Qatar is a civil law jurisdiction that relies on enacted laws and on Sharia principles in the absence of enacted laws. Judgments serve as guiding principles for lower courts when issued by the Court of Cassation.
Construction contracts are primarily governed by the:
Specific laws and regulations have also been issued in relation to contracts involving state entities in Qatar, including:
The laws and unofficial English translations of the laws are available on the Al-Meezan Portal.
Article 171 of the Civil Code sets out the principle of the binding effect of contracts. Parties are therefore free to agree on the terms of their construction contracts, provided they do not contravene mandatory provisions, public order or morality as set out under Qatari law. There are no specific formalities for the validation of a construction contract.
Standard forms of contracts are generally used by government entities, and each has its own form, which are generally based on the FIDIC provisions and procedures, with amendments.
For governmental projects, most state entities have tailored their own contract templates for construction, engineering and procurement contracts. This is the case for the PWA, Hamad International Airport, Qatar Rail, Qatar Energy (formerly Qatar Petroleum), Kahramaa and Qatar Gas, in addition to other state entities.
Where a state entity is involved, construction contracts may qualify as administrative contracts. The Qatari Court of Cassation has held that a contract will qualify as an administrative one if:
Employers in Qatar are typically:
An employer’s obligations under a construction contract are generally set out in law, particularly Articles 692 to 700 of the Civil Code (relating to service contracts) and include the following.
The employer’s rights include:
The types of companies that act as contractors in Qatar include local and/or international companies, depending on the complexity and types of the projects (airports, stadia, infrastructure, oil and gas plants, rail, hospitals, malls, hotels and energy plants). They also include:
The contractor’s rights are set out in the Civil Code and are as follows.
The contractor’s general obligations under Articles 696 to 691 of the Civil Code include the following.
The type of company that acts as subcontractor depends on the scale of the project and the nature of the work that is being subcontracted (such as electrical and mechanical works, civil works/core and shell, waterproofing, plumbing and HVAC, carpentry and joinery, flooring, painting and decoration, steel and metal work, scaffolding, landscaping and other specialised trades). In certain projects, a member of the joint venture will also act as subcontractor for the joint venture.
As back-to-back subcontract models are widely used in Qatar, subcontractors generally have the same rights and obligations as those of the contractors towards the employer with regards to the subcontracted work, subject to the specific requirements of each subcontract.
Articles 701 and 702 of the Civil Code include specific provisions for subcontract agreements.
Subcontractors generally seek funding from financial institutions through financial facilities/tender bonds (advance payment guarantee and retention bonds) in addition to other facilities, against which they generally assign the proceeds of the project to the bank. These facilities are generally similar to those obtained by the contractors under the main contract.
There are two main financiers in Qatar: the government and banks. Administrative contracts are financed by the government (eg, the Ministry of Finance).
The Qatar Investment Authority (the sovereign wealth fund, with a portfolio worth USD360 billion in 2022) provides funding, which is mainly generated from gas and oil revenues, for strategic projects abroad.
For public-private partnerships (PPPs), the State has determined the implementation of a partnership between the two sectors, including financing, through:
This is in line with one of the following model types:
For contractors, subcontractors and suppliers in the private sector, banks remain the main financiers in construction projects, in addition to a number of investment funds (private equity firms, infrastructure funds and real estate funds).
In terms of the relationship between the various parties, for example, in administrative contracts, the employer will generally fund the project and the contractor and subcontractors will respectively obtain facilities from a bank against:
Companies that typically act as a designer in Qatar must be licensed by the Ministry of Municipality and Urban Planning (the “MMUP”) or the Qatar Financial Centre Authority (the “QFCA”), and may be local, regional or international. They generally include the following.
Article 5 of Law No 19/2005 Regulating the Practice of Engineering Professions sets out a list of conditions for a person/entity to be eligible to join the register of engineers. This includes designers and the conditions are summarised below.
To enrol in the register of engineers, individuals must:
For local offices of engineering consultancies, the office must:
For international offices of engineering consultancies, the branch office must be a licensed branch of a main office abroad, supported by the main office, with a proven track record of at least ten years. The engineer in charge must:
Other engineers in the branch office must meet conditions outlined in the implementing regulations.
The MMUP has introduced updated construction codes to align with international best practices, covering aspects such as building materials, structural design, fire safety and sustainability. By enforcing these codes, the MMUP aims to ensure that construction projects meet the highest standards of safety, durability and environmental responsibility.
Two special legal stipulations address the licensing of engineering/design consulting services within the Qatar Financial Centre (the “QFC”). Both stipulations are part of the Non-regulated Activities Rules Version 2 – October 2023.
For context, the activities which can be undertaken by QFC entities are either regulated or non-regulated. The former are generally financial services and are regulated by the QFC Regulatory Authority (the “QFCRA”). The latter are the various engineering/design consulting services that form permitted activities falling under “professional services”, as provided under Schedule 5(G) of the QFCA Rules (Version No 17 – October 2023).
The Civil Code does not include a section on the rights and obligations of designers in construction contracts, which remain subject to party autonomy and the agreed terms of each contract. Where there is no specific agreement, the general principles of contract law set out under Articles 169 to 175 will apply.
In addition, and in the absence of any agreement to the contrary, Articles 712 and 713 include specific provisions regarding the designer’s liability in construction matters.
If the architect/designer has only provided the design of a construction or establishment, they may only be held liable for the defects relating to the design they have produced and may not be held liable for the manner in which it was executed (Article 712(1)).
However, if the designer/architect also undertook the supervision of the execution/performance, they will also be liable for any defects resulting from the manner in which the design was performed (Article 712(2)).
The contractor remains liable for defects pertaining to errors in design if the errors were apparent in line with trade usages (Article 713(1)) and for any design defects if the designer works for the contractor.
Article 711 of the Civil Code further stipulates a mandatory decennial and joint warranty on the part of the contractor and engineers for structural defects (including defects that would compromise the structure’s safety or risk its collapse) that cannot be set aside by agreement. This starts running from the taking over date and is subject to a limitation period of three years from the date the structural defect is discovered.
