Construction 2024

Last Updated June 06, 2024

China

Law and Practice

Authors



Merits & Tree Law Offices has a real estate and infrastructure team led by four key partners and more than ten supporting partners, in addition to over 20 lawyers. The team provides contentious and non-contentious legal services in the sector, including construction and engineering of buildings and infrastructure, real estate development and sales, land acquisition, project mergers and acquisitions, urban renewal, property management and operation, project investment and financing, project tax planning and asset-backed securitisation. The lawyers advise local giant real estate developers as well as various construction companies in China, such as Vanke, Longfor and Greentown. The team provides strategic and professional solutions to clients on contract negotiation, bidding and tendering, construction claims and disputes, and on-demand guarantee-related matters.

Legal System

As a civil law country, legislation is a major source of Chinese law. The hierarchy of legislative instruments is roughly as follows:

  • the constitution passed by the National People’s Congress (NPC);
  • national laws passed by the NPC or its standing committee;
  • administrative regulations enacted by the State Council (the supreme administrative body in China); and
  • the implementation of administrative regulations issued by ministries and commissions of the State Council, local laws passed by the local People’s Congresses or their standing committees, and regulations issued by local governments. 

Principal Laws Governing the Construction Market

Primary national laws governing the construction sector include:

  • the Civil Code of the People’s Republic of China (PRC);
  • the Bidding Law of the PRC (2017 Amendment);
  • the Construction Law of the PRC (2019 Amendment);
  • the Urban and Rural Planning Law of the PRC (2019 Amendment); and
  • the Law of the PRC on Environmental Impact Assessment (2018 Amendment).

The Supreme People’s Court (SPC) issued a judicial interpretation on issues concerning application of the law in construction contract disputes on the basis of the Civil Code on 29 December 2020 and the interpretation has been in force since 1 January 2021. 

Moreover, several administrative regulations by the State Council deal with key aspects of the administrative side of construction practice, including:

Various implementation rules of administrative regulation issued by the Ministry of Housing and Urban-Rural Development (MOHURD), the National Development and Reform Commission (NDRC) and other ministries also play a relatively important role, providing detailed and practical rules on construction practice, such as:

  • the Provisions on Engineering Projects Which Must Be Subject to Bidding;
  • the Measures for the Administration of Bidding for the Construction of the House Building and Municipal Infrastructure Projects; and
  • the Measure for the Administration of EPC of the House Building and Municipal Infrastructure Projects.

Mandatory national standards approved and promulgated by the State Council are the technical and detailed support of the law. Enterprises that do not comply with the technical requirements of the publicised standards shall bear civil liability, be included in the creditworthiness records or bear criminal liability. Mandatory national standards must be implemented and play a relatively important role, providing detailed and practical rules on construction practice, such as:

  • the Standards for qualification of construction enterprises; and
  • the Code of valuation with bill of quantity of construction works.

Model Contracts

There are certain model contracts available for parties to use on domestic projects in the construction market. Although such use is not mandatory, the terms of these contracts reflect a reasonable allocation of risks and capture good practice, so parties usually adopt these model contracts with amendments on specific projects. Alternatively, parties may design bespoke contracts from scratch or may use the FIDIC (International Federation of Consulting Engineers) forms with amendments on some projects involving unique or foreign elements. 

These model contracts are jointly issued by MOHURD and the State Administration for Market Regulations or the State Administration for Industry and Commerce and may be revised or amended as necessary. The latest versions of some major model contracts are as follows:

  • the Model Subcontract Contracts (GF-2003-0213/0214) between a contractor and a subcontractor;
  • the Model Engineering Contract for Construction Projects (GF-2015-0209/0210) between an employer and an engineering designer;
  • the Model Cost Consultation Contract for Construction Projects (GF-2015-0212) between an employer and a consultant;
  • the Model Survey Contract for Construction Projects (GF-2016-0203) between an employer and a surveyor;
  • the Model Contract for Construction Works (GF-2017-0201) between an employer and a construction contractor; and
  • the Model Contract for General Contracting Projects (GF-2020-0216) between an employer and a general contractor.

Standard Bidding Documents

On 20 December 2011, nine ministries and commissions jointly issued the Short Form of Standard Construction Bidding Documents and the Standard Bidding Documents for Design-Construction Integrated Projects, which took effect on 1 May 2012. For projects that must by law be subject to the bidding process, parties are required to mandatorily use these two standard bidding documents, which include instructions for tenders, bid evaluation and general contract terms.

The employer commissions works in a construction project and is typically the holder of the right to use construction land. An employer may take different forms, such as a variety of companies, institutions and even a natural person, depending on the nature and type of project. 

Rights and Obligations

In general, prior to entering into a contract, the employer has the right to determine a suitable project contracting mode and to select a qualified contractor following legal requirements and procedures (if applicable). 

The employer’s rights and obligations vary depending on the nature and scope of the construction contract.

Typically, the employer has the right:

  • to appoint its own representatives or entrust an engineer/supervisor to supervise site works and inspect the contractor’s completed works, on the condition that there is no disruption to the contractor’s work; and/or
  • to terminate the contract on the basis of illegal subcontracting, etc. 

On the obligation side, the employer is typically required:

  • to obtain approval to use the construction land, and to obtain planning approval for the construction land and construction project, as well as the permit for the construction works;
  • to assist the contractor with the contractor’s applications for any permits and certificates; 
  • to give the contractor right of access to the site, to provide site conditions and information, and basic materials to the contractor;
  • to effect payment as agreed;
  • to organise tests and acceptance of the works upon completion; and
  • to file project documents and records with the local authorities.

