In 1957, a newly formed electricity directorate acquired all the private power stations and transmission lines through Pakistan, which included East Pakistan (now Bangladesh), and, in 1958, East Pakistan Water and Power Development Authority (EP-WAPDA) was formed to effectively manage the power sector in the then East Pakistan (Bangladesh), which merged with the electricity directorate in 1960. After independence, the government of Bangladesh (GOB) demerged WAPDA by Presidential Order 59 to form the Bangladesh Power Development Board (BPDB) under the supervision of the Ministry of Power, Energy & Mineral Resources (MPEMR). BPDB was further demerged to form the Rural Electrification Board (REB) and the Dhaka Electric Supply Authority (DESA), and, in 2000, the transmission lines were handed over to the newly formed Power Grid Company of Bangladesh (PGCB). The generation of electricity has been privatised partially but the transmission and distribution are still under state monopoly as stated above.
Principal laws that govern the ownership and structure of the power industry include the following.
The power sector in Bangladesh is unbundled with generation, transmission and distribution. The government has six generation, one transmission and five distribution entities. The following are the major participants in this sector.
Currently there are no foreign investment restrictions that apply to the power industry and investment can be made by any investor from any country recognised by Bangladesh. However, as per the Bangladesh Industrial Policy, the power sector is a controlled sector and any investment in this sector is required to be properly licensed. There is no investment limit threshold as long as the relevant qualification (in terms of prior experience in similar size of investment, debt financing and operation, and so on) is met. There is also no restriction on holding of land rights through a Special Project Vehicle (SPV) and even 100% foreign-owned SPVs can hold lands.
Investment Protection
The Foreign Private Investment (Promotion and Protection Act), 1980 grants protection to foreign investments in Bangladesh, ensuring the following.
Protection is also available under various bilateral investment treaties (BITs) entered into by and between Bangladesh and other foreign countries. Countries with whom Bangladesh has concluded BITs include Austria, Korea, DPR, Thailand, Belgium, South Korea, UK, Canada, Malaysia, USA, Pakistan, Uzbekistan, France, Poland, Vietnam, Germany, Romania, Singapore, Indonesia, Switzerland, Denmark, Iran, The Netherlands, India, Italy, The Philippines, UAE, Japan and Turkey.
Access to Court and Foreign Arbitration
Foreign investors and corresponding SPVs shall have general access to the local courts. In addition, Bangladesh courts uphold choice of foreign law and party autonomy as agreed among the parties while entering into the contract. It was decided in PLD 1964 Dacca 637 that when the intention of the parties to a contract as to the law governing the contract is expressed in words, this expressed intention determines the proper law of the contract and in general overrides every presumption. However, enforcement of judgment is allowed only from those countries that have reciprocal co-operation with Bangladesh for such enforcement of judgment. Currently only Indian judgments are enforceable in Bangladesh.
Bangladesh is a member of the New York Convention. International arbitration is permitted under the Arbitration Act, 2001 of Bangladesh. Parties are free to choose the arbitral tribunal and underlying rules. Foreign arbitral awards are enforceable in Bangladesh and awards are required to be filed in the court of first instance to be enforced against the debtor or its assets. The court in which recognition or execution of the foreign arbitral award is sought may refuse to enforce such foreign arbitral award:
It may be noted that an arbitral award from an international commercial arbitration held offshore cannot be set aside. Furthermore, a set-aside order against an arbitral award from an international commercial arbitration held in Bangladesh cannot be appealed. Unless otherwise waived by the parties under Section 7A of the Arbitration Act, 2001, the High Court may grant an interim injunction to protect the rights of any party in an injunction to preserve the subject matter in connection to a domestic arbitration.
Foreign Exchange Regulations
Bangladesh has a very strict foreign exchange control regime under the Foreign Exchange Regulation Act, 1947 (FERA). Generally speaking, conversion and repartition of foreign exchange require approvals of Bangladesh Bank. For certain transactions no prior approval from Bangladesh Bank is required and banks arrange summary approvals from Bangladesh Bank as outlined under the Guidelines to Foreign Exchange Transactions (GFET), eg, foreign investment, divestment, repatriation, technical fee, royalty, consultation fee, distribution fee, dividend, loan repayment including interest payment, and import/export.