The method for description of the scope of work varies depending on the type and size of the project. However, it is generally similar to the methods used in international contracts and will likely include:
Qatari law does not have specific provisions on variations. These are generally negotiated and agreed on by the parties. The specific provisions within the Civil Code relating to services contracts cover events where the performed works have exceeded the scope or the agreed price.
If the contractor’s fees were not agreed on, the fees for the work should be assessed based on their value at the time of contracting, as well as on the value of the materials supplied by the contractor and required for the works. These provisions may serve as a preliminary basis for the evaluation of variations as they are considered works, whose price was not determined in the contract (Article 699 of the Civil Code).
For remeasurement contracts, if during the progress of the work, it is deemed necessary to considerably exceed the assessed measurements in order to perform the agreed design, the assessed expected increase in costs must be notified to the employer by the contractor, failing which, the contractor’s rights for the additional costs will extinguish. If the excess is substantial, the employer may terminate the contract, provided that they compensate the contractor for the works performed (Article 708 of the Civil Code).
For contracts in which prices are based on design, the contractor is not entitled to claim compensation for any variations to the design unless the variation is due to the employer’s acts as approved and agreed with the contractor (Article 709 of the Civil Code).
Although Qatari law does not specifically tackle variations ordered by the employer outside these provisions, the contractor may claim additional compensation based on these Articles or general principles of Qatari law governing compensation laid down under Articles 256 to 263 of the Civil Code. In doing so, the contractor should prove that the additional works were requested by the employer or caused by the employer’s fault/breaches (such as delays) and the resulting actual costs.
Time-related costs are part of the damages claimed due to events that were not caused by, or that were outside the control of, the contractor. In this case, and in the absence of any other stipulations in the contract, the contractor may claim the costs as damages under the general principles of the Civil Code (Articles 256, 263 and 268), trade usage and the principle of good faith performance of contracts.
The responsibilities regarding the design are usually determined and agreed on between the employer, designer, contractor and other parties, in their respective contracts.
Article 713 of the Civil Code provides that contractors are only liable for defects in the works and not for those in the design, unless the design errors were of such a nature that they could not have gone unnoticed by the contractor as per trade usages.
The designer is usually responsible for its designs and for its compliance with relevant applicable laws and safety measures.
These provisions are not mandatory and parties remain free to agree on design obligations, which may include the following.
The specific allocation of work can vary depending on the terms negotiated in the contract agreement and the nature of the project but will generally include the following.
The employer is generally the party responsible for site access and for geotechnical and ground conditions (including soil risks) unless the related defects were detectable at the time of contracting and accepted by the contractor. For this purpose, the employer is generally responsible for obtaining any permits to secure safe and authorised site access (including road construction, civil defence, road and traffic permits and others).
Nonetheless, the ultimate responsibility in this regard depends on the terms of each contract, which may shift to the contractor, as is often the case in turnkey contracts.
Specific permits are required in Qatar based on the nature and scope of the project, local regulations and the location of the construction site. They include the following (prior to commencement).
In addition, specific certificates are required upon completion of the project. These include:
Engineering consultancy firms in Qatar are required to obtain a licence from the engineering committee in line with Law No 19/2005.
Contractors are generally responsible for maintenance after performance of the works and taking over for a contractual period, which is known as the defects liability period. The defects liability period is usually 400 days and once it is over, the maintenance responsibility shifts to the employer.
Maintenance generally includes regular inspections, cleaning, lubrication, minor repairs and upkeep of the facilities to preserve their proper functioning, appearance and longevity. It also includes preventative maintenance such as servicing equipment, conducting regular inspections and implementing maintenance schedules.
Separate maintenance contracts outlining the specific terms and conditions for ongoing maintenance may be entered into between the employer and the contractor in large-scale projects (such as heavy plants) or with third parties.
The employer generally deals directly with operations and finance. Nonetheless, in specific cases, especially in EPC/turnkey or PPP contracts, these functions may be assigned to the contractor.
The testing and commissioning process is generally set out in the contract. Taking over or practical completion only occurs when testing is successfully completed. In certain types of contracts, testing may be required even after completion, during what is commonly referred to as the trial operation period.
Article 696(1) of the Civil Code expressly refers to practical taking over of the works and provides that, once the works have been taken over by the employer, whether practically or contractually, the contractor’s liability for apparent defects ceases.
The practical completion also triggers the time limit for latent defects, which should be notified to the contractor within a reasonable period in line with the applicable trade customs. The employer is required to take possession of the works following a formal notice from the contractor to this effect. The employer’s refusal to take possession of the works without just cause amounts to an acceptance of the works (Article 696(2) of the Civil Code). However, the parties remain free to agree to different terms and effects for the completion of the works.
Article 87 of the Commercial Code provides that the limitation period for rights arising from commercial acts between merchants, including construction contracts (which are considered commercial acts if concluded by a professional under Article 5(16) of the Commercial Code), is ten years from the date on which the rights have become due. Accordingly, provided that defects are duly notified in line with the provisions set out further below, the employer’s rights to compensation are subject to the decennial limitation period.
The Civil Code provides for the following three categories of defects.
Defects Liability Period
Construction contracts generally include a period of time during which the contractor has the right (and also the obligation) to return to the site to rectify any defects in the works at its own expense. This period is commonly known as the defects liability period, rectification period or maintenance period, and generally extends for a period of 400 days from provisional taking over or practical completion of the works.
The method usually used in general contracts to establish the price is the lump sum contract and the lowest bidder is normally awarded the contract provided they meet all requirements and qualifications. Some contracts have provisional sums. For the PPP pricing method see 2.4 The Financiers.
Some contract prices are based on design and remeasurement (see 3.7 Maintenance) and a few private contracts are based on cost-plus pricing.
The method of payment usually consists of an advance payment of 10% to 20% of the contract price against a bank guarantee to be monthly amortised and monthly interim payment certificates linked to progress, concluding with the final account, final payment certificate and release of the retention money.
