The Bulgarian legislative structure is contained in primary legislation adopted by the National Assembly and secondary legislation (regulations, ordinances, decrees) adopted by the Council of Ministers and respective Ministers.
Essential laws regulating construction relations, outside of the applicable EU legislation, are:
The construction contract is regulated by the SDA, which specifies the essential responsibilities of the parties. A large part of the responsibilities regulated by the SDA is of an administrative nature, and their fulfilment is necessary for the due and accurate performance of construction contracts. Matters such as payment, non-performance, liability for default, damages, compensation and penalties are regulated by the provisions of the OCA and the Commerce Act.
Ordinances regulating specific construction-related matters are:
The use of standard contracts, such as FIDIC Conditions of Contract, is not a common practice for small and/or privately commissioned construction projects in Bulgaria.
When it comes to public projects which are financed in whole or in part by international financing institutions or through funds of the European Union, the SDA expressly provides that FIDIC conditions of contract may be used by the parties. Thus, and especially in large infrastructure projects, the use of the first editions of the Red and Yellow books is relatively common and the Particular Conditions are modified in accordance with the mandatory provisions of the Bulgarian construction legislation.
Standardised documents and requirements are applicable to certain public procurement contracts.
The employer is the owner of the plot of land on which the construction is to be performed, or the person possessing an in rem right to construction or the right to construct on another person’s property by virtue of the SDA or of another special law.
In the private sector, the employer can be any privately owned legal entity or legally capable natural person(s). In the public sector, the employer is usually a governmental (minister, agency) or municipal (mayor) authority, or a publicly owned company having the right and/or charged with the operation or development of the relevant infrastructure or facilities.
The essential obligations of the employer are to:
Under the SDA, the employer is also responsible for:
The employer has the right to:
The employer generally has no direct contractual relation with the subcontractors.
Construction works are assigned by the employer on the basis of a written contract between the employer and the contractor.
The contractor is a legal entity (or a natural person), having engaged natural persons with the necessary technical legal capacity. Joint ventures are often contractors of complex infrastructure projects.
With the exception of the simplest projects, construction can be performed only by contractors – traders registered in the Central Register of Professional Builders (CRPB) with the Bulgarian Construction Chamber.
The contractor is responsible for:
and has to ensure that:
The contractor may subcontract certain types of construction and installation work or parts (phases) of the construction. Subcontractors involved in construction should be registered with the CRPB – see 2.2 The Contractor.
The relations between the contractor and the subcontractors are governed by an agreement. Generally, the subcontractor is contractually liable to the contractor and not to the employer, and the contractor is liable to the employer for the actions and omissions of the subcontractor. Nonetheless, the parties may agree that if the subcontractor is approved by the employer, the subcontractor is directly liable to the employer.
Payments to the subcontractors are usually conditional upon approval of the relevant construction works by the employer and, in some instances, conditional upon payment by the employer.
Private projects in Bulgaria are typically financed by banks through loan agreements between the bank and the employer. Such loans are usually secured by special pledge over the employer’s commercial enterprise and/or a contractual mortgage over the plot of land, the future building, or the individual premises therein.
The financier is not a party to the construction contract and does not interfere in the relations between the employer and the contractor. The payments under the financing agreement may be conditional upon reaching certain milestones.
Public projects are often financed by funds of the European Union and co-financed by the Bulgarian state.
The designer is a natural or legal person, having engaged natural persons with the necessary designers’ capacity. All architects and engineers, who prepare the designs for the construction, shall be registered with the Chamber of Architects and the Chamber of Engineers in the Investment Design respectively. In general, architects and engineers from EU member states, EEA states, Switzerland and third countries can exercise their profession in Bulgaria subject to recognition of their professional qualification.
The designer is responsible for:
The designer performs the author’s supervision and is liable for its actions in this regard.
The instructions of the designer relating to its copyright, for the accurate performance of the investment designs, are registered in the order book and are mandatory for all participants in the construction process. The relations between the employer, the designer and the contractor are outlined in 3.3 Design.
The scope of works depends on the type of contract. Under contracts for construction, the scope of works usually encompasses all construction works necessary for the completion and commissioning of the construction in accordance with the designs and bill of quantities, at the risk of the contractor and with the contractor’s own materials.
Under design-and-build contracts, the employer usually provides its requirements/technical specification, as the scope of works covers the preparation of all design in accordance with the requirements/specifications of the employer, the procurement of the necessary materials, and the performance of all construction works needed for the completion and commissioning of the construction.
In the private sector, the parties are free to agree on the circumstances that lead to a change in the scope and price of the contract, as well as the relevant mechanisms for their determination.
In the case of business frustration – meaning circumstances which arise after the contract is concluded – which the parties could not and would not be obliged to foresee, the continuation of the contract is contrary to justice and good faith, and either party may request the court to modify the contract in whole or in part.