Relations Between the Employer and Other Key Players

The employer and the contractor are parties to the construction contract, the terms of which are contractually binding as agreed. As to actual subcontractors in a scenario of illegal subcontracting, the employer might have legal responsibility to pay them directly, provided such payment is within the employer’s due and payable amounts to the contractor. Depending on modes of project financing, the financier can be the employer, or the employer’s shareholder.

The contractor carries out the works in a construction project and has the principal responsibility for completing the works. The contractor must have corresponding qualifications for undertaking the works and is not allowed to work beyond the scope and level of its qualification(s). Likewise, the company acting as contractor may take different forms but may not be a natural person. Complex projects are commonly undertaken by a joint venture. 

Rights and Obligations

The contractor’s role and responsibilities vary depending on the type of construction contract. The contractor has a typical right to be paid, to seek preferred payments of compensation for the unpaid amounts if the project quality is qualified and to claim for extension of time or costs if delays are caused by the employer. The contractor’s general obligations include:

  • executing and completing works within the agreed scope of the work and meeting technical standards and requirements; 
  • remedying defects within the defects notification period; 
  • assuming warranty obligations within the statutory periods; 
  • taking measures to ensure site safety and environmental protection; 
  • obtaining permits and certificates as necessary for construction works; and
  • co-operating with the supervisor or engineer as entrusted or appointed by the employer. 

Relations Between the Contractor and Other Key Players

If the contractor elects to subcontract part of the works to a subcontractor, the contractor and the subcontractor are both parties to the subcontracting contract. The contractor and subcontractors are jointly liable to the employer for the quality and safety of the works subcontracted.

It is very common in practice for the contractor to subcontract part of the works. Subcontractors are divided into two types: specialist subcontractor and labour subcontractor. A subcontractor is only allowed to undertake works within the scope and level of its qualification. Subcontracting works must also comply with legal and contractual requirements. Specifically, the contractor is restricted from subcontracting the entirety of the works to subcontractors. Illegal subcontracting may trigger the application of a series of legal consequences and the actual constructor may file a lawsuit against the employer directly for the construction project price. 

Rights and Obligations

Subcontractors share similar rights and obligations with the contractor for works subcontracted. A “pay if paid” or “pay when paid” clause is often seen in a subcontractor’s contract, meaning that the subcontractor’s right to payment under its contract may be subject to the contractor’s entitlement to payment under the main construction contract. The legal effects of such clause are in dispute in court practice. Subcontractors have no right to file a lawsuit against the employer directly, unless the contractor is negligent in exercising the creditor’s right that is due or the collateral right related to the creditor’s right, thus affecting the realisation of the creditor’s right that is due.

In traditional construction practice, the employer may raise funds on its own and the financiers would then be banks, financial institutions, shareholders or the employer itself. For government investment projects, the project funds would come from the financial budget of local or central governments. This traditional financial arrangement has changed in recent years and the contractor may also now participate as a financier. By way of example, in the creative PPP+EPC (Public-Private Partnership + Engineering, Procurement and Construction) model, the contractor may participate in project financing and also construction works, acting in the dual roles of investor/financier and constructor.

Rights and Obligations

The financier has the right to supervise the account of the project company, require the employee or the project company to mortgage the construction in progress and pledge the equity. There are many factors to consider in the guarantee setting, including whether the financier’s exercise of power affects the project operation, whether it triggers the termination of the commercial contract, etc. It is necessary to balance the interests of the financier and the project company. To take account supervision as an example, the financier hopes to control income and control dividends so that priority can be given to repayment of excess funds; the employer hopes to retain control and dividends payment. The failure to balance may lead to project cash flow problems, which will adversely affect employers and financiers.

Relationship

Contractors and subcontractors play an important role in the construction of the project, and their credit is also one of the important factors for the financiers to consider in deciding whether to provide finance. The financier, the employer, the contractor and the subcontractor form a project team by entering into various agreements and are the relevant parties of the project. By taking into account the interests of all parties, and through sound co-ordination, parties can achieve a reasonable sharing of risks and an amicable resolution of conflicts.

According to the Construction Law of the PRC, the construction designer is required to hold a qualification of design issued by the MOHURD. Such qualifications are classified into different categories to include general construction and specific industries (eg, chemical engineering, energy, railway, etc), as well as different levels depending on the scales of projects. The MOHURD will update the qualification rules every five to ten years.

Most of the holders of the qualifications are state-owned designing institutes, among which many are attached to state-owned contractors, universities or governmental departments. However, in the past 20 years, many private companies have cometed with state-owned institutes by obtaining more comprehensive qualifications and by establishing a more flexible business model. There are many foreign-invested studios led by overseas architects playing an important role in the high-end projects such as city landmarks and avant-guard complexes. However, they have to co-operate with a qualification-holder so that the official design work is produced under the name of the qualified institute.

Rights and Obligations

The rights of the designer under a common contract are not overwhelming. The designer must follow the instructions of the project owner regarding the technical specifications of the project, although mostly the project owner will leave the designer much discretion for the details of the design work.

In common practice, the design drawing is not deemed to be the intellectual property of the designer, for the reason that the drawing work is paid for and purchased by the project owner.

The designer is not allowed to designate any specific brand or producer of the construction materials in the drawing. However, the designer may recommend a range of brands or a grade of the reputation of the producer to the project owner.

It is the designer’s obligation to follow the national standards of construction quality and safety. The main design engineer of the project shall be personally responsible for the quality and safety of the project for its designed life.

Relationship

In a general construction contracting model, the designer and the contractor will have separate and independent contractual relationships with the project owner. Therefore, they will have to inter-relationship. If there is any design mistake to correct or optimisation to apply, the general contractor will report to the project owner, and the project owner will then consult the designer for further decision.

A typical construction contract is formed of several documents, listed below in order of priority:

  • contract agreement; 
  • particular conditions;
  • general conditions;
  • technical standards and requirements;
  • drawings;
  • bill of quantities or budgets; and
  • any other documents forming part of the construction contract. 