A Bangladeshi company may, in a shareholders’ general meeting, declare dividends to its shareholders from time to time. Banks arrange summary approvals from the central bank for repatriation of dividends to the non-resident shareholders. For sale of shares involving non-resident shareholders, a fair valuation is required and a post-closing notification to the central bank is essential. However, prior approval of Bangladesh Bank is required for repatriation of sales proceeds arising from a non-resident’s sale of shares in a non-listed company. Liquidation proceeds can also be repatriated as per the procedure laid out in the GFET. Foreign borrowing needs approval from regulatory authorities nominated by the central bank and is fairly easy for industrial and infrastructure projects.
Investment Incentives
Bangladesh has the following investment incentives.
Restrictions in General and Control Regime
There are no restrictions regarding the sale of power industry assets or businesses, or other transactions, including amalgamations and mergers in general. The Bangladesh Competition Commission has been formed under the Bangladesh Competition Act, 2012 to ensure competition in all industries. The BERC also retains some power to maintain competition as a first-tier regulator for power generation industries. The Bangladesh Competition Commission (BCC) still acts on a reactive basis as it is yet to formulate and enact the competition rules for merger control.
However, any combination (including acquisitions, amalgamation or mergers) in the goods and service market that adversely affects competition or creates a cause to adversely affect competition is prohibited. The BCC has wide powers to investigate any combination that adversely affects competition on its own motion or under complaint from any third party.
There are currently no minimum requirements that must be satisfied by a purchaser of assets or an acquirer of a business, such as market influence, financial metrics and industry expertise.
Contractual Lock-In
As per a prevailing implementation agreement (Concession Agreement) applicable to power projects in Bangladesh, it may be noted that the main sponsor (Lead Member) identified by the competent authorities will be required to hold at least 51% of equity until the COD and 40% thereafter until the sixth anniversary of the COD. An operating sponsor (Operating Member) that is identified by the competent authorities is required to maintain at least 20% of equity until the COD and 11% thereafter until the sixth anniversary of the COD.
A transfer that circumvents these lock-ins needs express approval from the offtaker, which is difficult to obtain, and needs to demonstrate the qualification of the purchaser and overall good impact over the industry.
Power Division
The Power Division under MPEMR is the central authority that oversees and administers the electricity supply and the development of transmission and distribution facilities to ensure the reliability of the electricity system and the adequacy of supply to satisfy the demand for electricity. Its function includes:
These include electricity supply adequacy, generation planning and development, and transmission system planning and development through its departments. Accordingly, the Power Division has prepared Integrated Energy and Power Master Plan (IEPMP) 2023 and is overseeing its implementation.
Power Cell
Under supervision of the Power Division, the Power Cell has a mandate to lead private power development, recommend power sector reforms and restructuring, conduct study on tariffs and formulation of a regulatory framework for the power sector. The Power Cell shall facilitate all stages of promotion, development, implementation, commissioning and operations of private power generation projects and suitably address the concerns of project sponsors.
SREDA
On the other hand SREDA, as an agency under the MPEMR:
There have not been any material changes in law or regulation regarding the power industry over the past year.
There have not been any announcements regarding new policies or initiatives that would result in material changes for the power industry.
In line with the Policy, currently the conventional power purchase agreements (PPAs) for fossil fuel IPPs provide for a capacity payment and an energy payment. Capacity payment is required to be paid irrespective of energy delivery (for market issues or government failure to provide fuel). However, the government is reportedly considering abolishing capacity payments for future fossil fuel projects. For renewable PPAs, the government only pays energy on the basis of “take or pay”.
Furthermore, the government is also thinking of denominating the tariff entirely in Bangladeshi Taka, as addressed in 2.1 The Wholesale Electricity Market.
Captive Power Plant
Under the Captive Power Plant Policy (CPPP), Captive Power Plants have been defined as power projects that produce power as per their own use or for the use of a group. Such power produced may be sold at a predefined rate not exceeding the rate at which BPDB sells power to distributors excluding the wheeling charge. The producer is required to enter into a PPA as per the template incorporated in CPPP. Connection to the grid is possible at its own expense and PGCB may charge a wheeling fee. A licence for power generation is also required to be procured from BERC. To connect to the grid, its capacity must be higher than 20 MW.
Small Power Plant
Small Power Plants are defined as power plants with a capacity of less than 10MW. Such power produced may be sold to anyone at a predefined rate where BPDB, DESA (Dhaka Electric Supply Company) and REB (Rural Electrification Board) are present, and for other areas the price may be mutually negotiated. Connection to the grid is possible at its own expense and PGCB may charge a wheeling fee. A licence for power generation is also required to be procured from BERC. Small Power Plants may sell electricity to BPDB distributors or to large consumers, which include Export Processing Zones, Special Economic Zones, Private Economic Zones, Hi-Tech Parks, Large Real Estate, etc meeting the following voltage level and load characteristics:
Net-metering
Net-Metering Guideline 2018 (NMG2018) allows Captive Power Plant, Small Power Plant and private solar grids to be connected to the national grid through the distributor in the corresponding area by way of executing a net-metering agreement. Within a 12-month settlement period any export of electricity with the system can be adjusted against any import from the local distributor. After the settlement period, if there is net export then such export is settled by way of cash payments by the distributor/utility.