Variations Requested by the Employer
The variations in the scope of works as a result of a change in the employer’s investment intentions, a change to the design or assignment of additional works, result in concluding of an additional agreement on the scope, cost and time for those additional works.
Variations Requested by the Contractor
The contractor has two statutory options under the OCA to request scope and price variations.
The contractor shall be entitled to an adjustment of the price if, during the term of the contract, the duly determined price for the material or labour is changed, notwithstanding that the price has been agreed in full.
In the event of additional unforeseen works necessary for the performance of the contract and resulting from various technological reasons or from mandatory prescriptions of control bodies, the contract price shall be adjusted.
Variations in the scope and price of contracts under the PPA is permitted in the special provisions of the PPA.
Under contracts for construction, the responsibility for the designs’ preparation vests with the employer. The contractor shall review the designs and immediately notify the employer of any deficiencies therein.
Under design-and-build contracts, the contractor is responsible for the designs’ preparation.
The contractor is responsible for carrying out the construction in accordance with the approved designs.
The Bulgarian legislation prohibits the same person from participating in the construction process both as a designer and as a builder.
The designs are prepared on the basis of a written contract. The technical assignment/specifications or other requirements of the employer usually form part of this contract.
The essential responsibilities of the employer, the contractor, the subcontractor and the designer are outlined respectively in 2.1 The Employer, 2.2 The Contractor, 2.3 The Subcontractors and 2.5 The Designer.
Another participant with essential responsibilities is the consultant, who:
When the consultant exercises construction supervision, it is responsible for:
Typically, the employer is responsible for the status of the construction site and for carrying out the relevant pre-design studies of the construction site.
In design-and-build contracts, these responsibilities may be shifted on a contractual basis to the contractor. Thus, any studies done in advance by the employer constitute part of the contract and the contractor is responsible for ensuring the compliance of the designs with such studies. The party responsible for preparing the designs shall ensure that the designs meet the requirements of environment conservation, biological diversity, cultural heritage and other laws.
Prior to the opening of the construction site, the employer is responsible for preparing a construction waste management plan (if required) and a health and safety plan.
The opening of the construction site is ascertained by a relevant protocol under Ordinance No 3.
All construction (except the simplest types of works) requires the issuance of a construction permit, prior to commencement. The issuance of the construction permit usually implies the preliminary approval of the designs for the construction project, and the completion of all of the necessary approval and co-ordination procedures and the obtaining of the necessary conformity assessment reports. Depending on the type of agreement between the parties, these can be either the employer’s or contractor’s responsibilities.
The construction permit is issued to the employer and the employer is responsible for obtaining it.
In some cases, the employer assigns to the contractor the procedure for obtaining the construction permit and/or the parties agree on specific rights, obligations and liability for default provisions with regard to obtaining the construction permit.
Until the handover and acceptance of the construction works, the contractor is responsible for their maintenance.
After completion of the construction but prior to its commissioning, a technical passport must be drawn up, detailing the basic characteristics of the construction, the means for its maintenance, the terms for carrying out relevant repair works and guidelines and instructions for its safe operation. The maintenance means entail the scheduling, implementation and/or documenting of:
The provisions of the technical passport are mandatory to the employer. In some large infrastructure projects, the maintenance of the construction is contractually assigned to a specialised maintenance company or an SPV.
The employer is responsible for maintaining the technical condition of the construction in accordance with the essential construction requirements and shall not allow or perform any changes to the construction which could lead to the deterioration of the designed levels of compliance.
It is not common in Bulgaria (excluding large infrastructure projects) for the employer to assign functions to the contractor other than the performance of the construction works (in contracts for construction) and the preparation of the designs (in design-and-build contracts).
A major exception is the concession for construction contracts, where the concessionaire (contractor) is assigned the performance of the construction works against the right of the contractor to operate the construction subject to assuming the operational risk.
Testing is not mandatory for all types of construction works.
In accordance with the provisions of the relevant agreement, tests are generally required for production facilities and other construction projects with a specific purpose. Where machines and equipment are installed as part of the construction works, they need to be tested individually.
The successful completion of the tests is the responsibility of the contractor.
The tests have to be successfully completed prior to the commissioning of the construction. If parts of the construction can be used independently, the construction contract may provide that the tests for these parts can be completed prior to the full completion of the construction.
The successful completion of the tests is ascertained with the relevant protocols for testing.
Upon completion of the works, the executive documentation shall be prepared (reflecting the non-material deviations from the approved designs) and shall be certified by the relevant participants in the construction process, and shall be handed over to the authorities that have approved the designs.
Thereafter, an ascertainment act under Ordinance No 3, certifying that the construction is executed in accordance with the approved investment designs, the certified executive documentation and the material requirements for construction, shall be drawn up. Where tests were carried out, the protocols for testing shall also be attached to this protocol.