The scope of the works is firstly described in the contract agreement in a general way. Then particular conditions and general conditions may provide a brief description of the scope of the works by referring to drawings and bills of quantities. Finally, drawings and bills of quantities supply more details. Sometimes, certain project items will be additionally defined in terms of technical standards and requirements. 

In fact, for projects procured through a bidding process, both the employer and contractor may determine and settle the scope of the works in a letter of award and a letter of tender and its schedules. Specifically: 

  • the employer may include drawings in the bidding documents, in which the scope of the works is determined;
  • the contractor will carefully study these drawings and put issues to the employer for clarification; and
  • upon the employer’s clarification, the contractor may prepare responses to the bidding documents, including parts related to the scope of the works. 

Occasionally, a programme and technical specifications are also used to define and determine the scope of the works in practice, while their major focus is about the standard of quality rather than the scope of the works.

Variations by the Employer

The employer generally has the right to vary and often exercises such right via its entrusted supervisor or engineer. With the employer’s approval, the supervisor or engineer may issue a notice of variation to the contractor, which may list items to be varied and may (rarely) include a price for such variation. The contractor may then submit a proposal of costs on the variation to the supervisor or engineer within an agreed period upon receiving such notice. Next, the employer will review the contractor’s price proposal and may negotiate with the contractor to determine the price for the instructed variation. The usual practice is that parties may refer to the unit price of similar work items as prescribed in the construction contract when determining the price of the variation. If unit prices of similar work items are not stipulated in the contract and the two parties cannot reach an agreement on the price of the variation, the parties may refer to the pricing method or standard issued by the local construction administrative department when the contract is signed.

If the employer requests a design variation, the employer must also ask the engineer designer to provide detailed drawings and explanations of such variation. 

Variations by the Contractor

Unlike the employer, the contractor’s right to vary is limited. The contractor is not allowed to vary any part of the works unless the employer has approved this. The contractor has, however, the right to submit reasonable proposals to the supervisor or engineer that may accelerate completion, reduce costs or improve the value of the works, etc. The supervisor or engineer will relay such reasonable proposals to the employer for approval. If the employer approves, the supervisor or engineer will issue a notice of variation accordingly and the same procedure to determine the scope and price of the variation shall apply.

Responsibilities Regarding the Engineering Design

Which parties are responsible for the design process largely depends on which contracting model the parties select. 

In a general construction contracting model, the contractor’s scope of work only covers construction works that are implemented on the basis of detailed drawings and design documents provided by the employer. The employer will separately engage an engineer designer for design works. As such, the employer bears responsibility regarding the design under the construction contract, while the engineer designer is responsible for its design works under the engineer design contract with the employer. Article 805 of the Civil Code provides that the employer will compensate the engineer designer for actual costs on design work resulting from the employer’s change of plan, failure to provide accurate materials or failure to provide the necessary conditions for the design. 

In a general project contracting model (engineering, procurement and construction or design-build), the contractor is responsible to the employer for design work under the contract.

The contractor takes full responsibility for the construction works, including any subcontracting. If the contractor has subcontracted part of the works to a subcontractor, the subcontractor will be responsible for the subcontracted works. The contractor and subcontractor are jointly responsible to the employer for the safety and quality of the subcontracted works. 

The surveyor and designer shall be responsible for the quality of their survey and design. Survey and design documents shall conform to relevant laws, regulations, construction project quality and safety standards, technical standards for construction project survey and design, and the agreement in the contract. The supervisor shall supervise the quality of construction and bear liabilities for the supervision of such quality under the laws, regulations, relevant technical standards, design documents and the contract.

The contractor undertakes overall responsibility for the status of the construction site and such responsibility is mandatory under the law. Relevant articles in the Construction Law of the PRC deal with the contractor’s responsibility in this respect.

  • Article 39 provides that the contractor shall take measures to maintain security, prevent danger and fires and may adopt closed management if conditions permit; the contractor must also take protection measures to prevent the construction site from causing damage to adjoining buildings, structures or the operational environment for special works.
  • Article 40 provides that the employer will provide materials for underground piping and wiring and the contractor will take protective measures.
  • Article 41 provides that the contractor will comply with laws and administrative regulations relating to environmental protection and safety in production and take measures to control pollution and damages caused by various kinds of dust, leaking gas and water, solid waste as well as noise, vibration, etc.

Permits Required for the Construction Process

Normally, to proceed with construction works, the following approvals or permits must be obtained in advance: 

  • approval/certificate of the right to use the construction land;
  • planning approval for the construction land;
  • planning approval for the construction project; and
  • a construction permit.

Parties Responsible for Obtaining the Permits

The employer is responsible for obtaining all the listed approvals or permits required by mandatory law, thus all the applications are submitted in the name of the employer. In practice, it is often seen in a construction contract that the contractor is required to assist the employer with obtaining such approvals or permits by acting on the employer’s behalf and preparing the relevant documents.

The contractor is responsible for maintenance of the works until all the works and the site are handed over to the employer upon completion. The contractor’s maintenance work typically includes looking after the site; inspection and examination of constructed parts; and supervision and repair of utility connections and the power supply. Maintenance works are generally included in the contractor’s scope of work in the construction contract. It is rare for parties to enter into a separate contract specifically dealing with maintenance work.

In a typical construction contracting model, the contractor undertakes only the construction work, while other works are undertaken by third parties such as surveyors, designers, suppliers, supervisors, etc. The employer may separately engage an operator to manage the business operation of the project. 

In complex contracting models incorporating project financing, such as BOT (Build-Operate-Transfer), BOOT (Build-Own-Operate-Transfer), F-EPC (Finance + EPC) and PPP-EPC, the contractor, employer and other third parties, such as financial institutions and project companies, may be involved at different stages and to varying degrees in project financing, transfer and operation.