Currently there is no open market either in form of capacity market or energy market in Bangladesh. As a single buyer, BPDB procures power from independent power producers (IPPs), small power producers (SPPs), corporatised generation companies and other publicly owned power plants based on negotiated bulk power tariff rates. These rates are based on fuel type, plant load factor and other operational parameters. BPDB exercises its inherent power to purchase electricity at a negotiated price under the Bangladesh Power Development Boards Order, 1972 with due approval of inter-ministerial committees. Generally, it enters into a PPA extending up to 20 years as per the Policy, which is upheld and valid up to the duration of the PPA. BPDB renegotiates the tariff with the developer after the expiry of the consecutive PPA term. As per the Policy, the tariff generally includes the following.
There is also a mechanism for the adjustments of certain tariff components to variations in taka/dollar exchange rate, fuel price and inflation rates. Based on experience, in renewable IPPs the tariff is dominated in USD only against energy payments. In general, the payment mechanism adopted in PPAs is take or pay mechanism, except, where there is an interconnection failure attributable to offtaker or interconnector, offtakers liability to pay is limited up to dependable capacity agreed in the PPA. For renewable power projects only Energy Payment is payable.
On the other hand, BPDB sells electricity to the distribution utilities at wholesale tariff rates. These wholesale tariff, transmission tariff and distribution tariffs are used to deduce the retail tariff, all of which are regulated by the Bangladesh Energy Regulatory Commission (BERC) as per the regulations below.
Latest tariff orders (both feed in and terminal) are located on the BERC website. Over the last decade, Bangladesh has seen an increase in the price of the consumer tariff at least ten times in attempts to lessen the gap between the income from consumers and expenditure by way of guaranteed capacity payments to power producers of BPDB. BERC is in the process of enacting a BERC (Tariff For Rooftop Solar PV Electricity) Regulation as currently such prices are negotiated between the developer and the user.
However, for captive power plants selling electricity to any utility undertaking, the tariff shall not exceed the published tariff by which BPDB sells power at 132 kV (Category G1) excluding wheeling charges provided that, for increase of price of fuel, the fuel component of the tariff for purchase of power from the captive power plant may be adjusted. The tariff of captive power plant is required to be pre-approved by BERC.
There are no restrictions for imports and exports of electricity to/from other jurisdictions in Bangladesh in general. However, as a single buyer, BPDB procures power from independent power producers and those independent power producers are not allowed to export electricity.
BPDB may procure import of electricity from other jurisdictions following the public procurement procedure, which in turns needs approval from the Cabinet Committee of Government Purchase (CCGP). So far, BPDB has entered into one cross-border PPA with a power producer in India.
Such import is permitted when the authorities deem that such import is necessary to maintain and secure supply of electricity in Bangladesh. As explained above, like local PPAs, BPDB is authorised to negotiate tariffs for such offshore supply of electricity.
Currently, Bangladesh has transmission interconnections with India only.
As of June 2023, the power generation capacity of Bangladesh amounts to 24,911 MW, encompassing a diverse range of sources. Combined cycle plants contribute the most with 8,363 MW (33.57% of total capacity), followed by reciprocating engines with a significant 8,023 MW (32.21% of total capacity). Steam turbines contribute 3,742 MW (15.02% of total capacity), gas turbines add 1,438 MW (5.77% of total capacity), and hydro power plant provides 230 MW (0.92% of total capacity). Solar PV systems contribute 459 MW (1.84% of total capacity), while power imports add 2,656 MW (10.66% of total capacity).
Bangladesh’s power generation is sourced from a diverse range of fuels. Bangladesh’s power generation is predominantly fuelled by gas, making a significant share with 11,372 MW (45.65%). Furnace oil follows with 6,492 MW (26.06%), coal provides 2,692 MW (10.81%), and power imports contribute 2,656 MW (10.66%). Diesel adds 1,010 MW (4.05%), hydro contributes 230 MW (0.92%), and solar PV systems contribute 459 MW (1.84%).