By virtue of law, this ascertainment act also serves as a protocol for acceptance of the construction works by the employer. The employer has the right to use the construction only after its commissioning with a use permit or commissioning certificate.
The contractor bears liability for defects and warranty liability. The two types of liability are of different legal natures and they exist and are extinguished independently from one another.
Liability for Defects in Works
Visible defects
At acceptance, the employer shall diligently examine the works within due course and immediately make all objections for inaccurate execution of the works. If no such objections are made, it is deemed that the works are accepted.
Hidden defects
In cases that the defects cannot be discovered within the course of an ordinary examination or defects appear later, the employer shall notify the contractor of the defects immediately upon their discovery. No additional notification shall be necessary if the contractor has known of the defects.
In case of visible or hidden defects, the employer has the right to request:
In case that the deviations from the assignment or the defects are irremediable and so material that the works are not fit for their agreed or ordinary purpose, the employer has the right to rescind the contract (see 9.6 Termination) and is entitled to compensation under the general rules.
The contractor remains liable to the employer for defects for a period of five years from the date of acceptance, after expiry of which term the above-mentioned rights of the employer are extinguished.
Warranty Liability of the Contractor and Warranty Terms
Warranty liability of the contractor is an obligation to ensure that for a certain period of time the construction and installation works, facilities and construction will retain their properties and qualities. Ordinance No 2 sets out minimum warranty terms, during which the contractor bears warranty liability. The warranty period depends on the type of construction and ranges from two to 13 years. All warranty periods start to run as of the date of commissioning of the construction. In the construction contract the parties can agree to warranty periods longer, but not shorter, than those under Ordinance No 2.
In respect of liability for defects in design, see 3.3 Design, 7.5 Risk Sharing and 9.1 Remedies.
The contract price is an essential element of the construction contract and can be determined using the following methods:
The contract price entails the amounts of all the direct costs plus profit.
Milestone payments are often used and are tied to reaching a certain milestone or completing a certain type of work. They are linked to the time periods (according to the programme) for reaching a certain stage or part of the works and form an appendix – an integral part of the contract.
In recent years, indexation clauses have been increasingly used in privately commissioned construction contracts.
Usually, the contractor bears the risk of substantial increase of the price of material or labour used. In addition to indexation (insofar as applicable), as per COA, the contractor is entitled to an adjustment of the price if, during the term of the contract, the duly determined price for the material or labour is changed, notwithstanding that the price has been agreed in full.
In public procurements, the price of a public procurement contract (PPC) for construction can be amended in cases where the prices of essential goods, materials and services, which form the price of the contract, have been substantially increased because of inflation. The amendment is subject to the availability of financial resource and is done in accordance with a methodology, approved by the Council of Ministers.
Any amendment to the price shall be reflected in a relevant additional agreement (annex) to the PPC.
The payment schedule is subject to negotiation between the employer and the contractor and generally the price is divided into instalments, including: advance payment, one or more interim payments and final payment.
Usually, the contract provides for an advance payment, which is used by the contractor for covering the initial expenses necessary for the construction. It is usually made prior to the opening of the construction site and is conditional upon the provision by the contractor of a security in the form of a guarantee deposit, retention money or a performance bank guarantee and the agreed insurances.
The largest portion of the contract price is paid in the form of one or more interim payments. Such payments are often conditional upon the reaching of a certain stage of the construction and acceptance by the employer of the relevant works completed up to that stage.
The final payment is usually made can upon completion of the works and their acceptance by the employer or upon commissioning.
The contractor can seek securitisation of its receivables – most commonly by a bank guarantee and less often by a promissory note.
Typical measures for managing late payment are compensations in the amount of the statutory interest for delay or liquidated damages. The contractor is also entitled to objection for non-performance of counter-obligation (see 9.5 Retention and Suspension Rights), or rescindment of the contract (see 9.6 Termination).
Invoicing conditions typically follow the agreed payment conditions, taking into account the provisions of the Value Added Tax Act. The invoicing of the interim payments usually follows the drawing-up of relevant ascertainment acts and protocols under Ordinance No 3 or the issuance of a relevant payment certificate, as the invoices need to be prepared in line with these documents.
The time for completion, as well as any interim deadlines, are essential in the construction contract. Strict administrative regulation and the principles of documentation and supervision of the construction process imply the need for planning and preparation of a programme (or schedule).
The programme can be prepared by the employer or by the contractor on the basis of the design, the employer’s requirements or the financing conditions. Once agreed between the parties it shall be an appendix to the contract.
Observing the time for completion and the programme are usually secured by liquidated damages for delayed performance, by linking the contractor’s payments to the milestone under the programme, by objection of the employer for a breach of contract.
Adherence to the programme is controlled by the employer and is ascertained by the relevant acts and protocols in accordance with Ordinance No 3 and by bilaterally signed protocols.
The construction process entails the completion of multiple procedures, works and activities within multiple periods, all of which may be delayed.