The indexation of prices is typically used in construction contracts to mitigate the risk of large price fluctuations, particularly in contracts with long durations. Indexation mechanisms are intended to help parties manage inflation and market changes by linking contract prices to an agreed upon index, such as the Consumer Price Index (CPI), producer price indices or specific industry indices.
The risk of large price fluctuations is typically divided between parties through negotiation and contractual agreements. The following are some common approaches.
Fixed-Price Contracts
The contractor agrees to complete the project for a predetermined, fixed price. Any cost increases or decreases are borne by the contractor subject to special considerations for unforeseen circumstances.
Cost-Plus Contracts
The contractor is reimbursed for the actual costs incurred during construction, plus a predetermined fee or percentage of costs. This arrangement shifts the risk of price fluctuations to the employer, who bears the responsibility for any cost increases.
Price Adjustment Clauses
These clauses allow for adjustments to contract prices based on changes in specified indices, such as inflation rates or material costs. Price adjustment mechanisms can be tailored to allocate risk between parties based on their preferences and market conditions.
Shared-Risk Contracts
Some contracts may include provisions for sharing the risk of price fluctuations between the parties. For example, the parties may agree to a formula that divides cost increases or decreases between them based on predetermined ratios or thresholds.
The allocation of risk of price fluctuations further takes market conditions, project complexity and the bargaining power of the parties involved into account. For example, recent global events, such as the COVID-19 pandemic, the Ukraine war and changes in legislation such as Qatar’s Minimum Wage Law have led to significant increases in construction costs.
Contractors are usually entitled to an advance payment guarantee of between 10% and 20% of the contract price against a bank guarantee to secure their cash flow. This amount will be amortised in the monthly interim payment certificates. Subsequent payments are generally made on an interim basis through monthly progress payment certificates.
As contracts are binding under Qatari law, any provisions for late payment or non-payment of certified payments can be implemented. Contractors are generally required to proceed with the works notwithstanding any delay in payments or pending claims in their contracts.
In the absence of these provisions, the following legal remedies are available for a contractor.
Typical means of invoicing may vary depending on the specific contract terms and the parties involved. However, the most common means of invoicing are through interim payment applications. These types of application involve the contractor submitting periodic invoices, usually on a monthly basis, reflecting the work completed during that period. These applications are accompanied by supporting documentation, such as progress reports, measurement sheets and records of materials used. The employer or the employer’s representative reviews the application for the purpose of certifying it. Each interim payment generally includes the amount of retention monies and recovered advance payments, where applicable.
Once the interim payment is certified, it is issued in the form of an interim payment certificate, which the employer is required to pay within an agreed timeframe from the date of its certification.
Disputed applications or payments are generally subject to a specific procedure provided for in the contract.
Programme planning depends on the party responsible for design (see 5.2 Delays). The detailed programme of work is then generally required from the contractor.
Under Article 687 of the Civil Code the contractor is required to complete the works within the agreed period or, if no period is agreed, within a reasonable period as required by the nature of the works, taking trade usages into account. If the contractor fails to perform the works in line with the terms of the contract, Article 688 of the Civil Code requires the employer to issue a notice underlining the defects in performance and setting out a deadline for them to be rectified. If the deadline elapses without the contractor rectifying the defects, the employer may request the termination of the contract or its completion at the expense of the contractor.
In addition, under Article 689 of the Civil Code, the employer may terminate the contract prior to its term if:
Aside from the applicable legal provisions, construction contracts typically set out the procedure to be followed by the parties if delays occur that would affect the date of completion of the works, which differ depending on whether the delays are due to the employer, the contractor or external cause.
As the party that is performing the works, the contractor is generally considered to have the necessary information to assess and alert the employer of any delays that would affect the completion of the works, even where these are not attributable to the contractor. The procedure generally applies where there is a critical delay and/or where a delay is likely to affect the completion date or result in additional costs.
In these instances, and whenever it becomes aware of any delaying events, the contractor is required to send a notice within a prescribed timeframe that varies from one contract to another, irrespective of the nature of these events. Failure by the contractor to issue the notice in a timely way might lead to them being banned from their right to an extension of time, as well as to any resulting costs. These clauses are commonly known as time-bar clauses. The notice is generally followed by a substantiation requirement to provide, within another prescribed timeframe, the particulars of its claim, whether for an extension of time or additional costs.
While there is no clear position in case law as to the enforceability of time-bar clauses in Qatar, it remains the case that these clauses lead to imposition of a shorter time limit on the contractor’s right to claim compensation than those set out in law (15 years for civil claims and ten years for commercial claims). To this extent, they might be considered as contravening the provisions of Article 418 of the Civil Code, which are mandatory.
Finally, concurrent delays occur where two or more delay events occur at the same time; one as an employer’s risk event, the other as a contractor’s risk event. In this case, concurrent delays do not become an issue unless both are recorded as critical.
In these circumstances, parties may agree on the procedure to assess concurrent delays and their effects on the parties’ rights and may choose that either:
In the absence of this type of agreement and in the event of a dispute, parties often have recourse to experts that will perform the relevant analysis and examine the cases of concurrency closely, to properly identify the responsibilities for delays and to allocate proper entitlements.
Articles 688 and 689 of the Civil Code grant the employer the right to either terminate the contract or complete the works at its own expense if the delays referred to in these Articles occur (see 5.2 Delays).
In addition, the following remedies can be granted.
Liquidated Damages
Construction contracts often include liquidated damages provisions as a form of agreed compensation under Article 263 of the Civil Code, which establish a predetermined amount of damages that the contractor must pay to the employer for each day of delay beyond the agreed completion date. The amount is usually capped at 10% of the contract price.
Nonetheless, liquidated damages cease to apply and can be set aside if the contractor proves that the employer did not incur actual losses under Article 266 of the Civil Code. This Article is mandatory and also grants the courts the power to reduce agreed compensation if it was excessive or if the related obligation was partially performed.