For industrial projects, tests for completion of the works are very common. In a typical construction contract, the contractor may prepare and submit a plan of completion test and the employer, after consulting with the supervisor or engineer, may approve the contractor’s plan of completion test. The contractor will then conduct the test according to the approved plan under supervision by the supervisor and/or the employer.

If the works fail to pass the tests, the contractor shall re-test the works after they have been repaired. If the works fail the re-test, the employer will assume the costs for the tests if such failure is on the employer’s part. The employer may exercise various remedies if such failure is on the contractor’s part, such as requesting the contractor to remedy defects at its own cost, compensate damages caused, exercise rights of set-off, rejection, termination, etc.

A typical completion proceeds as follows.

  • Preliminary specialised examinations are conducted by several administrative bureaus such as firefighting, urban planning and lightning protection.
  • If the employer considers conditions are ready for acceptance, the employer will convene the surveyor, the designer, the contractor and the supervisor and make a plan for completion acceptance (竣工验收).
  • The employer will report to the local authority seven working days before the day of completion acceptance. 
  • The employer will organise the completion acceptance. 
  • Should the completed works pass the various tests and checks for completion acceptance, all the attendees will sign a report of acceptance. At this point, the employer will confirm acceptance of the completed works. 
  • The contractor will hand over all project documents, records and drawings to the employer.
  • The employer then files the acceptance report, project documents, records and drawings with the local construction bureau. 

These processes influence each other as follows.

The completed works can be delivered for use upon passing completion acceptance; completed works that have not undergone completion acceptance or do not pass completion acceptance shall not be delivered for use.

If the construction project has not been accepted for completion and is delivered for use by the employer, the date of takeover of the completed works shall be the date of completion acceptance.

Defects Liability Period

There are several Chinese words for “defects liability period”, such as 质量保证期, 缺陷责任期, 质量保修期, which often causes confusion in practice, thus “defects liability period” should be clarified in the relevant terms of the construction contract. 

Defects Liability Period Related to Retention Money/Guarantee

Parties are free to agree on a certain time period for the contractor to remedy defects on notice upon completion of the works. There is no mandatory requirement regarding the length of such period by law but an administrative rule suggests that such period is generally one year but shall be no longer than two years. In practice, the defects liability period is often agreed as two years from the date of completion acceptance. Upon expiration of such defects liability period, the employer must return the retention money or release the retention guarantee. 

Defects Liability Period Related to Quality of the Project

The contractor has statutory quality warranty obligations within prescribed minimum periods for different parts of the project by law. These cannot be contracted out but can be extended in the contract. On expiration of such quality warranty periods, the contractor is released from contractual and legal obligations to the employer for the quality of the project, but the contractor may still be liable for personal injury or property loss of a third party caused by the project for reasons attributable to the contractor within a reasonable period of its use. Minimum statutory quality warranty periods for different projects are as follows:

  • for an infrastructure project, and foundations and main parts of a house building, the quality warranty period is the number of years of reasonable use as prescribed in design documents;
  • for waterproofing works on roofs, toilets, and rooms and outside walls with anti-leakage requirements that should be waterproofed, the quality warranty period is five years;
  • for heat supply and air-conditioning systems, the quality warranty period is two heating periods and two air-conditioning periods; and
  • for projects involving electric wires, gas, water supply and drainage pipes, equipment installation and decoration, the quality warranty period is two years. 

Remedies Available to the Employer

In the event of any defects in the work of the contractor, the employer may request the contractor to remedy such defects at its own cost within a reasonable time period, or it may entrust a third party with the remedial works at the contractor’s cost. The contractor shall also be liable for compensating for the losses. If the contractor fails or refuses to remedy defects within the defects liability period or quality warranty period, and further, if such breach is so material that the purpose of the contract cannot be realised, the employer may terminate the contract.

Quota Evaluation and Bill of Quantity

Two pricing methods are generally used to establish the contract price in construction contracts: quota evaluation and bill of quantity.

By using quota evaluation, a party, usually the contractor, applies project quotas and formulations or rules as published by local governments to calculate project costs on labour, materials, equipment, etc, to establish the contract price. Apparently, this method reflects China’s planned economy in the construction sector. 

With China’s transition from a planned economy to a market economy, the bill of quantity has gradually become more and more popular, replacing quota evaluation in establishing the contract price. The bill of quantity refers to a pricing model where the employer provides a bill of quantity and the contractor proposes prices on different items at its own volition, considering its own costs. 

In addition, several other price models are used in contracts; eg, lump-sum price, fixed unit price, costs plus fees, adjusted costs, etc. 

Milestone Payments

Payment by milestones is widely used in construction contracts. The payment schedule providing specific milestones is often a major issue in the parties’ negotiations and is itself a part of the contract documents. The common arrangement of milestones would include an advance payment, progress payment at different construction stages and return of retention money.

It is common to use indexation of prices to divide the risk of price fluctuations. The contracts between the project owner and the general contractor will often include a formula of price adjustment, stipulating that if the fluctuation exceeds a certain amount, the price will be adjusted accordingly. The index usually used by parties is often the price published by a government market research company, showing the fair market price of a certain material or work. Such market research is regularly conducted by the bureau of construction quality supervision to provide a reference for contractors.

Late or Non-payment

The employer’s primary obligation in the construction contract is to pay on time as agreed. As such, late payment or non-payment is the employer’s breach. Almost all construction contracts include relevant terms dealing with late payment or non-payment, such as liquidated damages (eg, a daily rate for late payment), and the contractor’s right to suspend or terminate. 