Delay of the Contractor
Generally, the contractor is in delay if it fails (by reason for which the contractor is responsible), within the agreed time, to perform the works or to hand over the works, executed in accordance with the contract.
The remedies available to the employer in case of delay of the contractor are outlined in 5.3 Remedies in the Event of Delays.
Delay of the Employer
The most common cases of delay of the employer are cases where, within the agreed time, the employer fails to:
The remedies available to the contractor in case of delay of the employer are, most commonly:
In case of delay by one of the parties, the other party shall serve a written notice, providing an appropriate time for performance. Many contracts provide for timely notifications to the other party of circumstances which could lead to delay. To avoid delays, periodic progress meetings and/or the submission of progress reports may be provided.
Delay by Reasons for Which the Party is Not Responsible
Generally, a party is not liable for delays by reason not attributable to the party’s default: see 5.5 Force Majeure, 5.6 Unforeseen Circumstances and 9.6 Termination.
Delays by reasons for which the contractor is not responsible have, as a consequence, an extension of time.
By virtue of law, in cases of the contractor’s delay, the employer is entitled to:
Special contractual provisions relating to contract terminations are also commonly used.
Liquidated damages are another commonly used contractual remedy.
In cases where both parties are in delay and the counter obligations are not conditional upon one another, each of them is entitled to rescind the contract and no compensation is due.
The contractor shall notify the employer of the reasons for an extension of time and the consequences thereof. In case of some of the grounds for extension of time which are due to the delay of the employer, the contractor also has the option of raising an objection for non-performance of counter obligation (see 9.5 Retention and Suspension Rights).
Generally, the grounds for extension of time are:
Some of the above-mentioned grounds are also grounds for suspension of construction. In such instances, for the suspension of the construction, a relevant act under Ordinance No 3 shall be drawn up and signed, which proves both the existence of a circumstance which leads to extension of time and its duration. The existence of a force majeure event can be proven through a certificate of force majeure, which is issued by the Bulgarian Chamber of Commerce and Industry.
Under Bulgarian law, force majeure is defined as an unforeseen or unavoidable event of extraordinary nature, which has occurred after the conclusion of the contract, is of a temporary nature and results in the impossibility of performance.
The Bulgarian legislation does not contain a list of events classified as force majeure. These generally include: natural disasters, state of war, labour strike, etc. The parties are entitled to specify events that they consider being or not being force majeure events.
The consequences of force majeure include:
If the force majeure lasts long enough so that one of the parties no longer has interest in the contract, this party is entitled to unilaterally terminate the contract (see 9.6 Termination).
The PPA provides that “unforeseen circumstances” are circumstances that have occurred after the conclusion of the contract, could not have been foreseen taking due care, are not a result of an action or omission of the parties, but render impossible the performance of the obligations under the agreed conditions. The presence of unforeseen circumstances is one of the grounds for amendment of the PPC, which is otherwise generally inadmissible.
The legally defined term “unforeseen circumstances” is applicable to PPC, but not to all construction contracts. However, based on the freedom of contract principle, the parties may contractually define what they would consider “unforeseen circumstances”.
Bulgarian legislation does not acknowledge disruption in the meaning of disturbance, or change in the originally planned execution, which leads to lower efficiency in the execution, respective to costs associated with it. There are no established methods for disruption evaluation.
The principles of accurate performance and good faith, of co-operation between the parties, of sequency and conditionality of the counter obligations are applicable to the construction contracts which usually contain clauses for compliance with these principles and that neither party will prevent the other from accurate performance of its obligations.
Pursuant to the ОСА, any provisions which limit or exclude in advance the debtor’s liability for gross negligence or wilful misconduct are considered invalid. Further, any exclusion of the liability of the parties for non-compliance with the statutory requirements would also be deemed invalid. Any exclusion or time limitation of the warranty liability of the contractor is invalid.
Both the concept of wilful misconduct and gross negligence exist in the Bulgarian legal system and are governed by mandatory provision of law as follows.
In general, the Bulgarian law allows for certain limitations of liability, subject to the restrictions outlined in 6.1 Exclusion of Liability.
Most commonly, the parties agree on capping the liquidated damages potentially due under the contract. However (if not agreed otherwise), if one of the parties suffers damages greater than the amount of the agreed liquidated damages, the injured party is entitled to seek compensation for the damages exceeding the amount of the liquidated damages, even if this is not expressly agreed in the contract.
In addition to the insurances of the contractor (see 7.3 Insurance) and the remedies available in case of default, which include compensation in case of contract non-performance (see 9.1 Remedies) and based on the freedom of contract, the parties may provide for certain risks associated with the performance of the construction contract, in the occurrence of which one of the parties owes indemnity to the other. Such indemnity clauses most commonly refer to the risk of claims of third parties for protection of intellectual property rights or tort claims of third parties that have suffered personal injury or property damage in connection with the construction works.
