Contributed By Drew & Napier LLC
Singapore’s construction market and built environment sector is governed by several key statutes and regulations, including the following.
Many of the relevant codes and regulations can be accessed at the official website of the Building and Construction Authority, and statutes and sub-legislation can be viewed at Singapore Statutes Online.
The legal system of Singapore also includes the common law or judge-made precedents. The laws of contract, tort, equity and restitution are some areas of the common law that play a significant role in governing the rights and obligations between parties and legal remedies when rights are breached.
There are significant differences between construction contracts in Singapore using local standard forms and more “international” contracts using international standard forms.
Local Projects
Many public sector contracts use the following standard form contracts:
For certain projects, it is quite common to utilise the bespoke standard form of a certain employer, such as the Land Transport Authority.
For private sector projects, popular standard forms include:
Projects With an International Element
On the other hand, large projects with an international element or flavour – such as those on Jurong Island, where many companies in the petroleum and petrochemical industries operate – adopt other contracting models, such as:
It is common for such projects to use popular international standard forms (or bespoke terms based on these forms), such as:
The Building and Construction Authority of Singapore is currently facilitating and trialling the use of collaborative contracting models for public sector projects, with an optional module to the PSSCOC or NEC4 being adopted for use.
In May 2024, the NEC released secondary Option clauses (Y (SG) Clauses) for use in Singapore, to support the use of NEC4 Engineering and Construction Contracts in Singapore. The clauses cover national legislative requirements for contracts, and were produced in parallel with the Singapore Building and Construction Authority.
There are no mandatory standard contracts at law, although public tenders may specify the standard form to be used. Except for certain categories of contracts that are excluded, construction contracts in the built environment sector in Singapore, along with related supply contracts for goods and services used in construction, are governed by the SOPA, which provides for a low-cost and fast adjudication mechanism to resolve payment disputes. Determinations under the SOPA have “temporary finality” until the dispute is finally determined by a court or a tribunal. The SOPA cannot be contractually excluded by contract, and contractual provisions that are inconsistent with the SOPA or undermine its intention are void.
Based on statistics published by the Building and Construction Authority of Singapore, public sector projects typically account for slightly more than half of the value of construction projects in Singapore. The employers in public sector projects such as utilities and roads, ports, train stations, hospitals and public housing projects are government agencies, statutory boards and government-linked corporations.
The employers in private sector projects are often private developers and owners, especially for residential or mixed-use projects, factories and warehouses, whilst multinational corporations and special-purpose vehicles owned by them are the employers for large private sector infrastructure projects such as petrochemical plants on Jurong Island, data centres and iconic infrastructure such as the Marina Bay Sands Integrated Resort.
The rights and obligations under a construction contract in Singapore will depend on the terms of the contract as well as general law. Generally, the employer will be entitled to delivery of the project by a certain date, at a fixed or ascertainable price. The employer will be entitled to liquidated damages for delays, but will correspondingly be obliged to grant extensions of time for delays for which it is responsible or has taken on the risk. The employer will be entitled to instruct variations to the work, and to grant cost and time adjustments as necessary. The employer must provide access, respond to claims within agreed timeframes, and make payment within an agreed timeframe after the amount payable is certified. Both the employer and the contractor will have termination rights in agreed scenarios, such as serious default or repudiatory breach by the other party. The parties will also agree on the dispute resolution mechanism, such as arbitration or litigation, and on applicable substantive law.
It is common for a main contractor to parcel out work to subcontractors, who contract only with the main contractor. There is privity of contract such that the terms of each subcontract and the terms of the main contract are not necessarily the same, although there is a practice in some projects of making obligations in a downstream subcontract “back to back” with rights and obligations in the upstream contract.
Although the employer has no direct contractual relationship with the subcontractors, suppliers and subconsultants down the line, the employer (who is often the occupier of the site) will nevertheless owe certain duties to the parties who are working at the site, such as duties relating to health and safety. The terms of the contract between the employer and the main contractor will usually seek to allocate risks arising from the actions of third parties to that contract.
The employer will usually have a separate relationship to the financier, governed by a separate contract for project finance aspects. However, the financier may sometimes require “step-in” rights within the construction contract between the employer and the contractor, to enable the financier to intervene and deal directly with the contractor in certain situations, such as if the project becomes distressed or the employer becomes insolvent.
The types of company that typically act as contractor range from local subsidiaries of foreign contractors and international contractors to regional players and homegrown local construction companies. The type of vehicle will often depend on factors such as the type of work to be carried out and the employer’s requirements. It is also quite common for foreign contractors to undertake large infrastructure projects in partnership with a local company, whether by way of a formal corporate joint venture vehicle or by way of a joint venture agreement that deals with the respective responsibilities and obligations of each party.
Contractors who carry out the following works for public or private sector construction projects are required to hold a builders’ licence:
The licensing requirements are set out in more detail in the Building Control Act 1989 and regulated under the Builders Licensing Scheme, which regulates the works allowed to be carried out under the relevant builder’s licence.
For larger public sector projects, there will be a tender process and the contractor will usually need to meet certain requirements, such as financial capability and track record requirements; the exact requirements will depend on what is stipulated in the employer’s requirements or tender requirements, if any. It can be difficult for a newly incorporated company to meet these requirements.