Depending on the circumstances, the contractor may claim payable amounts together with liquidated damages for late payment. If the contract is silent on liquidated damages, the contractor can also claim loss of interest, calculated based on contemporaneous and homogeneous loan interest rates or the contemporaneous loan prime rate under Article 26 of Interpretation of the Supreme People’s Court on Issues Concerning the Application of the Law in the Trial of Construction Project Contract Dispute Cases (I). If the employer’s late payment or non-payment constitutes material breach, the contractor may suspend works or even terminate the contract on condition that the contractor reasonably urges the employer to rectify such breach in advance. 

Advance Payments, Delayed Payments and/or Interim Payments

It is common for a traditional construction contract to include an advance payment and interim payment in the employer’s payment schedule. However, if an advance payment refers to the contractor’s advance payment (ie, the contractor contracts works with its own funds), this would be deemed as the employer’s outstanding payment to the contractor. Furthermore, if the contract is silent on the matter of interest on the contractor’s advance payment, the court may not support the contractor’s claim of interest loss on such advance payment. 

Delayed payment is often regarded in the same light as late payment, as illustrated above in a traditional construction contract. Yet in some creative models of project contracting, delayed payment may be used as a financing tool.

In government investment projects, the parties are not allowed to use the contractor’s advance payment in construction practice or use delayed payment as a project financing tool.

Invoicing is highly regulated in various areas in China and the construction sector is no exception. Invoices are issued on standard forms and printed out through a special tax-control printing machine that connects to the supervision system of local tax bureaus. By this means, the tax authority supervises the authenticity of the invoice and inspects the tax payment status of each individual invoice. 

The service provider or the seller are often the party to issue invoices. In the construction sector, the issuing party is often the contractor. The issuing party is not allowed to delegate the issuing of invoices on its behalf to a third party. 

It is common in construction contracts that parties include invoices as one of the payment conditions; ie, the contractor must issue an invoice against amounts payable and the employer must pay within a certain number of days upon receipt of such invoice, as agreed.

The planning of the construction is done by the contractor and is incorporated into the construction contracts as part of the contractual documents. If the construction contract is concluded via a bidding and tendering process, the planning would be proposed and included in the contractor’s bid documents in response to the employer’s substantive requirements. If the construction contract is concluded via direct negotiation, the planning done and proposed by the contractor would be a key issue for the parties to negotiate. 

The employer may review the planning proposed by the contractor and check whether it is feasible and in line with the overall project plan. Upon the employer’s approval, the parties may include the planning as part of the contract documents. If the planning does not meet the contract requirements or is inconsistent with the actual progress of the project, the employer may directly notify the contractor to revise the planning; if the contractor needs to make changes to the planning, the contractor shall report to the employer for approval in advance.

To safeguard the planning, the contractor will also make the construction organisation and implementation plan, record the actual progress and make the monthly progress report, then put forward the situations that may cause delay and the solutions.

Milestones

It is very common to have milestones in the planning, which often correspond to progress payments; ie, milestone payments. Some construction contracts may include liquidated damages should the contractor fail to meet milestones as set in the planning. For industrial projects, an interim certificate may be used to mark completion of a major milestone.

If a delay occurs, the first thing the parties need to do is identify the cause of the delay. 

  • If it is on the employer’s part, the contractor may claim extension of time and reasonable costs as provided in the contract.
  • If it is on the contractor’s part, the contractor will not have the right to claim extension of time or any costs. On the contrary, the contractor may need to pay liquidated damages, compensation for losses on delay to the employer and take further measures to accelerate the works to meet the completion date at its own cost.
  • If the delay is caused by a force majeure, the contractor shall notify the employer immediately of the occurrence of the force majeure, with proof, and take measures to mitigate the effects. The completion time will be extended accordingly.

Many construction contracts include liquidated damages for delay. In the event of delay on the part of the contractor, the employer may be entitled to claim such liquidated damages, compensation for losses and may request the contractor to accelerate the works at its own costs. If the critical path of the progress is seriously delayed on the contractor’s part, the employer may exercise its right to terminate the contract.

Likewise, in the event of delay on the part of the employer, the contractor may claim for extension of time and actual losses related to time. A serious suspension caused by the employer may trigger the contractor’s exercise of its right to terminate.

Typically, the contractor will submit a notice of delay to the supervisor or engineer, as entrusted by the employer, within a certain period as agreed in the contract. The contractor will usually send this notice together with evidence to prove the occurrence and cause of the delay and its impact on the works. The contractor may also send a claim letter on extension of time and costs shortly after or simultaneously with the notice on delay. The notice sent by the contractor, together with the reply of the supervisor or engineer, establish evidence of the extension of time. Additionally, the report or daily record of the supervisor is common evidence of the extension of time.

The term “force majeure” is defined in Article 180 of the Civil Code. It is “an objective event which is unforeseeable, unavoidable and insurmountable by the parties”. In a traditional construction contract, parties may repeat the legal definition of “force majeure” and provide some specific circumstances as instances – eg, earthquake, tsunami, plague, rebellion, war, insurrection, riot, etc. 

The parties are generally free to agree in the contract a broader scope of application and relief for similar events, which will generally be given effect. However, in that case, contractual provisions will apply, as supplemented by the force majeure provisions under the law, to the extent relevant to those events that meet the legal definition of “force majeure”. In contrast, in China’s current jurisdiction, courts and arbitration institutions tend to believe that “force majeure” is a natural phenomenon that cannot be avoided by human forces, meaning it is a legal exemption and cannot be exempted due to the exceptions of the parties. Those events being limited or excluded that do not meet the requirement of “force majeure” under the law will be afforded relief and/or entitlement only as agreed between the parties to share the loss of the consequences after the occurrence of the force majeure event.

Principle of “Change of Circumstances”

Risks such as unforeseen ground conditions, a change in the law, fluctuations in the price of materials and labour, etc, frequently occur in construction practice, which may trigger application of the principle of “change of circumstances” at law. 