With the exceptions mentioned below, in Bulgaria the parties have the freedom of contract to negotiate the type of guarantees which each of them should provide and the manner of the guarantees’ provision.
Guarantees of the Contractor
In private projects, at the tender stage, the participants may be required to provide a deposit or a bank guarantee. These serve as a collateral to the employer in the event that the participant in the tender procedure is chosen as contractor, but refuses to conclude the construction contract.
The provision of the advance payment is sometimes subject to the granting of a bank guarantee or a guarantee deposit by the contractor in order to ensure that the employer would be able to recover the amount paid in advance, should the contractor fail to fulfil its obligations.
Performance guarantees, corporate guarantee, guarantee deposits, and retention money are other commonly used forms of guarantee in Bulgaria.
Guarantees of the Employer
The payment obligations of the employer are most often secured by means of bank guarantees, and less often by promissory notes.
Special Provisions
As per the special provisions of the PPA, a guarantee shall be provided in the form of a cash deposit, bank guarantee or insurance securing performance by covering the liability of the contractor. An insurance can be provided only in a case where the amount of the advance payment or performance security is up to BGN500,000. The amount of any performance guarantee shall not exceed 10% of the contract value. A guarantee securing the advance payment shall be in an amount of the advance payments.
By virtue of law, the contractor, the designer, the person performing technical supervision on “Structural”, the person exercising construction supervision, and the consultant are required to obtain a professional liability insurance.
This insurance generally covers the damages caused to other participants in the construction and/or third parties as a result of unlawful acts or omissions of the insured person during or in connection with the performance of its obligations.
The following risks are not covered by the professional liability insurance:
The parties are free to negotiate other types of insurances such as: insurance of the contractor covering the liability with regard to the specific construction site, additional insurance covering the material damages on the construction, the materials, the on-site construction machinery and equipment during the term of construction (if these are paid by the employer or are its property).
The contractor shall also furnish а work accident insurance.
Construction All Risk (CAR) insurances are also commonly accepted.
In construction contracts it is generally agreed that if insolvency proceedings are opened against one of the parties, or one of the parties is declared insolvent, the other party has the right to rescind the contract.
In the event that the contractor is declared insolvent, it shall be de-registered form the Central Professional Register of the Builder.
The following (without limitation) provisions may also have a reflection on the relations between the parties in case of insolvency.
Aside from the contracts under FIDIC forms of contract, the risk-sharing model is not a common practice in Bulgaria. However, the Bulgarian laws contain multiple provisions relating to risk allocation, such as:
A risk, which by virtue of law is borne by one of the parties, can be shifted to the other party based on the principle of freedom of contract. In cases where the risk is transferred from the employer to the contractor, this is generally associated with an increase of the contract price (particularly in cases where a lump-sum price model is used). The inclusion of provisions, regulating the payment of contingencies (up to a certain amount) or reimbursement of certain costs, outside of the contract price is another commonly used method of pricing the risks shared between the parties.
Generally, it is agreed that the contractor shall ensure the necessary personnel are available, and that all employees engaged in the construction have the required professional qualification, knowledge and experience. In design-and-build contracts, the contractor shall ensure that the engineers and/or architects charged with the preparation of the designs have the required designer’s capacity.
It is usually agreed that the contractor is under the obligation to comply with the relevant occupational health and safety, traffic safety, fire protection, sanitary and hygiene requirements, including to provide the relevant protective clothing, equipment and specific instructions, where the nature of the works so requires.
In large construction projects the tender documentation often requires that the participant designates key experts with specific areas of expertise.
Unless agreed otherwise, the contractor has the right to subcontract certain types of construction works or parts (stages) of the construction.
Typically agreed contractual limitations to subcontracting are:
In public procurements the employer may specify that a portion of the procurement (up to 30% of the value) shall be done by subcontractors. The contractors may offer involvement of subcontractors for a larger portion. The contractors are required to indicate in advance the subcontractors that will be used. Specific conditions for the use of subcontractors in concession construction contracts are contained in the Concessions Act.
All approved architectural designs, approved urban development designs, maps, schematics, plans and others relating to architecture and spatial development are considered objects of copyright.
The natural person who has created the designs is their author and has the title of all authorship rights.
The following contractual provisions are often included in the contracts.
In the event of breach of the construction contract, the affected party can resort to the following remedies.
Remedies available to both parties:
Remedies available to the employer:
Remedies available to the contractor:
The compensations under the first two bullet points above cover incurred loss and the loss of profit to the extent the same are a direct and immediate consequence of the contract non-performance and could have been foreseen upon the obligation arising. Where a party seeks compensation for loss of profit as a result of delay in the construction, the obtaining of such profit needs to be certain, and such certainty is not presumed.
Although the parties may agree on restricting the remedies available, they cannot agree to waiving, limiting or excluding:
The parties cannot agree on waiving in advance or excluding the right to lodge a claim in the event of breach of contract.