For some employers and developers, there is a practice of requiring any foreign contractor to have a local joint venture partner present in Singapore, for greater accountability and to mitigate risks.
The rights and obligations under a construction contract in Singapore will depend on the terms of the contract, as well as general law. Generally, the contractor will be obliged to deliver the project by a certain date, and in return is entitled to be paid a fixed or ascertainable price. The SOPA provides a statutory framework for the contractor to seek progress payment claims, and a fast and low-cost adjudication mechanism to resolve payment disputes, which cannot be excluded by contract. The contractor will be obliged to pay liquidated damages for delays, but will correspondingly be entitled to seek extensions of time for delays for which the employer is responsible or has taken on the risk. The contractor will be obliged to carry out variations to the work instructed by the employer, and is entitled to cost and time adjustments as necessary. The contractor is entitled to be provided with access, and to payment within an agreed timeframe after the amount payable is certified. Both the employer and the contractor will have termination rights in agreed scenarios, such as serious default or repudiatory breach by the other party. The parties will also agree on the dispute resolution mechanism, such as arbitration or litigation, and on the applicable substantive law.
Please see 2.1 The Employer regarding the relationship between the contractor, the employer, the subcontractors and the financiers.
The type of company that typically acts as subcontractor may be:
Some trades, such as the testing and commissioning of petrochemical plants, may be so niche that a foreign subcontractor has to be engaged. However, subcontractors who seek to work in certain specialist areas that usually have a high impact on public safety will have to comply with licensing requirements.
Some contracts may stipulate that the contractor or subcontractor must work with a specialist sub-subcontractor or supplier down the line of the upstream party’s choice (ie, a nominated subcontractor) to construct a specific part of the work.
Please see 2.1 The Employer regarding the typical rights and obligations under a construction subcontract in Singapore and the relationship between the contractor, the employer, the subcontractors and the financier.
In Singapore, construction projects are typically financed by:
Financiers do not typically contract directly with contractors under the main construction contract, but exercise control and protection through finance documents and associated security structures. They do not ordinarily assume rights or obligations under the construction contract, unless they are expressly granted such rights by contract (eg, through step‑in rights triggered upon borrower/employer default) or have rights and obligations only under collateral agreements such as loan agreements, and performance or advance payment bonds.
Professionals and professional firms such as architects, engineers and engineering consultants typically act as designers for the permanent works in construction projects in Singapore. The design of temporary works is typically carried out by the main contractor and/or engineering staff or suppliers, such as crane suppliers who carry out designs for lifting operations.
A designer generally owes contractual duties to exercise reasonable care, skill and diligence, and may provide express contractual warranties such as that the design will comply with specified requirements and specifications. Depending on the form of contract and the project structure, the designer may also be subject to general or specific fitness for purpose obligations.
In tort, a designer ordinarily owes a duty to exercise reasonable care and skill in the provision of its design services, subject to the application of the principles of foreseeability, proximity and public policy, and any contractual limitation or exclusion of liability.
In design‑and‑build or turnkey projects, the designer is commonly engaged directly by the contractor and therefore has a direct contractual relationship with the contractor rather than the employer. In build‑only projects, the designer is typically engaged by the employer, and does not usually have a direct contractual relationship with the contractor.
The scope of works under a construction contract is determined based on the interpretation of contractual documents.
Most of the standard form contracts – such as the SIA Conditions of Contract, PSSCOC, REDAS and typical bespoke contracts – provide that the contract documents, including specifications and drawings, are mutually explanatory and are to be taken as a whole. It is common for an obligation to be placed on the contractor to review the documents and identify inconsistencies or ambiguities and seek clarification. There is therefore a package of contractual documents that describe what is to be designed, constructed, tested and completed.
A typical construction contract may contain:
The determination and limitation of the scope and price for employer-requested variations in Singapore construction contracts are governed first and foremost by the express terms of the contract, including any procedures for instructing and valuing variations. Statutory law, particularly the SOPA, provides a fallback mechanism for valuation where the contract is silent, directing that work be valued according to contract rates, agreed adjustments or, failing that, prevailing industry rates.
If the contract is silent or ambiguous, the courts will look to the parties’ objective intentions and conduct to determine whether a variation has been agreed. The absence of a formal variation clause does not preclude the possibility of a variation, provided there is evidence of agreement or instruction.
The starting point for determining the scope of a variation is the contract itself. Most standard form construction contracts in Singapore (such as the SIA, PSSCOC or REDAS forms) contain detailed provisions defining what constitutes a variation, the procedures for instructing variations, and the limits on the employer’s power to order variations. Typically, a variation is defined as work that is not expressly or impliedly included in the original contract scope but is required by the employer.
Where the contract is clear, the scope of a variation is limited to what is authorised by the employer (or their representative) in accordance with the contractual procedure. The employer cannot unilaterally expand the scope beyond what is permitted by the contract, and the contractor is generally not obliged to perform work outside the contract scope unless a valid variation order is issued.
The price for a variation is, in the first instance, determined by the contract. Most contracts specify that variations are to be valued using agreed rates or prices, or by reference to a schedule of rates. If the contract does not provide a mechanism for valuing the variation, or if the variation is of a type not contemplated by the contract, the SOPA (assuming it applies to the work in question) requires that the work be valued by reference to the contract price, any specified rates or, failing that, prevailing industry rates at the time the work was performed.