On-Demand Bonds
Construction contracts often require contractors to provide bonds (against advance payment, performance, retention) as a form of financial security. In the event of delays or non-performance, the employer may call upon the performance bond to secure compensation for the breach under Articles 406 to 413 of the Commercial Code.
Extensions of time are requested in line with the procedure set out in the contract, typically through a notice of claim, which should be submitted within the prescribed time limit (see 5.2 Delays). The grounds for the extension will usually be for any delays that are not caused by the contractor or that are not concurrent with delays caused by the contractor.
The extension-of-time process in construction contracts necessitates adherence to contractual procedures and time-bar provisions for similar claims. This involves clear communication, thorough documentation and adherence to procedural requirements, to ensure fair resolution of delays and of disruptions to the project schedule.
The extension of time is typically established, measured and proven through a systematic process outlined in the contract documents. The contract specifies procedures and criteria for granting extensions, including defining events that entitle the contractor to an extension, such as unforeseen site conditions or delays caused by the employer or other contractors.
The contractor is usually obligated to promptly notify the employer of any events that may entitle them to an extension and to provide supporting documentation for their claim. This documentation may include daily site reports, correspondence, meeting minutes and photographic evidence.
Parties (often with the assistance of contract administrators or project managers) assess the impact of the event on the project schedule by analysing the critical path and identifying delays. The employer evaluates the contractor’s claim based on contractual provisions and supporting documentation. If warranted, the employer issues a formal extension-of-time instruction specifying the duration and conditions of the extension.
In cases where parties cannot agree on the entitlement or duration of the extension, dispute resolution procedures outlined in the contract (such as expert determination or arbitration) may be invoked.
Force majeure is a civil law concept. It means that the occurrence of specific events under specific circumstances will exempt an obligor from liability if these events have prevented it from performing its obligations. While a number of Articles in the Civil Code (see, for example, Article 204 of the Civil Code) refer to force majeure and distinguish it from “external events”, it does not define it.
It is therefore recommended that the parties define force majeure in their contract. Where force majeure is not contractually defined, it has been narrowly construed by the Qatari Court of Cassation and has been considered to occur when it cumulatively meets two conditions: “unforeseeability and irresistibility” (ie, could not have been prevented by the obligor) (Qatari Court of Cassation, Civil and Commercial Circuit, Judgment No 134/2015 dated 25 May 2015).
Where a party has not performed its obligation because of force majeure, it is exempted from liability, whether in relation to performance or to compensation, for any damages incurred by the other party as a result of such non-performance (Articles 188 and 204 of the Civil Code).
Where a contract includes bilateral obligations, if the performance of an obligation has become impossible for external reasons, this obligation extinguishes and so does any reciprocal obligation. The contract is then deemed terminated de jure (Article 188 of the Civil Code).
The consequences of the occurrence of a force majeure event include:
Article 171(2) of the Civil Code gives the judge the power, in light of the circumstances, and while balancing the parties’ interests, to reduce the scope of the obligation to a reasonable limit. This provision is mandatory and cannot be set aside by agreement, where unforeseen exceptional circumstances have occurred and rendered the obligor’s performance financially burdensome.
This typically applies to unforeseen circumstances during the performance of the respective obligations in a construction contract, such as:
These events are generally considered to be risks ultimately borne by the employer. Nonetheless, given the mandatory nature of Article 171(2) of the Civil Code, even where the parties agree to maintain the obligor’s liability in these events, the contractor will still be entitled to avail itself of the provisions of Article 171(2) of the Civil Code.
Disruption is a technical concept that is not expressly defined in the Civil Code. Nonetheless, the parties are free to define it in their contract. Construction contracts usually include disruption clauses.
To the extent that disruption relates to an event outside the control of the parties and resulted in the impossibility to perform the obligations, it falls within the meaning of “external events outside the control of the parties” of Article 188 of the Civil Code.
Where the disruption could not have been foreseen and has rendered the performance substantially more onerous, the contractor could request to reduce the obligation or claim compensation for the additional costs (Article 171 of the Civil Code).
Various steps may assist in establishing and measuring disruption and its effects:
Contractual exclusion of liability is recognised and enforceable in Qatar to the extent that it does not contradict mandatory liabilities at law (such as fraud, gross negligence or illegitimate acts and decennial liability), which cannot be set aside by an agreement between the parties.
Article 259(1) of the Civil Code therefore allows the parties to exclude the obligor’s liability resulting from its failure to perform its contractual obligations or from delays in performance. This exclusion does not include liability in the event of fraud or gross fault, which cannot be excluded. Article 259(2) of the Civil Code also allows the debtor to exclude its liability for fraud or gross fault committed by those assisting it in the performance of its obligations. This provision could serve as a basis for the contractor to exclude liability for its subcontractors’ fraud or gross fault.
Article 715 of the Civil Code considers any condition to exclude or limit the liability of the engineer or the contractor from the decennial liability null.
The terms “wilful misconduct” and “gross negligence” do not feature in the Civil Code. The Civil Code instead refers to “fraud” and “gross fault” (see 6.1 Exclusion of Liability).
The Civil Code does not provide for a definition of these concepts within the context of exclusion of liability. However, Article 134 of the Civil Code defines “fraud” in the context of defects that would vitiate consent and considers this to occur where consent was given as a result of manoeuvres aimed at misleading a party into contracting.
In defining the act of fraud, the Qatari Court of Cassation has set out a general definition of the concept of fraud in contracts as follows: “Any acts or methods aiming to deceive a contracting party by impairing its consent or preventing it from making a sound and informed decision. Mere lying is not sufficient to constitute fraud unless it is clearly demonstrated that the deceived party was unable to uncover the truth beyond the lie. If the deceived party could discern the truth, then fraud is not recognised.”
“Gross fault” is not defined within the Civil Code, but is considered in civil law countries, including Qatar, as fault which should not be made by the least cautious or the most negligent. It assesses liability on the basis of whether or not a party has failed to take minimal care to avoid the fault.