The IEPMP forecasts a maximum demand of between 27.4 and 29.3 GW in 2030, between 50.4 and 58.6 GW in 2040 and between 70.5 and 96.8 GW in 2050, with a target of renewable power generation to the extent of 10%, 22% and 35% in 2030, 2040 and 2050 respectively.
Currently, there are no concentration limits regarding the percentage of electricity supply. However, if such a concentration limit is imposed, it is likely that BERC would have authority and oversight on such implantation.
Bangladesh is yet to facilitate a fully functional competitive market in the sector of electricity generation, transmission and distribution. The Bangladesh Competition Commission has been formed under the Bangladesh Competition Act, 2012 to ensure competition in all industries. It also retains some power to maintain competition as a first-tier regulator for power generation industries. BERC has been authorised to ensure fair competition in this sector, to conduct surveillance of the market to detect anti-competitive behaviour and to undertake enforcement under the BERC Act, 2003, where it has been accorded with relevant investigative powers. However, a detailed rule on the parameters of such fair competition, the process for surveillance and its enforcement is yet to be enacted. Violation of the BERC Act, 2003 is punishable with imprisonment for a term not exceeding three years or with a fine not less than BDT5,000 or with both, and in case of continuation of the offence they shall be fined with an amount not exceeding BDT3,000 for each day of continuation.
Under the Competition Act, 2012, any anti-competitive behaviour limiting competition is prohibited. Any act shall be deemed to have an adverse effect on competition in the market if it:
In addition, the Competition Act, 2012 specifically declares the following practices as anti-competitive:
The Competition Commission has been empowered to investigate and adjudicate any complaint following the Code of Criminal Procedure. For any non-cooperation, it can sentence up to one year’s imprisonment or fine for other offences. Appeal is possible by paying 10–25% of the fine.
The principal laws that govern the construction and operation of generation facilities are as follows.
Other important laws that also influence the construction and operation of generation facilities include the following.
Award of Concessions
IPPs are awarded as per the Private Sector Power Generation Policy for a term (generally 15–20 years) negotiated between the offtaker (BPDB) and the power producer. The concession is awarded in the form of a letter of intent (LoI) and after attaining the required conditions. The concession contract is executed in the form of an Implementation Agreement that commits government obligations to the project, a PPA that includes the terms of offtake, and, in appropriate cases, along with a fuel supply agreement and a land lease agreement. The tariff structure has been discussed in 2.1 The Wholesale Electricity Market.
The LoI is required to be accepted by the awardee by way of submitting a security in the form of an irrevocable and unconditional bank guarantee. The purchase and payment obligations of the offtaker under the PPA and the interconnection-related obligations of PGCB are guaranteed by the government by executing a guarantee agreement. Currently, the following are the processes under which BPDB awards PPAs in favour of private sector power generators.
As per the Unsolicited Proposal Guideline for Solar Projects, the applicant needs to meet the following criteria.
Land Acquisition
If land lease is not a part of the concession, then for the execution of the concession agreements demonstration of land procurement is a prerequisite for the execution of the concession agreements. Bangladesh recognises the concept of freehold title of land, leasehold title, general lease (as per the Transfer of Properties Act), easements and licence (as per the Easements Act, 1882). Whereas for the plant freehold title of land, leasehold title and general lease are accepted, easements and licence are frequently used for transmission lines and wind masts.
Interconnection
As per the policy, the electricity is purchased from the IPP at a specified voltage at the outgoing terminal (interconnection point) of the substation of the power plant as agreed with BPDB. The transmission line for interconnection with the national grid will be either provided by the appropriate agency or otherwise needs to be constructed by the IPP. The costs of interconnecting facilities up to outgoing terminals of the private power projects (including step-up auto transformers, circuit breakers and associated switchgear) will be borne by the private power producers.
The concession agreement incorporates PGCB as a party providing the interconnection point up to which the project company is required to develop relevant facility to supply power. Before construction of the interconnection and transmission line, the IPP is required to negotiate the full interconnection plan with PGCB and get PGCB’s approval.
Environmental Clearance
The environmental laws of Bangladesh consist of the Environmental Policy, 1992 and the Bangladesh Environment Conservation Act, 1995 (ECA) read in conjunction with the Environment Conservation Rules, 2023 (ECR). Formed under the ECA, the Department of Environment (DOE) issues environmental clearance certificates (ECC) subject to issuance of no objection certificates from the local government authorities. Any industrial project (including power projects) must obtain an ECC from the DOE prior to commencement of construction of its project.