Where the parties have agreed to a specific price for the variation, that price will generally be binding. If no agreement is reached, the contractor may be entitled to a reasonable price, assessed by reference to the contract rates or, if none are applicable, to market rates.
Any defects in the work are to be taken into account by deducting the estimated cost of rectification.
Time-related costs for variations in Singapore construction contracts are generally managed according to the terms of the contract, with standard forms providing detailed procedures for valuing such costs, including the possibility of extensions of time and compensation for prolongation. Where the contract sets out a mechanism for valuing time-related costs, that mechanism will generally be followed. This may involve the use of agreed rates or prices, or, in the absence of such agreement, the assessment of costs based on prevailing industry rates at the time the work was carried out.
Where the contract is silent, these costs may need to be assessed based on the actual delay and expenses incurred, often with reference to prevailing industry rates.
If a claim for time-related costs is brought in the form of damages for breach of contract, its quantum will have to be proven by the claimant in the same way as any claim for damages.
Some of the standard forms in Singapore provide certain limitations on the ability to claim for damages in the form of disruption, and some contracts will impose exclusions for possible heads of claim, such as loss of profits and indirect loss or indirect costs.
There is no “one size fits all” approach to contractual relationships and risk allocation in Singapore, as much will turn on factors such as the risk appetite and corresponding pricing solution, relative bargaining power, market practice in that specific trade, and so on.
In the context of the design process, commonly used contracting models for project delivery include:
In traditional “build-only” contracts, the project developer directly engages architects, designers, contract administrators and technical consultants/engineers, and then awards a contract to the contractor for construction work only in accordance with the designs and requirements produced by the employer with the assistance of the consultants.
In “design-and-build” contracts, the contractor will be responsible not just for carrying out the construction work, but also for the design and requirements of the contract. This will commonly include an obligation to ensure that the works are fit for purpose. This substantially shifts the risks relating to design towards the contractor, and the contractor will correspondingly price for such risks.
In EPC contracts, the contractor is obliged to turn over a fully functioning project to the employer. Thus, the contractor assumes the majority if not all of the risks relating to design.
There are variants in contracting models such as ECI or FEED, where the contractors are engaged at an early stage to provide input to the design consultants through early collaboration.
It is also common for foreign contractors to undertake projects in partnership with a local company, whether by way of a formal corporate joint venture vehicle or by way of a joint venture agreement, where the respective responsibilities of each party will be agreed, including in relation to design.
It is usually the contractor who carries out the construction work.
It is common for an EPC or main contractor to parcel out subcontracts to various third parties, particularly professionals who carry out certain specific roles that require professional licences, such as architects, professional engineers or checkers, and to subcontractors to carry out work in specific trades, such as lift and escalator works, plumbing works, electrical works and so on, where specific licences are required.
It is also common for employers to engage a professional representative to manage the project, oversee and deal with the contractor, and manage claims and notices that may be given by the contractor during the construction process, such as claims for extensions of time or variations.
The roles and responsibilities ought to be defined with sufficient clarity in a responsibility matrix within the project documentation.
The obligations, risks and responsibilities of each party in relation to the status of the construction site will typically be allocated between the parties under the terms of the construction contract. It is generally open to the parties to agree how to allocate the obligations, risks and responsibilities, subject to a few areas where obligations are mandated by law or regulation. Such areas include:
It is common for an EPC or main contractor to parcel out subcontracts to various suppliers and subcontractors, and it is also common for employers to engage a professional representative to manage the project. The roles and responsibilities ought to be defined with sufficient clarity in a responsibility matrix within the project documentation.
The obtaining of permits is governed by statute and regulations, although the parties may sometimes contractually agree between themselves (unless mandated by statute) who is responsible for obtaining the relevant permit.
Before construction commences, a developer may be required to obtain planning permission from the Urban Redevelopment Authority (URA) under the Planning Act. To commence building works, approvals are generally required under the Building Control Act and associated regulations, including the approval of building plans by the Building and Construction Authority (BCA) and the approval of structural plans, which must be endorsed by a qualified person and approved by the BCA before structural works may begin.
Where the project involves fire safety or dangerous works, such as those involving lithium-ion batteries, the building owner or developer may be required to obtain approval for the relevant plans from the Singapore Civil Defence Force (SCDF) under the Fire Safety Act.
Depending on the nature and location of the works, additional specialist permits or clearances may also be required from other statutory authorities, such as:
For larger projects, upon completion of construction works, the employer or building owner is generally required to obtain a Temporary Occupation Permit (TOP) from the BCA before the building may be occupied on a temporary basis, and a Certificate of Statutory Completion (CSC) must be obtained from the BCA for permanent occupation. Depending on the specific characteristics of the project, additional approvals from other authorities may be required before the TOP and CSC are issued.
Where fire safety works for designated public, industrial and commercial buildings are involved, the employer or building owner must also obtain a Fire Certificate (FC) from the SCDF before occupation is permitted.
In Singapore, responsibility for the maintenance of the works will depend mainly on the contractual arrangements between the parties.
During the construction period, the main contractor is typically solely responsible for protecting the works and maintaining temporary works, until handover. This will typically be provided for in standard or bespoke construction contracts.