The Civil Code recognises the parties’ right to limit liability under Article 267 of the Civil Code. This states that if the agreed compensation amount is exceeded, the creditor cannot claim compensation for the excess unless it proves “fraud” or “gross fault” by the debtor. Construction contractual limitations on liability, including liquidated damages, are generally valid and enforceable, except for “wilful misconduct” and “gross negligence”.
Indemnity clauses aim to compensate the indemnified party for any losses incurred as a result of the liability it may hold towards third parties following the indemnifier’s default. In the context of subcontracting, the subcontractor may be required to indemnify the contractor for damages resulting from their default and which have affected the main works. These clauses play a crucial role in allocating risk and ensuring that the responsible party bears the ultimate financial burden.
In construction contracts, it is common to include an obligation for the contractor to provide several types of bonds to the employer to guarantee it performs its contractual obligations. These typically include:
In Qatar, bonds often take the form of “irrevocable and on-demand” letters of guarantee issued by the contractor’s bank and provided for in Articles 406 to 413 of the Commercial Code. Article 409 requires the bank to pay the employer the amount of the bond upon first demand, irrespective of the status of the employer’s relationship with the beneficiary.
Under Qatari law, the following are required for a valid guarantee:
The agreed terms and conditions of the guarantee will govern its validity and enforceability.
Given the risks encountered in construction projects, insurance requirements are generally negotiated and included in the contract. The contractor is the party that is contractually required to take out and maintain insurance coverage for risks encountered during performance.
Insurance products in Qatar offer contractors coverage for a wide range of risks, including:
The scope of coverage can be negotiated between the insurer and the insured to include additional risks. However, insurance typically excludes delay damages caused by environmental hazards, such as the runoff of toxic liquids onto adjacent lands.
Architects and engineering consultancy offices licensed in Qatar are required to have professional indemnity insurance and an indemnity coverage for their personnel and employees under the Implementing Regulations to Law No 19/2005.
Qatar has also enacted the Healthcare Services Law (Law No 22/2021), which includes a mandatory supplemental health insurance provision for employers to provide health insurance for non-Qatari employees and their families, as well as for foreign visitors, for the duration of their stay. However, this Law entered partial effect on non-residents only as of the date of this publication.
In Qatar, two regimes are provided for in law:
Construction contracts usually provide for the right to terminate if the other party becomes insolvent or bankrupt, without providing a specific timeframe.
Bankruptcy is defined as the event “where a merchant stops paying his or her commercial debts at maturity due to its disrupted financial status”. In terms of the requirements for a creditor to initiate bankruptcy proceedings against its debtor, the creditor should:
Courts have accepted voluntary liquidation of companies (as opposed to declaring them bankrupt) upon a lawsuit filed by the shareholders due to the company’s inability to pay its debts or honour its financial obligations or due to the failure of the company to complete its projects based on the provisions of Article 291 of the Commercial Companies Law.
Qatari law does not specifically address the allocation of risk in construction contracts. This is generally determined and agreed on in the contract through the allocation of risks between the parties, namely in the event of force majeure and unforeseen circumstances.
Failing any stipulations to this effect, the risks that will affect the performance of the obligations, namely force majeure and extraneous events are set out and will be deducted from the law as stated in the Civil Code (see 5.5 Force Majeure).
Shared risks in construction contracts are generally assessed and priced based on factors such as:
Pricing mechanisms may include:
Construction contracts generally include the following provisions in relation to personnel:
Aside from the construction contract and in relation to the relationship between the contractor and its employees, the Qatari Labour Law (which secures employees’ basic rights) is mandatory and cannot be set aside by agreement. However, it can be improved. These improvements include:
Construction contracts in Qatar must comply with these provisions and ensure the protection of workers’ rights and adherence to labour standards.
Qatar issued the Healthcare Services Law (Law No 22/2021) regulating the health services in Qatar, which came into effect from 4 May 2022. The Law provides basic health insurance coverage for Qatari nationals and foreigners, whether they are residents or visitors. It repealed all former laws governing health services and prescribed a minimum level of coverage with insurance companies registered with the Ministry of Public Health. As of the date of this publication, the Law has been implemented for visitors to Qatar but not Qatari nationals or residents. It is awaiting the publication of detailed implementing regulations.
Article 701 of the Civil Code authorises contractors to subcontract all or part of the works. However there are limitations. Contractors must do so with the employer’s prior approval, unless the terms of the main contract state otherwise and/or provide for nominated subcontractors or unless, given the nature of the work, the contract was concluded ad personam.
However, this Article (and the contract) stipulates that the main contractor remains liable to the employer for its subcontractor’s work.
Intellectual property (IP) provisions address ownership, use and protection of IP rights in relation to the project, and, in certain cases, have specific laws and benefit from protection in Qatar.
Depending on the contract, they usually include:
While the specific provisions on IP rights and IP risks may vary depending on each project, they generally include:
Articles 241 et seq of the Civil Code provide for the remedies available to a party in the case of a breach of contract and primarily set out the principle according to which an obligor should be ordered to specifically perform in the case of breach, following a notice to this effect. Compulsory performance can only be sought through a court judgment following a lawsuit before the competent judge.
Where the obligation requires the performance of a service, Article 251 of the Civil Code authorises the creditor to seek a court order to have the obligation performed by a third party at the obligor’s cost, except in emergency cases where the creditor is exempted from obtaining the court order.
If, given its nature, the obligation cannot be performed in nature, or if the obligor has delayed performance, the creditor may request compensation for actual losses incurred as a result of the delay or non-performance (Article 256 of the Civil Code).
The creditor may also request termination in the event of breach or where the other party fails to perform its reciprocal obligation under specific conditions set out by the law or in the contract (see 9.6 Termination).
For a party to be able to enforce any of these remedies, it is required to obtain a final judgment from the substantive competent court, unless the contract expressly provides for the right to terminate without the interference of the court.