The ECR categorises all projects into four divisions:
Power projects fall into the Red category. Prior to construction of a power project (renewables fall in Yellow/Orange category, waste to power and gas-fired IPPS in Orange but gas-fired IPPs above 100MW and coal-fired IPPs are categorised as Red), the project company must obtain relevant certificates in the following order. For the Red category of projects, a full environmental impact assessment (EIA) is required. The EIA must be conducted as per the approved terms of reference. A public consultation is required to be arranged with the inhabitants of the project area and other stakeholders, including experts, and the details of the discussion must be incorporated in the EIA.
The EIA approval and the ECC will typically be valid for a period of one year from the date of issue and must be renewed 30 days before expiry. The site preparation work can be initiated after an LCC is obtained from the DOE. Development works may be initiated after the EIA approval. In order to obtain the ECC, the company is required to submit an application to the relevant department of DOE along with details of the project and relevant feasibility report, environmental impact assessment, effluent discharge plan and environmental management plan (as applicable to the relevant category). On inspection by the authorised officer at DOE, and after verification of the report and documents, the report is submitted to the DOE, which issues an ECC RED category at a meeting of the Environmental Clearance Committee, a standing committee under the DOE.
It is important to note that it is prohibited to start commercial operation of such an infrastructure without having a valid and concurrent environmental clearance. Any contravention to this may result in two to five years’ imprisonment or BDT100,000–500,000 fine or both may be imposed. The Department of Environment (DOE) also has the power to impose fine, compensation for environmental pollution, improper discharge, failure to take measures as negotiated with DOE and even, at its discretion, shut down any facility that fails to comply with the environmental protection laws and regulations. However, the DOE is required to provide reasonable notice (usually one month’s notice) before exercising such discretion.
In addition to the conditions outlined in 3.2 Obtaining Approvals to Construct and Operate Generation Facilities and the following licences/authorisations, the only other conditions imposed in approvals to site, construct and operate a generation facility are as follows.
Other approvals include the following (the chronology provided is for a typical IPP).
The primary laws regulating the transfer and ownership of land in Bangladesh are:
As stated above, Bangladesh recognises the concept of freehold title of land, leasehold title, general lease (as per the Transfer of Properties Act), easements and licence (as per the Easements Act, 1882).
Currently, the Acquisition and Requisition of Immovable Property Act, 2017 applies to acquiring any appropriate interest over land for any public purpose. It also applies in determining the amount of compensation to be awarded for any property to be acquired. In the event of the government acquiring any land for any individual or private organisation, it will be required to pay three times more than the market price of the land. In the event of the government acquiring any land for itself, it will be required to pay two times more than the market price of the land. The Electricity Act, 2012 defined such acquisition/right of way over land for power generation and transmissions as public purposes. For this, the following procedure must be followed.
For private procurement of land (by way of acquisition), the project company is responsible for relocation and resettlement of business, facilities and residents. For public land lease, it depends on the lease agreement and the concession. In most of the cases where public land is leased, it is taken care of by the lessor. Whereas there is no statutory obligation (unless the project is funded by world bank or IDA credit), in most of the cases such rehabilitation/resettlement is imposed as a condition under the ECC; and, also, in many cases the prospective lenders place emphasis on IFC guidelines and equator principles for such resettlement.
In general, under such framework (ie, IFC guidelines), the Project Company is required to ensure that:
To perform such relocation and resettlement of business, facilities and residents, the standard practice is that a non-governmental organisation (NGO) is appointed to prepare the Rehabilitation Action Plan (RAP). Upon finalising the RAP, the company needs to allocate a fund from its budget for the RAP and the NGO makes use of the rehabilitation fund appropriately to implement the RAP.
For decommissioning of power plants, there is no separate guideline or regulation. However, the IPP owner needs to ensure that the terms of the environmental clearance are maintained during the decommissioning process, which needs the owner to restore the site on an “as was” basis. There is no obligation to fund decommissioning over the physical life of the facility and it can be funded at the end of its physical or economic life.
Construction and operation of transmission lines and associated facilities are not allowed for the private sector. For the public sector, the law that governs such ownership, construction and operation is the Electricity Act, 2018. In addition, other than the private sector policies and Net Metering Guidelines, the laws stated in 3.1 The Construction and Operation of Generation Facilities also apply to such ownership, construction and operation of transmission lines by public authorities.
In addition to the approvals to be awarded to the contractors and other laws and regulation stated in 3.2 Obtaining Approvals to Construct and Operate Generation Facilities,before construction and operation of a new or new segment of transmission lines PGCB needs approval from MPEMR and then from the Executive Committee of the National Economic Council (ECNEC). Thereafter, PGCB can perform public procurement for the engineering, procurement and construction (EPC) contractors (as per 3.2Obtaining Approvals to Construct and Operate Generation Facilities)and finally needs approval from CCGP for the award of the contract.