After completion and handover, responsibility for routine and long‑term maintenance generally shifts to the employer or building owner. Some forms of operation and maintenance may be undertaken by the contractor.
Certain specialist and complex projects may have a specific maintenance regime, such as power plants or solar farms. These will be entered into in a specific collateral contract, such as by a specialist operator under a separate O&M or facilities management agreement.
There are also separate contractor obligations during defects liability periods, and warranties where the contractor’s responsibility post-completion (and the corresponding right to enter to rectify them) is to rectify defects, rather than carry out maintenance.
Under typical build-only and design-and-build models, the construction contract does not significantly provide for other functions, although short‑term operational support or training can sometimes be provided for.
Functions that extend significantly beyond completion are not mandated by law and are instead governed by contract, often through agreements separate from the construction contract or through clearly defined additional scopes within integrated project documents. These can include:
In Singapore, tests for completion are primarily governed by contract. These tests will have a bearing on whether practical completion is achieved and whether the works are sufficiently complete for takeover and use. Testing is usually conducted in stages and may include:
Various tests may be carried out during the process of construction, such as concrete compression strength testing to ascertain compliance with standards and contractual requirements.
The contractor is ordinarily required to give notice that the works or relevant sections are ready for testing and to submit test procedures, programmes and results in accordance with the contract and specifications.
Successful completion of the prescribed tests is commonly a precondition to certification of practical completion.
In Singapore, completion, takeover and delivery are related but conceptually distinct matters. These and the precise mechanics and consequences are primarily governed by contract.
Unless completion is expressly defined otherwise under the contractual terms, completion typically occurs when the works have reached practical completion – that is, the works are substantially complete and ready for occupation and use, save for minor defects. Under many of the standard forms, completion is certified by the contract administrator, architect or Superintending Officer. When completion occurs, the upstream party’s entitlement to be paid delay liquidated damages (that may be payable if the works are completed after the stipulated date for completion) stops running.
Handover and/or takeover occurs when possession and control of the works are passed back from the contractor to the employer. Generally, the risks in relation to the works are passed to the employer, and the defects liability/maintenance period commences.
Delivery is not usually treated as a separate legal concept, but will form part of the takeover and handover procedures. This may include the delivery of as‑built drawings, operation and maintenance manuals, and the obtaining of statutory approvals (such as TOP and CSC).
In Singapore, a contractor may be held liable for defects through contractually agreed mechanisms, most commonly a defects liability period (DLP), as well as through claims brought within the applicable statutory limitation periods. The DLP typically lasts around 12 months from completion, although parties may agree to longer periods.
During the DLP, the employer may require the contractor to rectify defects arising from defective workmanship, materials or non‑compliance. If the contractor fails to do so, the employer may carry out the rectification itself or by employing a third party, and recover the reasonable costs of rectification, including by set‑off against payments due or deductions from retention sums.
The DLP also benefits the contractor as it gives them a right to re-enter to rectify the defects and therefore contain the rectification costs of works that it is able to carry out itself, before the employer may proceed to carry out rectification itself or by employing a third party and recovering the costs of doing so.
The expiry of the DLP does not extinguish liability. Claims in contract or tort may still be brought within six years from accrual of the cause of action, and within three years from discovery for latent defects, subject to a 15‑year longstop.
There are no mandatory statutory rules prescribing defect notification periods, which are primarily governed by contract.
The method of determining the contract price depends on whether it is a lump sum or measurement contract.
Lump Sum Contract
Construction contracts are most commonly structured as lump sum contracts, particularly under the SIA Conditions of Contract 9th Edition 2016 (SIA) and REDAS 4th Ed 2022 (REDAS) forms, where the contract price is the contractor’s interpretation of the tender documents and such a sum is fixed, subject to adjustments for variations.
Measurement Contract
In a measurement contract, the contract price is based on an established Bill of Quantities provided as part of the tender document, and subject to a remeasurement of the works at completion.
Public Sector Standard Conditions of Contract for Construction Works 2020 (PSSCOC), like SIA and REDAS, provides for lump sum contracts but also accommodates remeasurement structures for specific areas of the work, and only for public sector works.
Components of the Contract Price
The contract price typically comprises:
Milestone Payments
Under SIA, payments may be based on periodic valuation or milestone payments, while PSSCOC provides for progress payments through periodic valuation mechanisms. In practice, interim payments in the form of monthly progress payments are more commonly adopted. See 4.4 Invoicing for more detail.
The indexation of prices is not automatically adopted in construction contracts and is typically incorporated only where expressly provided through fluctuation clauses, which are optional.
Fluctuation Clauses
Under SIA, fluctuation is dealt with expressly as an optional clause, which provides a mechanism for the adjustment of the Contract Sum based on prescribed indices or cost changes. REDAS also provide for fluctuation provisions where expressly included, allowing adjustment of the contract sum in response to changes in the cost of labour and materials. Like SIA, such clauses are optional and must be expressly incorporated.
PSSCOC contains provisions for price fluctuation adjustments, typically for labour and materials, where specified in the contract, using formula-based mechanisms tied to published indices. These provisions are more commonly used in public sector projects of long duration where inflation risk is material.
It is common for construction contracts to opt out of the inclusion of a fluctuation clause, with the exception of contracts with a long duration.