If urgent measures are required, a party may also apply to the emergency judge for an interim measure of protection in order to prevent or resist an imminent danger. The requirements for the application are strict in that the applicant should prove an imminent danger to property or livelihood. This means it can only be granted in limited cases.
Subcontractors are granted the right of direct recourse against the employer if the contractor fails to honour its payment obligations to the subcontractor. This course of action is conditional upon the employer retaining monies owed to the contractor and can only be made up to the value of the monies at the date of the initiation of the lawsuit (Article 702 of the Civil Code).
Articles 265 to 267 of the Civil Code allow parties to agree on monetary compensation for delayed or non-performance, provided the underlying obligation is non-monetary. However, if the debtor can prove that no losses were suffered, the agreed compensation does not become due and payable. The judge also has the authority to reduce the agreed compensation if it is deemed excessive or if partial performance has occurred.
Under Article 267 of the Civil Code, the employer is prohibited from seeking a higher compensation if actual damages exceed the agreed amount, making the agreed compensation the sole remedy for damages resulting from non or delayed performance. However, this does not apply if the creditor proves “fraud” or “gross fault” by the debtor.
Article 259 of the Civil Code allows clauses that limit or exclude liability, except in cases of “gross fault” or “fraud”. While liquidated damages may be the exclusive remedy for delay-related losses, the employer can still seek compensation under the Civil Code for other breaches, unless the contract explicitly excludes it.
To the extent that liability can be excluded or limited contractually under Qatari law, exclusive remedy clauses may be enforced (see 5.2 Delays and 6 Liability).
Liability for damages may be excluded to the extent it does not relate to “fraud”, “gross fault” or illegitimate acts under Qatari law. The exclusions may include direct damage, lost profit or other moral damages (see 6.1 Exclusion of Liability).
Retention and suspension rights are commonly used to provide the employer with recourse in the case of defective work, non-performance or other breaches by the contractor. These are not prohibited under Qatari law.
Contracts generally grant the employer the right to withhold 10% of the contract price until a specified time. Out of this amount, 5% is released to the contractor upon completion, while the remaining 5% is released at the conclusion of the defect liability period.
Unless agreed otherwise, Article 191 of the Civil Code enshrines the civil law principle of exceptio non adimpleti contractus, according to which a party may suspend performance if the other party fails to perform its reciprocal obligation. For a party to avail itself of this principle, the opposing party should have failed to perform an obligation that is immediately due and that is considered reciprocally linked to the obligation it wishes to suspend.
Under Qatari law, unless otherwise expressly stated in the contract, termination can only be achieved through a court order.
Under Articles 707, 183 and 184 of the Civil Code, a construction contract can be terminated either fully or partially for convenience (termination at will) due to default or impossibility to perform:
The contractor has the right to terminate the contract and demand compensation if the employer, despite being notified, fails to take necessary actions required for the progress of the works (Article 692 of the Civil Code).
The following institutions are competent to adjudicate disputes:
The newly established Trade and Investment Court (Law No 21/2021) (first instance, appeal and cassation) is competent.
The civil and commercial courts (administrative circuit) retain jurisdiction for disputes relating to construction contracts of an administrative nature. A circuit is also established within the Court of Appeal for arbitration-related applications (arbitrator’s appointments, challenges, setting aside awards).
The Qatar International Court and Dispute Resolution Centre of the Qatar Financial Centre (the “QICDRC”), which is an onshore Qatari jurisdiction, retains competence over disputes between companies established within the QFC (in line with the provisions of Article 9 of the QFC Court Regulations) as well as over disputes within and against the Qatar Free Zone Authority (the “QFZA”). The QICRDC is competent in arbitration-related matters where the parties have chosen the QFC as the seat of arbitration (in which case the QFC Arbitration Regulation 2005 will apply) or have chosen this court as the competent court under the Arbitration Law (Law No 2/2017).
The Claim and Compensation Committee (the “CCC”) was established in 1996 (with subsequent multiple legislative amendments, most recently in 2020) under the Ministry of Finance reviews compensation applications by contractors arising from construction contracts and involving a government entity whose decisions are not legally binding nor published. The contractor has the option to accept the decision or to seek a court judgment or arbitral award depending on the dispute resolution agreement.
The new Enforcement Court was established by virtue of Law No 4/2024 issued on 4 April 2024 and promulgating the Judicial Enforcement Law. Law No 4/2024 incorporates legislative measures intended to effectively expedite the enforcement of judgments and executory deeds. It expressly grants cheques the power of executive instruments, enabling beneficiaries to collect amounts even if there are insufficient funds. It also grants registered or authenticated property lease contracts executive authority regarding property evacuation post-contract, in both cases without initiating primary substantive legal proceedings. Finally, it grants the enforcement judge the power to accelerate the enforcement proceeding and to impose penalties in the case of obstruction of enforcement.
Mediation is an optional procedure that parties can choose to resolve their disputes as there are no legal limitations preventing its use. It can be found as a pre-arbitration step in certain dispute resolution clauses included in construction contracts in Qatar.
The Law on Mediation for the Settlement of Civil and Commercial Disputes (Law No 20/2021) was issued on 18 October 2021, to regulate mediation agreements. Qatar had already ratified the Singapore Convention on Mediation on 12 September 2020, which aims to facilitate the recognition and enforcement of mediation settlements.
The QICDRC provides for mediation services through its mediation rules, while the Qatar International Conciliation and Arbitration Centre (the “QICCA”) offers conciliation services through its rules issued in 2012.
The QICCA introduced its new arbitration rules, effective from 1 January 2025. These rules represent a significant modernisation of the previous 2012 framework, aligning the QICCA with international best practices and enhancing its appeal as a dispute resolution forum in the Middle East.
Arbitration agreements pertaining to private contacts or administrative and public contracts are recognised under the Arbitration Law (Law No 2/2017), which applies to arbitrations seated in Qatar or to the recognition and enforcement proceedings of foreign awards in Qatar, provided they do not contravene Qatari public policy or morals (Article 28). For administrative contracts, the approval of the Prime Minister (or his designated delegate) is required.