The principle of “change of circumstances” was first introduced in the Interpretation on Certain Issues Concerning the Application of the Contract Law (II) and is now codified in the Civil Code. 

Article 533 of the Civil Code provides that “where the basic conditions of a contract undergo a material change unforeseeable by the parties at the time of contracting which is not a commercial risk after the formation of the contract, rendering the continuation of the performance of the contract unconscionable for either party, the adversely affected party may renegotiate with the other party; and if the renegotiation fails within a reasonable time limit, the party may request the people’s court or an arbitration institution to modify or rescind the contract”.

As a result, in the event of unforeseen circumstances that may substantially change basic conditions at the stage of contract conclusion, one party may propose to renegotiate the contract terms with the counterparty. Should the renegotiation fail, either party may apply for the court or the arbitral tribunal to step in to revise the relevant terms or to terminate the contract on the basis of the principle of fairness.

There is not any clear definition in China’s legislation or sample contract regarding disruption. There is no systematic study or inspection that can establish or measure the market disturbance which leads to disruption or other legal effect, although from the practitioner’s view the disruption exists, to some extent in some sub-industry.

Therefore, disruption is not yet acknowledged as a legal element or situation which causes extension or compensation. However, other methods of dealing with the adverse effect can be seen, such as reference to the force majeure or “change of circumstances” principle. A recent example in 2017–2018 occurred when the concrete industry was substantially affected by the environmental protection campaign of the central government, and many contracts referred to the “change of circumstances” principle to find a fair solution rather than introduce the concept of disruption.

General Clauses

Article 506 of the Civil Code provides: “the following exclusion clauses in a contract shall be void: (1) those that cause personal injury to the other party; (2) those that cause property damages to the other party as a result of wilful misconduct or gross negligence”.

It is therefore not possible to exclude liability for personal injury or death to the contractual counterparty and liability for property damages to the contractual counterparty as a result of wilful misconduct or gross negligence. 

Standard Clauses

Under Articles 496 and 497 of the Civil Code, clauses that are “standard” – ie, clauses that one party uses repeatedly in its contracts and which, in the case of the particular contract in question, are included and not negotiated with the other party, would be deemed void where they attempt to exempt the liability of the party who includes them; or where they unreasonably decrease the liabilities of the party that includes them, increase the liabilities of the other party or limit the rights of the other party. 

Besides the legal position for a general contract above, parties to contracts in a specific industry may not contract out of mandatory liabilities prescribed at law. For instance, the contractor must assume statutory quality warranty obligations within the prescribed minimum periods for different parts of a project, which cannot be contracted out in the construction contract.

The concepts of “wilful misconduct” and “gross negligence” are not expressly defined at law. 

However, in practice, the courts have discretion to apply these concepts to cases by considering specific circumstances and the failing party’s expertise. Generally, “wilful misconduct” illustrates a person’s intention where they can reasonably foresee another’s losses owing to their action/breach but they still wish or allow it to happen. 

“Gross negligence” refers to a person’s intention where they are in serious breach of the duty of care and should have foreseen, but fail to foresee, or have foreseen but measures haven’t been taken due to credulity, the losses caused to another by their action/breach. In a Supreme People’s Court (SPC) judgment ((2016) Zui Gao Fa Min Shen 381), the SPC found that DHL Shangdong Company (DHL) failed to deliver a package in accordance with the agreed post-operation procedures and held that DHL’s breach did not reach the threshold of “wilful misconduct” but should be ascertained as “gross negligence”.

Limits/Caps on Liability

Articles 496, 497 and 506 of the Civil Code and their restrictions on exclusions of certain types of liability only apply to absolute exclusions. Generally, limitations of liability are permissible; however, all such limitations are subject to the principles of fairness and good faith, which are also codified in Articles 6 and 7 of the Civil Code. The courts could potentially use these principles to hold that limitations of liability are unfair or in breach of the principle of good faith, and they have the power to step in and adjust such limits. This is well-reflected in the application of liquidated damages. 

Liquidated Damages

Parties are allowed to limit liabilities for their breach by including terms of liquidated damages. However, the court may adjust the liquidated damages on a party’s application if:

  • the liquidated damages are significantly higher than the actual losses suffered by the complying party – ie, the liquidated damages are more than 30% higher than the actual losses suffered; or
  • the liquidated damages are lower than the actual losses suffered. 

In fact, besides the gap in the amount between liquidated damages and actual losses, the court will also look into other factors, such as the parties’ performance under the contract concerned, the extent of culpability of the relevant party in causing the losses suffered, etc.

As model construction contracts do not adopt indemnity terms in the FIDIC forms, parties using model forms rarely include indemnity terms in the contract. However, if parties elect to use the FIDIC forms for projects involving foreign elements, indemnity provisions relating to personal injury and damage to property (other than the works) during the course of the project will be included in the FIDIC forms. 

Some provisions equivalent to indemnities exist in the Model Contract for General Contracting Projects – ie, provisions that one party shall be responsible to the other party for contractual breach resulting from a third party’s fault, and that one party shall be responsible for any claims on intellectual rights by a third party.

There are no restrictions on the nature and types of guarantees. Bonds, usually on-demand bonds (creating a primary obligation on the bondsman to pay), issued by banks or financial institutions, are commonly used in practice. Occasionally, parent companies may provide guarantees for the performance of subsidiary companies. 

Various guarantees are involved in the process of project construction, such as advance payment guarantee, performance guarantee, retention money guarantee, payment guarantee, etc. 