Risk for (Large) Price Fluctuations
In practice, where no fluctuation clause is included, the contractor bears the full risk of price increases, consistent with the lump sum allocation of risk. Conversely, where fluctuation clauses are included, price risk is shared between the parties through pre-agreed formulae and indices.
Construction contracts rely heavily on statutory and contractual payment protections, particularly under the SOPA, to manage late or non-payment. This protection typically covers interim payments, retention monies, certification mechanisms and remedies for non-payment.
Advance, Delayed and Interim Payments
Advance payments are not typical but may be provided in specific project types – for example, in prefabrication-heavy projects where upfront procurement costs are significant.
Delayed payments are primarily addressed through statutory adjudication under the SOPA, supported by contractual rights such as interest on late payment, suspension of works and eventual termination.
Interim payments are standard and closely aligned with the SOP regime. See 4.4 Invoicing.
Invoicing is typically carried out through a payment claim regime, aligned with the SOP framework. Contractors submit monthly payment claims, which are then assessed by the contract administrator.
Progress Claim
Under SIA, the contractor submits a payment claim, following which the architect issues an interim certificate stating the amount due, effectively serving as the payment response. Similarly, under PSSCOC, the contractor submits progress payment claims, which are evaluated and certified by the Superintending Officer within prescribed timelines. REDAS adopt a comparable certification-based mechanism.
The process generally involves:
This structured certification process ensures compliance with SOP requirements and provides a clear basis for payment and, if necessary, adjudication.
Planning is generally contractor-led but subject to oversight by the contract administrator.
Under SIA, the contractor is required to submit a programme showing the sequence and timing of the works, including methodology, for the architect’s review. Similar obligations exist under PSSCOC, where the contractor must provide and update a detailed programme for monitoring by the Superintending Officer.
Planning is safeguarded through several contractual mechanisms, including the submission and periodic updating of the programme, ongoing progress monitoring against the programme, and the use of interim certificates tied to progress of works. In addition, projects may incorporate milestones or sectional completion requirements, which are often linked to payment stages or key completion obligations, ensuring alignment between time, progress and cash flow.
Construction contracts impose strict notice and mitigation obligations in relation to delay. Under SIA, the contractor is required to give timely notice of delay events and to submit supporting particulars, following which the architect assesses entitlement to an extension of time. Similarly, under PSSCOC, the contractor must notify delay and provide details for the Superintending Officer’s assessment of time and cost consequences.
Time-Related Relief
Time-related relief is typically addressed through two mechanisms:
Concurrent Delays
Concurrent delays are primarily addressed through contractual provisions. In practice, where delays are concurrent, contractors are often not granted an EOT, particularly where the contractor’s delay is operative on the critical path. Even if an EOT is granted due to a concurrent employer’s acts of prevention, the contractor is typically not entitled to recover prolongation costs, unless the contract expressly provides otherwise.
Liquidated Damages
The employer’s primary remedy for delay is liquidated damages (LDs), which accrue upon the contractor’s failure to complete the works by the contractual completion date. Under SIA, LDs are expressly provided as a pre-agreed rate payable for delay, allowing the employer to recover damages without proving actual loss. Similar provisions exist under PSSCOC, where delay damages are stipulated and recoverable upon late completion, and under REDAS, which likewise provide for agreed delay damages as the primary remedy for late completion.
Termination
In addition to LDs, employers are typically entitled to terminate the contractor’s employment for default, particularly where the contractor fails to proceed regularly and diligently or is in substantial delay. Upon termination, the employer may recover the additional costs of completing the works, including engaging replacement contractors and associated expenses, with such costs set off against monies due to the contractor.
Performance Bond
Employers may also call on performance security, such as performance bonds, to secure payment of losses arising from delay or non-performance, as provided across SIA, PSSCOC and REDAS.
In practice, LDs are the most commonly applied remedy, as they provide certainty, are straightforward to administer, and avoid the evidential burden of proving actual loss, while preserving the employer’s ability to pursue further remedies where contractually permitted.
The contractor must submit formal notice and substantiation of delay events, typically within strict contractual timelines. Typical grounds for an EOT include variations, acts of prevention or delay by the employer, force majeure events, and exceptionally adverse weather conditions, as recognised under SIA and equivalent provisions in PSSCOC and REDAS.
Entitlement to an EOT is assessed based on causation and critical path impact, requiring the contractor to demonstrate that the relevant delay event affected completion of the works. In practice, this is established through contemporaneous records, including programmes, progress reports and delay analyses, which are evaluated by the architect or Superintending Officer in determining the appropriate extension.
Force majeure is recognised to typically cover events such as war, riots, civil commotion and other exceptional circumstances beyond the parties’ control.
Under SIA, such events are addressed through provisions relating to force majeure, which may entitle the contractor to relief from delay and, in certain cases, termination rights. Similarly, PSSCOC includes provisions for force majeure events and exceptional risks, allowing for time relief and, where applicable, cost consequences, depending on the nature of the event. REDAS also recognise force majeure-type events, typically defined within the contract and providing for corresponding relief.
The scope of force majeure is largely a matter of contractual agreement, and parties may expressly define, limit or exclude certain events from qualifying as force majeure. The consequences of such events typically include extension of time for completion, and in some cases cost compensation where the contract so provides. In prolonged or severe cases, standard forms such as SIA and PSSCOC also provide for termination rights, allowing either party to bring the contract to an end if performance becomes impracticable due to the force majeure event.