The parties may agree on:
With the exception of the exclusive liquidated damages clause, the parties may not limit the applicability of types of remedies available by virtue of law.
The use of sole remedy clauses in construction contracts is not a common practice in Bulgaria. The parties can agree on an exclusive liquidated damages clause, which provides that in the event of breach of contract the defaulting party’s liability will be covered by the exclusive liquidated damages and that it will not owe any other compensation (unless the damages have been caused as a result of wilful misconduct or gross negligence, in which case the defaulting party shall owe compensation).
The liability of the parties is limited to the incurred loss and the loss of profit to the extent the same are a direct and immediate consequence of the contract non-performance and could have been foreseen upon the arising of the obligation. If the defaulting party has acted in bad faith, it is liable for all direct and immediate damages (regardless of whether they could have been foreseen or not).
The parties are not liable for indirect, non-consequential damages (ie, in cases where the cause-and-effect link between the contract breach and the damages has been interrupted).
Excluding certain forms of damages on a contractual basis is not a common practice in Bulgaria.
Retention rights (on real estate and commercial liens) are not applicable to the construction contract.
Suspension rights are usually used in construction contracts. The general applicable rule is the objection for non-performance of counter-obligation set out in the OCA. By exercising such objection, either party to the contract may refuse to perform its enforceable obligation until the other party has performed its counter-obligation. The contractor may suspend the works until due payment is performed or until the necessary assistance or provision of construction machinery or materials (if provided by the employer) is received. Accordingly, the employer may suspend the due payments in the event of non-performance of the works due.
The SDA contains a special rule enabling the employer to suspend all payments due in the event of failure by the contractor to maintain professional liability insurance.
Termination herein means any termination of the contractual relationship.
In Respect of a Construction Contract in the Private Sector
General grounds:
Special grounds for termination of construction contract:
Special grounds for termination are provided for in the PPA and the Concessions Act in respect of PPC and concession contracts, respectively.
Special grounds for termination are provided for in respect of works awarded by way of a works concession.
Unless the parties have agreed otherwise, construction disputes are resolved under claim proceedings before a court under the general rules of the CCP.
The courts of first instance are:
Unless agreed otherwise, the local jurisdiction of the courts is determined by the seat and/or permanent address of the defendant.
The first instance judgment is subject to appeal before the relevant district court or the relevant court of appeal, and in the presence of the grounds for cassation appeal – before the Supreme Court of Cassation of the Republic of Bulgaria.
Arbitration is the most preferred alternative means of resolving construction disputes in the private sector.
Disputes relating to contracts awarded under the PPA are also subject to arbitration.
Arbitration is governed by the ICAA, which establishes mandatory prerequisites for arbitration.
The parties usually specify in the contract a standing institutional arbitration which shall solve all disputes that may arise between the parties. The arbitration agreement shall be in a written form. The arbitral award is final, has the force of res judicata and is enforceable. It is subject to annulment by bringing a claim for annulment on the grounds exhaustively set out in the ICAA before the Supreme Court of Cassation, which cannot consider the merits of the dispute. Foreign arbitral awards and agreements are subject to recognition and admission for enforcement in the Republic of Bulgaria, following a three-instances judicial proceeding.
Mediation is another method for dispute resolution in construction expressly regulated by the MA.
The settlement reached on a legal dispute in the mediation proceedings has the force of a court settlement and is subject to the approval of the regional courts in the country.
9 Hristo Belchev Street
Floor 2
Sofia
1000
Bulgaria
+359 2986 79 07
vpenkova@penkova-partners.com www.penkova-partners.comIn the wake of the COVID-19 pandemic, just as the construction sector had returned to its upward trend, the war in Ukraine caused disruptions in the supply chains and – consequently – substantial increases in the costs of some essential goods and materials for construction. In turn, this became a cause for serious concern for contractors, who, in general, bear the risk on substantial increase in the price of materials, goods and labour.
As a response, in 2022, changes were made to the Public Procurements Act (PPA), which allowed for indexation of the price of public procurement contracts for construction.
Indexation of the Prices of Public Procurement Contracts for Construction
In the second half of 2022, changes to the Public Procurements Act (PPA) were made providing that the price under a public procurement contract can be amended, where as a result of inflation the prices of essential goods and materials, which form the price of the contract, are substantially increased. Pursuant to the aforementioned amendments, the Council of Ministers adopted a Methodology (the “Methodology”), detailing the procedure and formula for indexation of the prices under public procurement contracts for construction.
However, the practical application of the Methodology showed that the legal framework at the time limited, or in some cases, disallowed some contractors from benefiting from indexation. Another issue was that the initial version of the Methodology provided that subject to indexation were the prices of works, which have been accepted by the employer. This meant that some contractors were put in a disadvantageous position, as the entitlement to apply for indexation was conditional upon the specific terms of the contracts regulating the acceptance of the works.
