or in a specific arbitration agreement. For public contract disputes, the Codice dei contratti (D.Lgs. 36/2023) allows arbitration and establishes an ANAC Camera arbitrale and a list of arbitrators, with procedural rules and filings tied to Article 825 c.p.c.
  • Dispute boards (public works): a technical consultative panel (CCT) can be constituted to prevent/resolve execution disputes. In some suspensions it is mandatory, and its determinations may have contractual value (Article 808-ter c.p.c.).
  • Mediation: civil/commercial mediation may apply (D.Lgs. 28/2010). Its use is voluntary unless a subject falls within mandatory lists; so far, construction contracts do not fall within the framework of disputes subject to preliminary mandatory mediation.

Italy recognises several ADR mechanisms, which are widely used and regulated. The most relevant are as follows.

  • Arbitration is governed by the Code of Civil Procedure (Articles 806 ff). Awards become enforceable via exequatur (Article 825 c.p.c.). Arbitral clauses are common in complex private works and permitted in public contracts alongside the ANAC framework.
  • Dispute boards in public works: the Collegio consultivo tecnico (CCT) can be constituted to prevent/resolve execution disputes. It may issue determinations with contractual lodo value by reference to Article 808‑ter c.p.c., and its involvement is envisaged in key execution events.
  • Mediation: civil/commercial mediation under D.Lgs. 28/2010 is a condition of admissibility before suing in some listed matters (construction is generally not on the mandatory list unless tied to covered subjects).
  • Court‑supervised technical ADR (Article 696‑bis c.p.c.): this is a court expertise procedure, normally used as a preliminary procedural tool before filing a full fledged civil case. It also allows an expedited expert determination, which may be aimed at settlement. It is frequently used in construction disputes.
VPB Studio legale associato

Via Lanzone, 4
20123 Milano
Italy

+39 )2 7600 9000

studio@vpblegal.com www.vpblegal.com
Author Business Card

Law and Practice in Italy

Authors



VPB Studio legale associato is an independent law firm based in Milan, with offices in Rome and Hong Kong. The firm assists Italian, foreign and multinational companies, focusing particularly on small and medium-sized enterprises operating in international markets, foreign companies with current or prospective interests in Italy, and private clients investing in real estate projects in Italy, including construction, renovation and refurbishments. VPB offers expertise across numerous areas, including corporate transactions and disputes, contract law, conflict prevention and dispute resolution. The firm’s lawyers have managed complex litigation across corporate, M&A and contractual matters. In construction, the firm has advised Italian and international companies and consortia in litigation and arbitration proceedings in Italy and abroad relating to both construction contracts and the relationship between members, in industries such as hospitality and energy. Partners of the firm have acted as arbitrators in ad hoc and administered construction cases.