Unforeseen circumstances are governed primarily by the terms of the contract rather than mandatory law, with risk allocation determined by the agreed provisions between the parties. Such circumstances are typically addressed through variation clauses, EOT provisions and broader risk allocation mechanisms.
Contractual Mechanisms
Under SIA, unforeseen matters are generally dealt with through the variation regime and EOT provisions, which allow adjustments to time and cost where instructed changes or qualifying delay events arise. REDAS adopt a similar approach, relying on contractual variation and time extension mechanisms to address unforeseen issues encountered during the works. By contrast, PSSCOC provides a more structured and express treatment of unforeseen site conditions, including provisions that allocate risk for physical conditions encountered on site and allow for corresponding adjustments to time and cost where such conditions differ materially from what was reasonably anticipated.
In all three standard forms, the allocation of risk for unforeseen circumstances ultimately depends on the contractual framework, with relief typically granted through established mechanisms for valuation, time extension and compensation, rather than any overarching doctrine of hardship under Singapore law.
Disruption is recognised as a basis for loss and expense claims, although it is not expressly defined.
Act of Prevention by the Employer
Under SIA, contractors may recover loss and expense arising from an employer’s act of prevention, which can include disruption where such events materially affect the regular progress or productivity of the works. Similarly, PSSCOC provides for recovery of additional costs incurred due to delays or disruption caused by the employer, subject to proper notice and substantiation. REDAS adopt a comparable approach, allowing claims for additional costs arising from events attributable to the employer or other qualifying causes.
To establish disruption, the contractor must demonstrate actual loss of productivity and a clear causal link between the disruption and an employer’s act of prevention, and support the claim with contemporaneous records, such as site records, labour outputs and programme updates. In practice, such claims are complex and evidence-intensive, often requiring detailed analysis to substantiate both causation and quantum.
Parties generally have freedom to allocate risk and exclude liability by contract. However, certain liabilities cannot be excluded or are subject to statutory controls.
Wilful misconduct is recognised under Singapore common law and generally refers to intentional wrongdoing or reckless disregard of known risks. As a matter of public policy, it will typically fall outside the scope of contractual limitation or exclusion clauses.
Gross negligence is not a distinct legal category under Singapore law. It is treated as a factual description of serious negligence unless specifically defined in the contract.
These concepts are governed primarily by common law rather than statute, although statutory controls such as the UCTA may affect the enforceability of exclusion clauses.
Liability may generally be limited contractually. Typical approaches include financial caps, often linked to the contract sum or specific heads of loss, as well as the use of pre-agreed remedies such as LDs for delay. In addition, construction contracts generally operate to limit recovery to direct losses, with indirect or third party losses often excluded or not expressly recoverable within the contractual framework.
In practice, such limitation mechanisms most commonly apply to the contractor’s liability, particularly in relation to delay and defects.
Indemnities are used in construction contracts. The common areas covered include third party injury or property damage, breach of statutory obligations, and intellectual property infringement.
Under SIA, the contractor is required to indemnify the employer against claims for personal injury, death and damage to property arising out of the execution of the works. Similarly, PSSCOC provides for contractor indemnities in respect of third party claims, damage to property and statutory breaches arising from the contractor’s performance of the works. REDAS adopt a comparable approach, requiring the contractor to indemnify the employer against liabilities arising from the works, including injury, damage and infringement-related claims.
These indemnities typically operate broadly and are closely aligned with the contractor’s insurance obligations under the contract. See 7.3 Insurance for more detail.
Guarantees in construction contracts include performance bonds (on-demand or conditional) and parent company guarantees, which serve as key forms of performance security. These instruments are primarily governed by contractual terms and case law, rather than detailed statutory regulation.
Performance Guarantees
Under SIA, the contractor is typically required to provide a performance bond as security/guarantee for the due performance of its obligations, which may be called upon by the employer in the event of default. Similarly, PSSCOC requires contractors to furnish performance security, usually in the form of an on-demand bond. REDAS adopt a comparable approach, requiring performance security to safeguard the employer against non-performance or default.
In practice, the contractor is the primary provider of performance guarantees, while subcontractors may also be required to furnish guarantees, particularly in nominated subcontract arrangements.
Parent Company Guarantees
Parent company guarantees may also be required, providing further assurance of performance and financial standing.
Typical insurances include Contractors’ All Risks insurance, third-party liability insurance, work injury compensation insurance, and contractor’s plant and equipment insurance, forming a key part of the contractual risk allocation framework.
Under SIA, the contractor is required to procure and maintain insurance covering the works, third-party injury or property damage, and liability arising from the execution of the works. Similarly, PSSCOC provides for comprehensive insurance requirements, including insurance of the works, third-party liability and statutory insurances, to be maintained throughout the project. REDAS adopt a comparable regime, requiring the contractor to insure the works and associated risks, including injury and property damage.
These insurance policies operate to allocate risk between the contracting parties and insurers, ensuring that specified risks are transferred to insurers, while also supporting the indemnity framework under the contract.
Construction contracts provide for termination upon the insolvency of a party, with detailed consequences governing the parties’ rights and obligations.