Thus, in 2023, another set of amendments to the PPA and the Methodology were made further to the feedback from the construction sector, allowing contractors to apply for indexation for works that have been completed (regardless of whether or not they have been accepted by the employer). Some limitations to the total value of the price increase (indexation) for which the contractor could apply, were also repealed.
The Methodology aims to compensate the substantial increase of the costs of essential goods and materials, included in the formation of the price of a public procurement contract for construction. The Methodology, however, does not regulate an increase of the costs of services included in the price of a public procurement contract.
Pursuant to the Methodology, the prices of construction and installation works completed after 30 June 2021 shall be subject to indexation.
The indexation is done in accordance with a formula, taking into account:
For the purposes of indexation, the parties to the construction contract shall draw up and sign trimester reports, specifying the type, quantity and value of the construction and installation works during the relevant trimester.
At the time of the initial adoption of the Methodology (2022), the PPA provided the that the increase (or the total value of all increases) of the price of a public procurement contract due to unforeseen circumstances cannot exceed 50% of the value of the main contract. That meant that some contractors could not benefit (fully, or some contractors at all) from the indexation, as the price of their construction contracts had already been amended on another grounds. In 2023, amendments to the PPA were made, providing that the limitation whereby the price of a public procurement contract due to unforeseen circumstances cannot exceed 50%, does not apply to the cases of amendments as a result of indexation. However, it was also provided that where the price of the public procurement contract is adjusted due to indexation, the increase (or the total value of all increases) of the contract price due to indexation cannot exceed 50% of the value of the main contract.
Other Amendments to Public Procurement Act
In October and December 2023, other amendments to the PPA were made, introducing changes related to:
Changes have been made to the maximum amount of the performance guarantee, which may not exceed 10% of the contract value, and the requirement to provide a guarantee for the full amount of the funds advanced.
Amendments to the PPA were made with regard to contracts for which financing has not been secured at the opening of the procedure and the contracting authority has disclosed this circumstance. In accordance with the amendments, in such instances the performance of the contract shall commence after confirmation by the contracting authority of the secured financing and the provision by the contractor of the relevant performance guarantee. Failure to submit the performance guarantee within the time limit specified by the contracting authority, without objective reasons, shall lead to termination of the contract by the contracting authority. In the event that, after a period of three months from the date of conclusion of the contract, financing has not been provided, either party may request termination of the contract without notice. If financing has not been provided after a period of ten months from the date of conclusion of the contract, the contract shall be considered terminated by virtue of the law.
Furthermore, multiple bills for adoption or amendment to essential laws in the construction sector were submitted. These bills are in performance of the measures provided under the National Recovery and Resilience Plan of the Republic of Bulgaria, with the aim of improving the regional development and the business environment in the country.
Digitalisation of the Construction Sector
The digitalisation of the construction sector is recognised as crucial for meeting the goals of the European Green Deal, such as enhancing energy efficiency in construction material production and providing comprehensive product information through electronic passports for both products and buildings. According to the strategic plan for “Digital Transformation of Bulgaria from 2020 to 2030”, the digital shift of the construction industry aims to implement circular economy principles, sustainable building practices, energy efficiency and carbon footprint minimisation. Additionally, digitalisation is a tool for achieving a more balanced energy landscape by integrating renewable energy sources and smart grid technologies to regulate building energy usage, ultimately reducing greenhouse gas emissions.
To that end and in performance of the National Recovery and Resilience Plan 2022–2026, the Ministry of Regional Development and Public Works is preparing:
In 2023, the Bulgarian government developed and adopted a National Strategy for the Transformation of the Bulgarian Construction Sector and a roadmap for its implementation. The Strategy provides for a digital transformation of the construction sector by 2030 through:
Creation of conditions for effective electronic administrative services in the investment process
The improvement of the efficiency of administrative services requires the creation of the necessary regulatory conditions and IT infrastructure for the provision of electronic administrative services in spatial planning, investment design and construction permitting by setting up a unified public register for spatial planning, investment design and construction permitting (a “unified public register”) and a unified information system for spatial planning, investment design and construction permitting (a “unified information system”); digitalisation of existing spatial plans and integration into a common spatial data base.
The establishment of a unified public register on the website of the Ministry of Regional Development and Public Works was introduced by an amendment to the Spatial Development Act of February 2021. It is provided that this register shall bring together the various administrative acts issued pursuant to the Spatial Development Act. The conditions and procedure for publishing and keeping up to date the information in the register shall be determined by a regulation of the Council of Ministers, which had not been adopted as at 18 April 2024, and the unified public register had not been created.
The project for the creation of the unified information system, which intended to manage the processes of application, electronic signing, co-ordination, approval and delivery of the final administrative act and to provide the opportunity for submission and approval of draft development plans and investment designs is included in the National Recovery and Resilience Plan. As at 18 April 2024, the conceptual model for the creation of the system had been adopted.