  • An advance payment guarantee is provided by the contractor in an amount equal to the advance payment.
  • A performance guarantee is provided by the contractor to secure its due performance under the construction contract. A performance guarantee is not mandatory. The employer and the contractor shall agree on the method, amount and submission time in the contract. The performance guarantee can be in the form of bank guarantee or guaranteed by a bonding company.
  • A retention money guarantee is an alternative to the employer’s retention money. The Ministry of Finance and MOHURD have jointly issued an administrative measure on managing the practice of retention money, which provides that a retention money guarantee shall not exceed 3% of the final settlement of the project’s total price, though the provisions of this administrative measure are not mandatory.
  • A payment guarantee is provided by the employer to secure its payment obligation to the contractor, but is rarely used in practice.

For construction projects, the most common types of insurance are construction/erection all-risk insurance and third-party liability insurance, which can be taken out by the contractor or the employer, or both, depending on the parties’ agreement. Construction/erection all-risk insurance provides coverage for property damage; and third-party liability insurance provides coverage for injury, illness or loss to property of third parties or damage claims, and is not mandatory. 

Both the employer and the contractor have a mandatory legal obligation, however, to take out work injury insurance for their respective employees. The contractor is further mandatorily required to procure accident liability insurance for employees who engage in dangerous operations.

Taking the Model Contract for General Contracting Projects as an example, one party’s insolvency may trigger circumstances where the other party has the right to terminate the contract by immediate notice without giving advance notice of its intention to terminate.

Risk Allocation Between Parties

Many terms in a construction contract are designed to allocate responsibilities between the parties in respect of certain risks. 

Under Measures for the Administration of General Contracting of House Building and Municipal Infrastructure Projects, major risks allocated to the employer include:

  • fluctuation exceeds the range agreed by the parties in the price of materials, equipment and labour compared with the price at base date;
  • fluctuation in the price due to a change in the law;
  • unforeseen ground conditions;
  • delays and additional costs on the part of the employer; and
  • delays and additional costs for force majeure. 

This does not provide a mandatory mechanism for allocating risks, but a reasonable mechanism for parties’ reference. Parties may allocate risks considering their specific projects and circumstances but are generally expected to allocate risk in a reasonable manner.

Most shared risks are not actually "shared" but are allocated between the parties. This means that the parties do not proportionally distribute or price a particular risk; instead, the entire burden of the risk is placed on one party. To achieve balance, the parties strive for a comparatively equal allocation of risks.

Risk Sharing Between Parties

Risk sharing depends on the mechanism of risk allocation between the parties. Taking the Model Contract for General Contracting Projects as an example, both parties may share certain risks as follows:

  • abnormal weather conditions – the contractor shall take reasonable measures to proceed with the works and the employer shall grant an extension of time accordingly; and
  • force majeure:
    1. the employer bears the cost of damages to permanent works, and the cost of personal injuries and property loss of third parties resulting from such damages;
    2. the contractor bears the cost of damages to the contractor’s equipment;
    3. each party bears its own personal injury and other property damages;
    4. additional costs for the suspension of the works shall be reasonably allocated between both parties; and
    5. acceleration costs per the employer’s instruction, and the contractor’s additional costs for caring for and cleaning the site, and remedying the project, shall all be for the employer’s account.

The Employer’s Personnel

In general, the employer’s personnel include the employer’s representative and other personnel sent to the site by the employer. The employer’s representative may act on behalf of the employer within the scope of authorisation. Details and the scope of authorisation of the employer’s representative shall be expressly included in the contract. Should the employer replace its appointed representative, the employer shall notify the contractor in writing within a certain number of days before such change. 

The Contractor’s Personnel

The contractor’s personnel include the project manager and all other personnel sent to the site by the contractor. The contractor is required to submit a report about its project manager, technical manager, construction manager and all personnel on site to the supervisor within a certain number of days after receiving the notice of commencement. In addition, the contractor must provide an employment contract, plus proof of payment of social insurance for its major managing staff on project. 

In particular, the contractor’s project manager must have a corresponding civil engineering qualification. The project manager in a general contracting project is not allowed to act for two projects in the role of project manager or construction manager at the same time. Furthermore, the project manager shall assume lifelong liability for the quality of the project.

The Supervisor

The employer may entrust a supervisor (very often a supervising institution or company other than a natural person) to check and examine the works, review project documents and issue notices on the employer’s behalf within the scope of authorisation. The supervisor may send a supervising director and a supervising engineer to site to act accordingly.

It is very common for the contractor to subcontract part of its works to subcontractors. There are two types of subcontractors: the speciality subcontractor and the labour subcontractor. The contractor must comply with certain legal requirements on subcontracting so that the subcontracting is legal and will not be deemed as void under the law:

  • unless the construction contract provides otherwise, the contractor must obtain the employer’s consent before subcontracting;
  • the contractor may not subcontract the entirety of its works to a subcontractor;
  • the contractor may not subcontract part of its works to an unqualified subcontractor or an individual;
  • the contractor may not subcontract its works for the main structure, save for steel structure work;
  • a speciality subcontractor may not further subcontract speciality works (subcontracted by the contractor) to another subcontractor, save for the labour works of the subcontracted speciality works; and
  • a subcontractor may not further subcontract labour works (subcontracted by the contractor) to another subcontractor.

In general, the intellectual property right belongs to the author of the work. Such work in a typical construction process may be in the form of drawings, working records, technical documents, technique development, communications in texts, etc. The construction work itself does not constitute a work within the concept of intellectual property. 

Parties to the construction contract may include relevant provisions dealing with intellectual property rights. These provisions, in general, would be:

  • for drawings and technical documents provided by the employer, all the intellectual property rights belong to the employer and the contractor may only copy and use these documents for the purpose of carrying out the works;
  • for documents the contractor makes for the purpose of carrying out the works, the contractor only has the right of authorship and all other intellectual rights belong to the employer, and likewise the contractor may not use these documents for purposes unrelated to the construction works; and
  • each party shall be responsible for its own wrongful use of a third party’s intellectual property rights.