Entitlement to Termination
Under SIA, the employer is entitled to terminate the contractor’s employment upon insolvency, including where the contractor becomes bankrupt or unable to pay its debts. Similar provisions are found in PSSCOC and REDAS, which allow termination and re-entry where the contractor becomes insolvent or financially incapable of performing the works.
Upon such termination, several consequences follow, typically including:
Call on the Performance Bond
In addition, the employer may rely on performance security to offset losses arising from the contractor’s insolvency. These provisions serve to ensure continuity of the project while protecting the employer against financial and performance risks.
Risk sharing in construction contracts differs depending on the procurement model, particularly between construction-only and design-and-build arrangements. In general, the risk is allocated to the party best placed to shoulder the risk.
Construction-Only Contracts
In construction-only contracts, risk is generally divided such that the employer bears design responsibility, including for the adequacy and co-ordination of design prepared by consultants, as well as risks relating to site access and instructed variations. The contractor, in turn, bears responsibility for workmanship, construction methods, sequencing and productivity in executing the works (SIA cl 12 on variations and cl 23 on delay). This reflects the risk allocation where the contractor builds to the employer’s design and is not responsible for design adequacy unless expressly stated.
Design-and-Build Contracts
By contrast, in design-and-build contracts (REDAS), the contractor assumes both design and construction risk, including responsibility for the fitness and co-ordination of the design as well as execution of the works. This results in a shift of design risk from employer to contractor, with the employer typically retaining only limited risks, such as changes to the employer’s requirements or certain site-related risks.
In both models, certain risks may be shared contractually, such as price escalation (see 4.2 Indexation). Overall, the allocation of risk falls mainly onto the contractor, and this risk is reflected in pricing at tender stage, with contractors pricing for the risks assumed, particularly more extensively under design-and-build arrangements where design liability is included.
Construction contracts in Singapore typically require the contractor to provide competent and adequately qualified site personnel.
Competent Personnel
Under SIA, the contractor must ensure proper superintendence and execution of the works, and comply with all instructions issued by the architect. Similarly, under PSSCOC, the contractor is required to deploy suitably qualified personnel and comply with directions of the Supervising Officer, who oversees contract administration and site execution. REDAS adopt comparable provisions, requiring proper staffing and compliance with the employer’s representative.
Statutory Requirements
In addition to contractual requirements, standard forms also require contractors to meet statutory personnel requirements and to appoint statutorily required personnel, such as workplace safety and health officers, technical officers and other designated roles mandated under legislation, particularly for larger or higher-risk projects. These roles are essential to ensure compliance with safety, regulatory and site management obligations.
Subcontracting is permitted but is subject to contractual control, with the contractor remaining fully responsible for the performance of all subcontractors.
Contractor Fully Responsible for Subcontractor
Under SIA, the contractor retains full responsibility for subcontracted works, including those carried out by nominated and domestic subcontractors, and assignment may require consent. Similarly, REDAS include provisions on subcontracting and assignment, emphasising contractor responsibility and employer consent requirements. PSSCOC likewise regulates subcontracting, maintaining that the main contractor remains liable notwithstanding delegation.
Standard Forms of Subcontract
In practice, standard forms of subcontract are commonly used alongside these main contracts, ensuring back-to-back risk allocation. Importantly, the main contractor is generally not permitted to subcontract the entirety or substantially the whole of the works without consent, as this would undermine the contractual allocation of responsibility.
Intellectual property typically remains with the party producing the design, while the other party is granted only a project-specific licence to use the design, with express restrictions preventing use beyond the project scope.
Construction-Only Contracts
SIA expressly restricts the contractor’s use of drawings and contract documents to the project, reinforcing that ownership does not pass to the contractor. PSSCOC adopts a similar structure, where design documents are controlled by the Superintending Officer, and the contractor’s rights are confined to execution of the works. These contracts reflect a clear separation between design ownership and construction obligations.
Design-and-Build Contracts
Under REDAS (a design-and-build contract where the contractor typically assumes responsibility for the design), the contractor retains intellectual property to their design but is subject to a licence in favour of the employer for the purposes of operating and maintaining the project, with restrictions on broader use or reproduction.
Overall, these provisions ensure that intellectual property rights are preserved while allowing the necessary licences for project execution, with clear restrictions preventing misuse or replication of design documents beyond the contractual scope.
An employer’s remedies against a contractor for breach of a construction contract may include:
A contractor’s remedies against the employer may include:
A consultant or designer may claim against the employer for unpaid professional fees and for damages arising from the employer’s wrongful termination of the consultancy agreement. The employer may claim against the designer in contract and/or tort for losses arising from negligent or defective design.
It is common practice for construction contracts to contractually limit the remedies available to parties. Such limitations serve as a mechanism of risk allocation and are common in standard form contracts as well as negotiated contracts. These limitations may take several forms, including:
In practice, Singapore courts generally uphold contractual allocations of risk in commercial construction contracts between sophisticated parties.
Parties’ freedom to contractually limit remedies is subject to certain constraints under Singapore law, including:
A contractual sole remedy clause limits the available relief for specific breaches to an agreed remedy or mechanism. This may have the effect of precluding the innocent party from seeking other remedies. The purpose of such clauses is to manage risk and they are, in substance, not uncommon in construction contracts. For example, defects liability provisions commonly provide that the contractor’s obligation is to rectify defects notified within the defects liability period, which may operate to limit the employer’s recourse to that contractual mechanism.