An amendment to the Spatial Development Act provided for the development of the specialised spatial data information systems of the Geodesy, Cartography and Cadastre Agency, including the establishment of the Spatial planning portal, as a central, web-based information system that ensures the publication of draft spatial plans, their amendments and plans that have entered into force. The regulation that shall govern the terms and conditions for the publication of acts and documents on the portal had not been adopted as at 18 April 2024.
Another objective aimed at the creation of conditions of effective electronic administrative services is the update and upgrade of the Register of Landslide Areas on the Territory of the Republic of Bulgaria with a Register of Areas with Abrasion and Erosion Processes on the Black Sea and Danube Coasts.
Implementation of level two of BIM in investment design and construction
The use of BIM in the survey, design and construction process has been promoted by the Bulgarian government to optimise design, protect the environment, improve the quality of construction, modernise the construction sector and to reduce costs. The introduction of BIM as part of the digital reform of the construction sector is in its initial phase.
Preparation of amendments to acts and regulations related to the digital reform of the construction sector
In March 2024, a bill for amendment and supplementation of the Spatial Development Act was submitted to the Bulgarian Parliament for consideration.
The purpose of the proposed amendments is to:
At the end of March 2024, and in continuation of the measures taken in connection with the digitalisation of the construction sector, the Ministry of Regional Development and Public Works has submitted for consideration a bill for amendment and supplementation to the Cadastre and Property Register Act (the CPRA), with the aim to relieve the administrative burden for citizens and businesses. The main objective of the bill is to introduce a new approach to the provision of services with cadastral, geodetic and specialised data and to create a new legal basis for the development of specialised spatial data information systems.
Amendments to the laws and regulations related to the digitalisation of the construction sector, as well as the creation of relevant regulations to govern the operation and maintenance of the relevant registers and information systems are expected from the construction sector and stakeholders, which require the relevant amendments to the legal framework to achieve a precise legal regulation, carried out in compliance with the applicable special provisions of law and securing access to the relevant information systems.
New Act to Allow for Construction of Offshore Wind Farms in Bulgaria
In December 2023, a bill on the Renewable Energy in Marine Spaces was submitted to the Bulgarian Parliament for consideration. The purpose of the bill is to regulate the procedures and principles for planning, construction, operation and removal (at the end of their life cycle) of electrical power plants in the marine spaces of Bulgaria.
In accordance with the bill, the Minister of Energy shall assign the preparation of a Plan for Development of Marine Electrical Energy Capacities. The plan shall specify the priority zones for construction and operation of marine electrical energy capacities (offshore wind farms). The plan shall also provide for the initiation of concession procedures for wind farms with a capacity of not less than 1 GW until 2027 and for not less than new 2 GW for the period 2027–2030. The provisions of the plan shall also guarantee a constant increase in the installed capacities.
The bill provides that the right to construct and operate an offshore wind farm in a priority zone is to be granted on the basis of a concession contract.
On the other hand, the right to develop offshore wind farms in non-priority zones is to be done on the basis of a special permit, allowing its title to carry out all necessary pre-design studies, place temporary facilities in the provided area for carrying out the studies and be granted a concession-by-right for construction and operation of an offshore wind farm.
As at the date of writing, the bill has been accepted by the Bulgarian Parliament at first reading.
Amendments to the Cultural Heritage Act to Simplify Administrative Procedures and to Ensure Better Protection of Cultural Heritage
In March 2024, a bill of amendment and supplementation of the Cultural Heritage Act was submitted to the Bulgarian Parliament for consideration. The World Heritage Center has drawn the attention of the Bulgarian state to the need to include in the national regulatory framework texts on the assessment of the impact on cultural heritage, as well as other texts related to the protection of world heritage sites.
On the other hand, the aim of the amendments to the Cultural Heritage Act is to ease investors, designers and contractors, by optimising and improving the procedures for co-ordination of investment designs and requests for interventions in protected territories for the protection of cultural heritage.
The purposes outlined above are to be achieved by the following amendments proposed by the bill.
The Bulgarian Construction Sector Overcomes the New Challenges Placed Before the Industry
In accordance with the annual economic report of the construction sector for 2023, prepared by the Bulgarian Construction Chamber, the construction sector marked growth in the total monetary value of construction (building and engineering construction), the total number of construction permits issued, the number of PPC and the number of constructions started.
The Economic Policy Institute Forecasts Overall Growth in the Construction Sector for 2024
According to published information, the civil and non-residential construction segments in Bulgaria are expected to grow by 2025. On the other hand, the residential construction sector enters a period for which a zero or negligible growth is forecast.
9 Hristo Belchev Street
Floor 2
Sofia
1000
Bulgaria
+359 2986 79 07
vpenkova@penkova-partners.com www.penkova-partners.com