Other than those stated above and certain licences/permits as stated in 3.3 Approvals to Construct and Operate Generation Facilities, no further terms and conditions are imposed on approvals to construct and operate a transmission line and associated facilities.
The premise stated in 3.4 Eminent Domain, Condemnation or Expropriation Rights equally applies to construction and operation of transmission lines and associated facilities.
As of now, PGCB has monopoly rights to provide transmission service within Bangladesh.
The BPDB sells electricity to the distribution utilities at wholesale tariff rates. These wholesale tariff, transmission tariff and distribution tariffs are used to deduce the retail tariff, all of which are regulated by the Bangladesh Energy Regulatory Commission (BERC). The Bangladesh Energy Regulatory Commission (Power Transmission Tariff) Regulations, 2016 establish the procedures for adjustment of tariffs for power transmitted into the transmission system.
Currently, the PGCB has a negotiated transmission tariff rate agreed with each of the electricity distributors throughout the country. From time to time, the PGCB may apply to the BERC for the escalation of its transmission tariff based on the components outlined in the Bangladesh Energy Regulatory Commission (Power Transmission Tariff) Regulations, 2016. Upon receipt of such application, the BERC conducts a public hearing and decides on the tariff increase by way of government gazette publication.
As the PGCB exercises monopoly rights to provide transmission service within Bangladesh, it is required to provide on an open-access and non-discriminatory basis to all distributors throughout Bangladesh, which are also state-owned entities, subject to the grid capacity of PGCB in corresponding interconnection points as per the Bangladesh Grid Code 2018 against a transmission tariff.
Construction and operation of electricity distribution facilities are not allowed for the private sector. For the public sector, the law that governs such ownership, construction and operation is the Electricity Act, 2018. In addition, other than the private sector policies and Net Metering Guidelines, the laws stated in 3.1 The Construction and Operation of Generation Facilities also apply to such ownership, construction and operation of transmission lines by public authorities.
In addition to the approvals to be awarded to the contractors and other laws and regulation stated in 3.2 Obtaining Approvals to Construct and Operate Generation Facilities, before construction and operation of electricity distribution facilities corresponding utility needs approval from MPEMR and then from Executive Committee of the National Economic Council (ECNEC). Thereafter, the utility can perform public procurement for the engineering, procurement and construction (EPC) contractors (as per 3.2 Obtaining Approvals to Construct and Operate Generation Facilities) and finally needs approval from CCGP for the award of the contract.
Other than those stated above and certain licences/permits as stated in 3.3 Approvals to Construct and Operate Generation Facilities, no further terms and conditions are imposed on approvals to construct and operate distribution facilities.
The premise stated in 3.4 Eminent Domain, Condemnation or Expropriation Rights equally applies to construction and operation of electricity distribution facilities.
As of now, the government exercises monopoly rights to provide distribution services within Bangladesh.
The BPDB sells electricity to the distribution utilities at wholesale tariff rates. These wholesale tariff, transmission tariff and distribution tariffs are used to deduce the retail tariff, all of which are regulated by the Bangladesh Energy Regulatory Commission (BERC). The Bangladesh Energy Regulatory Commission (Retail Distribution) Regulations, 2016 establish the procedures for adjustment of tariffs at which the distributor would sell electricity to end consumer.
Currently, the distributors have a retail tariff rate fixed by the BERC. From time to time, the distributors may apply to the BERC for escalation of its retail tariff based on the components outlined in the Bangladesh Energy Regulatory Commission (Retail Distribution) Regulations, 2016. Upon receipt of such application, the BERC conducts a public hearing and decides on the tariff increase by way of government gazette publication.
Doulah House
Plot-153/2, Rd-2/2
Mirpur-12A
Dhaka 1216
Bangladesh
+88 0171 1506 015
+88 0280 164 42
ndoulah@doulah.com www.doulah.netIntroduction
Bangladesh has experienced significant economic growth and development over the past two decades. Alongside the economic growth, there has also been a rapid rise in energy consumption. This trend is expected to intensify further in the upcoming years to cater to the dynamic fast-growing market in Bangladesh as it strives to become a high-income country by 2041.
Energy and power are key ingredients for alleviating poverty and improving the socio-economic conditions in any country. The government of Bangladesh has given top priority to development of the power sector, considering its importance in the overall development of the Bangladesh economy, and has set the goal of providing electricity to all citizens in Bangladesh by 2041.