Grand Hamad Street 810
Al Fardan Center Building 36, Floor 3
Old Ghanim 6
Qatar
+974 4443 0651
+974 4443 0836
admin@marri-hage.com www.marrilaw.comNational Address Law and Judicial Notifications
In the context of disputes in Qatar, where foreign entities often operate through project-specific branches or joint ventures, the issue of judicial notification could become particularly sensitive once those companies have ceased operations in the jurisdiction. The National Address Law No 24 of 2017 (the “National Address Law”) was issued in 2017 and published in the Official Gazette on 21 April 2019. Based on Article 9, the National Address Law came into effect six months later, ie, on 20 October 2019.
The National Address Law establishes a central database which is maintained by the Ministry of Interior (the “MOI”). All residents, institutions and companies in Qatar have to register their address with the authority. Under Article 2 of the National Address Law, registrants must provide key information, including their contact number, email address, employer’s address (for employees), permanent address abroad (if any) and any other data requested. The competent authority may designate any of these data points for the purpose of serving judicial announcements and official notifications.
Article 5 of the National Address Law therefore stipulates that judicial notifications and official notices served to a national address are deemed valid and produce all legal effects.
Under Article 3 of the National Address Law, if the company fails to provide its national address to the competent authority within the prescribed deadlines, any notification or service made to that authority will be deemed valid and will produce all its legal effects.
Under Article 4 of the National Address Law, failure to update the address does not absolve a party from responsibility. Notifications sent to the last registered national address are therefore deemed legally served. Companies must therefore promptly update any changes to their information to avoid the risk of missed legal communications and being bound by notifications sent to an incorrect or outdated address.
Notification of foreign companies under Qatari Law
Article 1 of the National Address Law defines the parties subject to its provisions as all natural or legal persons, whether Qatari citizens or expatriates, including their legal representatives. However, foreign companies that are not registered or established in Qatar are not considered among the parties bound by the National Address Law. Consequently, the notification procedures applicable to foreign companies fall under the provisions of the Civil and Commercial Procedure Law (the “CCPL”) for due process.
According to Articles 10(8) and 10(9) of the CCPL, service abroad is managed as follows.
Foreign companies that have ceased operations in the country and have expired CRs should not therefore be subject to notification procedures under the National Address Law once an entity formally deregisters. Instead, they should be treated as a foreign-domiciled entity.
In some recent cases, courts have accepted service via the MOI under the National Address Law even where the commercial registration of a branch of a foreign entity, without any presence in the State, has expired.
To avoid disputes regarding the validity of court notifications, foreign companies that have ceased operations and have previously established a presence in the State should take steps to formally deregister their local branches from the Commercial Registry, even if their commercial registration has expired. This will clearly evidence the absence of legal presence in the country and reinforce that they are not subject to the National Address Law.
Electronic notification of companies under the Investment and Trade Court
On 18 October 2021, Law No 21 of 2021 establishing the Investment and Trade Court in Qatar was introduced detailing procedures for electronic case filing and notifications. Under Article 17 of the Law, the Case Management Office must, within three days of electronic filing, verify that court fees have been paid and that all case documents are complete. Upon completion of this verification, Article 18 of the Law obliges the Case Management Office to notify the defendant electronically at the address registered with the competent authority, within another three days. Article 15 of the Law confirms that service through any registered element of the address, such as an email address or phone number, is legally effective and binding. Articles 3 and 4 of the National Address Law will be applied.
Accordingly, once a company is electronically notified of a lawsuit at any of the data points listed on its national address certificate or at the authority (pursuant to the provisions of Article 3 of the National Address Law), it is deemed to have been validly served under both the National Address Law and the Investment and Trade Court Law. Following the notification, companies are granted a strict period of 30 days to submit their electronic replies and all supporting documents and counterclaims (if any). Failure to respond within this timeframe, as stipulated in Article 22, results in a forfeiture of the right to later file any new memoranda, documents or claims unless the courts grants the right at its own discretion, based on valid reasons.
On this basis, the legal framework may carry risks at the litigation stage and in practice, a simple administrative oversight, such as not monitoring the company’s registered email account or neglecting to check messages sent to the registered phone number, could result in a company effectively losing its right to due process. Without any defence submissions on record, a judgment may be rendered against the company in its absence. This has raised some concerns about conflicts with the fundamental right of defence set out under Article 119 of the CCPL for the parties to be guaranteed a fair opportunity to present their case.
Given that the Investment and Trade Court issues notifications under a new electronic system, it does not explicitly outline the notification procedures for foreign-domiciled companies. The provisions of the CCPL should therefore remain applicable to these entities.
In a recent judgment (No 700008/2024) rendered on 20 May 2024, the Qatari Court of Appeal considered that notification is valid if the court system shows that:
This implies the mere fact of sending an SMS to the opponent’s mobile phone or its e-mail is not sufficient on its own. It does not necessarily prove that the recipient has received the notification.
The court must therefore ascertain that it has received an automatic response from the telecommunications company confirming the recipient’s receipt of the SMS before proceeding with the case. If both steps are achieved, the court can proceed with moving forward with the case. However, if the recipient can prove that these procedures were fundamentally flawed preventing the notification from reaching them, the notification can be invalidated.
This judgment is important because it essentially softens a previously stringent approach to electronic notifications and acknowledges potential technical issues that may occur in the notification process. It therefore introduces a due process safeguard to ensure that parties are not unfairly deprived of their right to defend themselves due to technical failures in electronic and technical systems.
Conversely, another judgment (No 2013/2024) rendered on 31 December 2025, illustrates a stricter approach by the Qatari courts. In that case, the Court of First Instance issued its ruling without the defendant submitting any defence or being formally notified of the rendering of the judgment itself. The defendant later initiated an appeal outside the 15-day deadline, invoking Article 157 of the CCPL and considering that the judgment was rendered in absentia.