Extension of time contractual provisions are often drafted to define exhaustively the contractor’s entitlement for delay and disruption to liquidated damages, potentially excluding parallel common law claims, if properly drafted.
Final account provisions or certification mechanisms may operate to bar further claims unless they are brought within prescribed procedures.
In Singapore, construction contracts commonly exclude liability for certain categories of damages as part of the contractual allocation of risk. Typical exclusions include:
Notwithstanding contractual exclusions, liability for fraud cannot be excluded as a matter of public policy. Negligence may be excluded in principle, subject where applicable to the UCTA and the requirement of reasonableness.
Retention Rights
In Singapore, “retention” typically refers to a contractual mechanism rather than a freestanding legal right. Standard form construction contracts such as the SIA Conditions of Contract commonly provide for a portion of interim payments to be retained as security for the contractor’s performance and the rectification of defects.
Suspension Rights
Suspension rights in Singapore generally depend on their source. At common law, there is no broad right to suspend work for non-payment. A contractor who suspends without contractual or statutory entitlement risks being in repudiatory breach of contract.
Statutory suspension rights arise under the SOPA. They operate independently of the contract and cannot be excluded.
Contractual suspension rights are commonly found in standard form contracts, and they typically allow for suspension for non-payment or other serious breaches.
In Singapore, construction contracts may be terminated pursuant to the terms of the contract’s express termination regime or at common law.
Contractual Termination
A contract may be terminated pursuant to express contractual termination provisions, upon the occurrence of specified termination events. This may include contractor default, failure to proceed regularly and diligently, or breach of contract by the defaulting party. An example of such a clause is Clause 31.1 of the PSSCOC 2020.
Some construction contracts also allow a party to terminate without establishing any default by the other party. Standard forms provide expressly for this, such as Clause 31.4 of the PSSCOC 2020 or Clause 32(1) of the 2016 SIA Form. The consequences of such termination depend on the construction of the clause and contract as a whole.
The terms of the contract would be subject to any overriding statutes limiting when termination may occur (eg, Section 440 of the Insolvency, Restructuring and Dissolution Act 2018, which prohibits termination solely by reason of insolvency or commencement of judicial management or scheme of arrangement proceedings).
Termination at Common Law
A contract may also be terminated at common law on the following grounds:
Where termination is effected at common law, the innocent party is generally entitled to claim damages as of right for loss resulting from the breach, subject to any applicable legal constraints.
In Singapore, construction disputes may be resolved through both adjudicative processes (such as litigation, arbitration and statutory adjudication) and consensual processes (such as mediation and settlement). The main adjudicative fora are as follows.
Litigation
Construction disputes may be heard across the Singapore Court system, comprising:
Lower value construction disputes are typically commenced in the State Courts, subject to their jurisdictional limits. Higher value and more complex disputes are heard in the High Court. The General Division maintains a specialist list for construction cases, which are managed by judges with relevant expertise.
The SICC is designed to hear international commercial disputes, including construction disputes with an international element. It features both local and international judges, and has procedures tailored for complex, cross-border matters.
Statutory Adjudication Under the SOPA
Payment disputes in the construction industry may be referred to adjudication under the SOPA, which provides a fast and cost-effective dispute resolution mechanism intended to facilitate cash flow. An adjudication determination is binding on an interim basis, and must be complied with unless and until it is set aside by the court or the underlying dispute is finally determined.
Arbitration
Arbitration is commonly adopted in construction contracts in Singapore. Arbitration in Singapore is governed by two statutory regimes: the International Arbitration Act 1994, which applies to international arbitrations and incorporates the UNCITRAL Model Law, and the Arbitration Act 2001, which applies to domestic arbitrations.
Dispute Boards
Dispute boards are typically used in large infrastructure projects. For example, the FIDIC 2017 forms provide that disputes may be referred to a Dispute Avoidance/Adjudication Board (DAAB), whose decisions are binding when issued. The DAAB is a standing panel of experts appointed at the start of a project to prevent conflicts and provide fast, binding decisions on disputes so that work can continue.
In Singapore, the Singapore Infrastructure Dispute Management Protocol (SIDP) may be adopted, for example, under the PSSCOC 2020. Determinations are contractually binding. The SIDP is generally suited for complex infrastructure projects of substantial value.
Expert Determination
Expert determination is typically used for discrete technical or valuation issues. For example, Clause 39 of the 2016 SIA Form provides that parties’ disputes relating to technical issues may be referred for expert determination. The decision of the expert determinator is binding on an interim basis, and parties must comply with such decision unless and until the matter is revisited in subsequent court proceedings or arbitration.
See 10.1 Regular Dispute Resolution regarding adjudication, arbitration, dispute boards and expert determination as alternatives to litigation.
Parties may also elect to resolve disputes through mediation. For instance, the Singapore Mediation Centre provides mediation services for construction disputes. Whether a settlement reached through mediation is legally binding depends on usual contractual principles and whether there was an intention to enter into a legally binding settlement.
10 Collyer Quay
#10-01
Ocean Financial Centre
Singapore 049315
+65 6535 0733
+65 6535 4906
mail@drewnapier.com www.drewnapier.com