As the power sector is a highly capital-intensive industry, huge investments are required to generate additional capacity. Competing demands on the government’s resources and declining levels of external assistance from multilateral and bilateral donor agencies have constrained the potential for public investment in the power sector. Recognising these trends, the government of Bangladesh amended its existing industrial policies and approved the “Private Sector Power Generation Policy of Bangladesh” in October 1996, which was then revised in November 2004 to enable and encourage the flow of private investment into the power sector. The government of Bangladesh has also introduced a wide array of facilities and attractive incentive policies to encourage investment in the power sector.
Based on the liberal investment regime, Bangladesh has been successful in attracting domestic and foreign investment in the power sector, enabling remarkable progress to be made.
Transition to Renewables
The government of Bangladesh recognises that there is a major transition underway in the energy sector worldwide and Bangladesh is yet to achieve efficient utilisation of renewable energy resources. Recognising these trends, the government adopted the Renewable Energy Policy 2008 to enable, encourage and facilitate both public and private sector investment in renewable energy projects.
Bangladesh’s installed renewable energy capacity (including on-grid and off-grid) at present is approximately 1,200 MW, with solar making up approximately 950 MW and hydropower producing approximately 230 MW. The remainder is produced by wind, biogas and biomass.
Solar Power Projects
At present, solar power dominates the renewable energy mix in Bangladesh. Through the Infrastructure Development Company Limited, the government of Bangladesh has partnered with the World Bank and other development partners to implement the Solar Home System (SHS) programme, so as to provide clean and affordable electricity to communities in far-flung areas. As a result of the SHS programme, there have been developments in off-grid rooftop solar power, which has provided access to electricity to a large number of people living in rather remote off-grid locations. The contribution is approximately 260 MW, which is expected to increase further in the future.
There has also been rapid installation of rooftop solar systems in Bangladesh, which is expected to play a vital role in decarbonising the energy sector. To encourage this further, the government of Bangladesh promulgated the Net Metering Guidelines 2018, whereby electricity consumers are able to export any additional electricity generated by the solar system installed at their premises to the distribution grid network, after self-consumption. This has now seemingly become a popular choice for industries to minimise their electricity costs.
The contribution of SHS and the rooftop solar systems in the context of national power demand and generation is, however, insignificant. The government has awarded a number of grid-tied solar power projects over the last decade but only a handful of them have materialised. The largest solar project in the country, the 200 MW solar park in Sundarganj, Gaibandha achieved commercial operations in January 2023. Another 100 MW solar park in Mongla Upazila, Bagerhat became a commercial operation in 2021. The rest are smaller-scale projects.
Challenges in solar power projects
The major challenge faced in implementing grid-tied solar power projects is the inadequacy of the land, as approximately three acres of land is required for the generation of one megawatt of power. As per the direction of the government, no agricultural land can be used for power projects, including solar power projects, and since Bangladesh is a densely populated, fertile agricultural country, non-agricultural unused land is not easily available. Private investors initially struggle to identify a suitable parcel of land and, once that has been identified, they struggle to acquire clean title over the earmarked land. Price negotiations between landowners and land aggregators are usually prolonged and sometimes even retracted at the whim of the landowners, resulting in a prolonged pause in the development of the project.
The government is considering implementing a couple of projects where a government entity would lease land to the private sector for the construction of solar power projects. One such project is located in Kushtia, Bangladesh where the government entity, the Sustainable and Renewable Energy Development Authority, has appointed International Finance Corporation (IFC) as its transaction adviser. During the feasibility study, IFC advised that the tariff is expected to be much lower if land owned by the government is used for the project, as the private partner would not have to bear the risk of acquiring the land.
However, considering that land is a scarce resource in Bangladesh, a major technological breakthrough is required to increase the number of solar projects in the country.
Hydropower Projects
There is only one hydropower generation facility, in Kaptai, Bangladesh, which generates 230 MW. There is, however, a cross-border deal being negotiated at present whereby hydropower of approximately 40–50 MW will be exported from Nepal to Bangladesh.
Other Renewable Power Projects
Bangladesh is largely untapped with respect to other renewables like wind, biogas and biomass. The first large wind-power project of approximately 66 MW capacity, located in Cox’s Bazar, Bangladesh, became a commercial operation in May 2023. There are a few other wind projects in the planning and implementation stage.
The government has also signed agreements with private investors for waste-to-power projects, the commercial operation of which is expected to be achieved in 2024. Successful implementation of these waste-to-power projects will diversify the country’s renewable energy sources and also help to manage waste.