While the Court of Appeal initially accepted the appeal as duly filed, the Court of Cassation ultimately ruled that the appeal was time-barred and dismissed the cassation. The interesting aspect of this judgment, though, lies in the Court of Cassation’s observations that the enforcement proceedings related to the case had already been “linked” on the court’s online system to a law firm (ie, a lawyer has the file or case file associated with their registered law office account). This raised another point to potentially take into account, which was the defendant’s potential constructive knowledge of the underlying judgment.
However, the Court of Cassation did not go so far as to say this counts as formal notification or that it would trigger procedural deadlines, especially as prior Court of Cassation rulings have firmly established that notifications cannot be inferred or presumed from separate matters, cases or related proceedings (Court of Cassation rulings No 116/2023 dated 6 March 2023 and No 243/2013 dated 7 January 2024 and No 90/2006 dated 16 January 2007).
Judicial Enforcement Reform and Establishment of the Enforcement Court
In October 2024, Law No 4 of 2024 (the “Judicial Enforcement Law”) came into effect with the establishment of the Qatari Enforcement Court. Since then, several practical developments have emerged. The key development relates to the handling of dishonoured cheques. These types of cheques are now treated as executive instruments, in addition to lease contracts.
The Enforcement Court’s online portal now features a section for initiating direct enforcement action against dishonoured cheques. This means that, under the new framework, creditors are no longer required to go through initiating a lawsuit or criminal proceedings to establish the debt. As soon as a cheque becomes due and is returned unpaid, it may be submitted directly for enforcement.
This is a change from the previous system under which, cheque claims required a greater degree of judicial procedure to establish the debts.
Article 4 of the Judicial Enforcement Law notably expressly repeals all provisions set out in the Third Book of the CCPL (namely Articles 362 to 518) which had previously governed enforcement procedures relating to these measures. These specifically relate to preventive and interim measures, which are commonly used to preserve assets ahead of a final judgment and are only briefly referenced in the new regime, without substantive guidance on the conditions, timelines or procedural mechanisms for seeking this relief.
This is important to stakeholders in sectors which often involve large contracts and staged payments, especially to those where there is a history of delayed payments or of payments being withheld. It is expected that further case law and judicial practice will help clarify how the Enforcement Court will apply and approach interim relief measures going forward. In the meantime, businesses may consider proactive measures, such as enhanced contractual protections or payment guarantees, to complement the enforcement tools now available under the new legal structure.
Amendments to the QFC Law and the QICDRC Court Procedures
In October 2024, Law No 16 of 2024 was enacted, which introduced key amendments to the Qatar Financial Centre (the “QFC”) Law (Law No 7 of 2005) and the Qatar International Court and Dispute Resolution Centre (the “QICDRC”) procedures (commonly referred to as the “QFC Courts”). One of the changes brought about by these amendments was the provision for certain cases to be heard by a single judge in the First Instance Circuit and the QFC Regulatory Tribunal, as opposed to the previous requirement for a panel of three judges This amendment, which is at the discretion of the Court President, is expected to allow for more flexible case management and quicker hearings, particularly for less complex matters, thereby addressing the growing caseload of the QICDRC and to enhance the accessibility and efficiency of the courts.
The period for filing appeals has also been shortened. The appeal window for first instance decisions has been reduced from 60 days to 30 days in order to expedite the finality of judgments and dispute resolution process. For businesses operating under project timelines or financing arrangements, this helps mitigate disruption in time-sensitive disputes and cases where there is ongoing work.
To further promote the functioning of the courts, court fee structures are also being introduced with the aim of deterring unnecessary claims and to ensure that parties are serious about pursuing legal action.
The initiative aligns with the introduction of litigation restraint orders under Practice Direction No 1 of 2024, which empowers the court to prevent individuals or entities from initiating repetitive or meritless litigation without prior permission.
The first application of a litigation restraint order occurred in the case of Amberberg Limited and Rudolf Veiss ([2024] QIC (F) 24), where the Court issued a two-year restraint order against the respondents. The decision was based on multiple meritless applications submitted by the respondents. The restraint orders prohibit entities or individuals from filing new claims or applications without prior permission from the President or a nominated judge of the Court.
Elsewhere, a recent judgment by the Appellate Division in The University of Cambridge v The Holding WLL [2025] QIC (A) 6 clarified a key matter in relation to the QFC Courts’ jurisdiction which is important for businesses structuring their contracts and managing dispute risk/forums for dispute resolution. The claimant in this case was an entity established and regulated under the laws of the United Kingdom, while the defendant was a Qatari company, but not established in the QFC. It was held by the Appellate Division that the parties could not “opt-in” jurisdiction to the court merely by contractual agreement. The court’s jurisdiction is strictly limited to what is outlined in the QFC Law and any extension of the QFC Courts’ jurisdiction must come from primary legislation. Any clause purporting to submit disputes to the court where neither party falls within its statutory jurisdiction and the heads of jurisdiction under the QFC Law will therefore be ineffective.
Launch of QFC Digital Assets Framework
An important milestone in 2024 was the launch of the QFC Digital Assets Framework, which came into force on 1 September 2024. This was jointly issued by the QFC Authority (the “QFCA”) and the QFC Regulatory Authority (“QFCRA”). The framework consists of the Digital Asset Regulations 2024 and rules that establish a legal infrastructure for tokenised assets, smart contracts and digital financial services.
Under this framework, businesses are allowed to apply for a licence as a token service provider (TSP) within the QFC. The Regulations introduce definitions for permitted tokens and investment tokens, as well as for tokenised ownership rights. It also regulates the custody, transfer and exchange mechanisms for digital assets, to provide clarity and legal recognition for these financial instruments.
Key components of this framework include the following.
The regulatory framework is expected to attract both domestic and international players and support Qatar’s broader digital transformation agenda in line with the State’s Third Financial Sector Strategy and National Vision 2030.
Grand Hamad Street 810
Al Fardan Center Building 36, Floor 3
Old Ghanim 6
Qatar
+974 4443 0651
+974 4443 0836
admin@marri-hage.com www.marrilaw.com www.elhagelaw.com