The transition to clean energy will play an active role in promoting economic development, saving energy and reducing emissions, as well as protecting the environment in Bangladesh.
Developments in Fiscal Incentives
Local and foreign investors are keen to invest in the power industry in Bangladesh, mainly because of the various tax incentives granted by the government. From mid-2013 up until the beginning of 2020, private power-generation companies enjoyed exemption from corporate income tax for a flat period of 15 years, commencing from their respective commercial operations dates.
However, in 2020 the government took a different stance when it decided that power-generation companies that became commercial operations by 31 December 2022 would be eligible for exemption from corporate income taxes for a period commencing from their respective commercial operations dates up until 31 December 2034. This meant that a company achieving commercial operations status in December 2022 would only be entitled to income tax exemption for 12 years.
The stakeholders in the power industry were truly concerned in the six-month period between December 2022 and June 2023 when the above exemption was not extended to private generation companies achieving commercial operations after 31 December 2022. There was a lot of speculation as to whether the government would extend the timeline or whether private generation companies would now have to change their financial models to take into account the next available incentive. The next available incentive was an exemption from income tax at truncated rates for a period of ten years.
To everyone’s relief, the government has now passed a new order whereby power-generation companies that achieve commercial operations before 31 December 2024 will be eligible for exemption from corporate income taxes for a period commencing from their respective commercial operations date up until 31 December 2036, and those who achieve commercial operations before 31 December 2025 will be eligible for exemption from income tax at truncated rates for a period of ten years.
The initial 15-year tax exemption was used by the government as a tool to promote investment in the power sector to meet the goal of providing electricity to all citizens in Bangladesh. Recent developments in the income tax incentives indicate that the government is now shortening the exemption period and there may be no further exemption for private power-generation companies who achieve commercial operations in or after the year 2026. The government is now more prone to revenue collection to meet other economic goals of the country.
Developments in Transmission Lines
The Power Grid Company of Bangladesh Limited (PGCB) is the sole transmission company in Bangladesh. Previously, the interconnection line from the power-generation facility to the nearest substation was implemented by PGCB. However, in recent times, the private partner has been made responsible for the construction of the interconnecting line, including the arrangement of the necessary land and any right of way.
These changes arise from the government’s and PGCB’s decision to allocate the risk of construction of the interconnection line and its operation and maintenance to private power-generation companies. The cost and risk of construction of the interconnection facilities is not expected to be a serious problem, but the obligation on the private power-generation companies to procure the right of way is a concern.
Pursuant to the Electricity Act 2018, the power-generation company reserves the right of way over the land and the space above or underground, for the purpose of laying power supply lines or doing civil works, subject to certain terms and conditions. This includes payment of a compensation amount to the person affected if any damage, harm or inconvenience is caused while doing civil works. The government promulgated the Electricity Rules in 2020, which provide further details on the notification requirements and compensation mechanism with respect to right of way. The Electricity Rules also outline the procedure to be followed for acquisition of the land on which the tower is to be installed.
In the absence of these express provisions, power-generation companies were struggling to construct these interconnection lines, which resulted in an overall delay in the implementation of projects. The new rules have been issued to assist the project company, but only time will tell to what extent they will resolve the existing issues.
Recent Impediments
The Bangladesh economy has been facing considerable challenges with global economic uncertainty, rising inflationary pressure, dwindling foreign exchange reserves and fuel shortage. The country also faced disruptions to electricity supply due to erratic weather this year, with soaring temperatures pushing up demand in April and a deadly cyclone cutting off supplies of natural gas to power plants the following month. These resulted in frequent power cuts during April and May 2023.
However, the government of Bangladesh is giving top priority to the power sector and is exploring alternative ways to meet the soaring demand for electricity. The situation had already improved in June 2023, when power cuts were significantly reduced.
Moreover, following the Russia–Ukraine war, EP-DP payments became less regular than before. Furthermore, even when money was accessible, it was still challenging to make payments because of Bangladesh’s USD crisis. Consequently, a number of projects had to come up with innovative schemes to guarantee that USD would be available for payments.
Conclusion
The government of Bangladesh wants to increase the share of power generation from renewable sources to 40% of the production mix by 2050. With the ongoing initiatives and strategies, Bangladesh is expected to attract further investment in the power sector, mainly the renewables sector, on which it can build a sustainable future.
3rd floor, Darus Salam Arcade
14 Purana Paltan
Dhaka – 1000
Bangladesh
+88 029 566 100
www.farooqandassociates.com