Construction contracts generally include various remedies that each party can exercise in the event of failure by the other party to comply with an obligation. Financial remedies, as well as some courses of action, are available to the parties; to name a few:

  • damages such as liquidated delay damages for the employer and liquidated payment delay damages for the contractor;
  • compensation of any expenses and losses caused to the other party due to violation of law or the contract;
  • suspension, as in the employer may prevent progress of unsafe work;
  • termination by either party under material breach by the other party;
  • the employer’s withholding of payment; and
  • the employer’s notice to remedy defects.

Financial remedies in the form of liquidated damages are usually available to the parties. Liquidated damages are designed to reflect the complying party’s loss caused by the failing party’s breach, which could have been reasonably foreseen by the failing party at the time of concluding the contract. Should such liquidated damages be significantly higher or lower than the complying party’s actual loss, the court may step in to adjust such liquidated damages, applying principles of fairness. See 6.3 Limitation of Liability for more details on this point. In model contracts, except for losses caused by fraud, crime, intent, gross negligence, personal injury and other misconduct, both parties’ agreement on the restriction of remedies also includes that the contractor’s compensation to the employer shall not exceed the agreed maximum amount or the contract price.

It is rare to see a sole remedy clause in a construction contract. Should a sole remedy clause be included, it is highly likely to be a limit on liability with a cap figure. Such clause is generally valid and enforceable subject to legal requirements on exclusion and limitation of liability clauses, which are discussed in 6. Liability.

See 6.1 Exclusion of Liability.

Retention Rights

If “retention rights” refers to the contractor’s right to retain works in the event of the employer’s failure to pay, the contractor does not have such a right under the law, but the contractor may claim priority right to compensation. 

If “retention rights” refers to the employer’s right to withhold a certain amount of money as retention money against the contractor’s obligation to remedy defects within the defects notification period, this is a very common right for the employer. As the employer has greater negotiation power than the contractor, it is almost impossible in practice to contractually exclude the employer’s retention rights.

Suspension Rights

In terms of suspension rights, suspension is a common remedy, or at least a protective threat, invoked by the contractor in the event of late or non-payment by the employer or other breach of contract that makes the contractor unable to continue to perform the contract. In a construction contract where suspension rights are excluded, this often means that the contractor has no right to suspend works but has a right to claim compensation as an alternative. There have been quite a few successful claims by contractors relying on such clause, which indicates that this contractual arrangement is held valid by the courts and tribunals.

Termination of a contract is usually triggered by a serious breach of contract, and sometimes only those breaches which lead to frustration of contract may entitle a party to terminate. For example, if the critical path of the progress is seriously delayed on the contractor’s part, the employer may exercise its right to terminate the contract.

It is stipulated by Article 565 of the Civil Code that a notice shall be issued to terminate the contract. However, the party may seek such termination right directly at a court by filing a case.

According to the Civil Code, the result of termination of a contract includes:

  • immediately stopping and cancelling the performance of the contract; or
  • settling, paying or returning the performed part of the contract.

The termination does not affect the responsibility arising from the previous performance or violation of the contract.

In a more specific situation, termination of a construction contract often leads to the settlement of the already completed part and forces the parties to discern the proportional responsibility of such termination or previous violation of the contract.

In terms of or in a construction-related case, the court of the place where the project is located has exclusive jurisdiction to adjudicate the case. The level of the first instance court is determined based on the threshold of claims and the complexity of the case.

Court System

Generally, the court system is divided into four levels:

  • basic courts at district level;
  • intermediate courts at city level or equivalent; 
  • high courts at provincial or direct-controlled municipality level; and
  • the SPC.

Thresholds for Allocating Jurisdiction

There are different thresholds for allocating jurisdiction between the four levels of court. For instance, in a domestic case where both parties reside in Beijing, if claims are over CNY100 million, the first instance of the case will be heard before the intermediate courts in Beijing. As most project claims are high in value, the first instance case will usually be adjudicated before an intermediate court.

Arbitration

In practice, as construction cases involve technical elements, the parties are commonly willing to enter into a written arbitration agreement to resolve disputes before an arbitration institution, such as the Beijing Arbitration Committee and the China International Economic and Trade Arbitration Commission.

Mediation

Mediation also plays an important role in resolving construction disputes, sometimes as an independent process and sometimes as part of the arbitration/litigation process. For the widely known “arbitration-mediation” mechanism, the arbitrator may play two roles in the process.

Dispute Review Boards

Several arbitration institutions provide a construction project dispute review service and have a panel of experts with legal and technical expertise. This review procedure borrows wisdom from the Dispute Adjudication Board (DAB) and the Dispute Review Board (DRB) in the FIDIC forms. Whether the experts’ review decision has a binding effect is subject to the parties’ agreement in the construction contract. Should the construction contract be silent on this, the review decision shall be binding on the parties according to the review procedure rules.

Merits & Tree Law Offices

Unit 1801
Raffles City Changning Office Tower 1
No 1133 Changning Road
Changning District
Shanghai 200051
People’s Republic of China

+86 21 5253 3500

+86 21 5253 3599

zheyuan.jin@meritsandtree.com www.meritsandtree.com
Author Business Card

Trends and Developments


Authors



Merits & Tree Law Offices has a real estate and infrastructure team led by four key partners and more than ten supporting partners, in addition to over 20 lawyers. The team provides contentious and non-contentious legal services in the sector, including construction and engineering of buildings and infrastructure, real estate development and sales, land acquisition, project mergers and acquisitions, urban renewal, property management and operation, project investment and financing, project tax planning and asset-backed securitisation. The lawyers advise local giant real estate developers as well as various construction companies in China, such as Vanke, Longfor and Greentown. The team provides strategic and professional solutions to clients on contract negotiation, bidding and tendering, construction claims and disputes, and on-demand guarantee-related matters.

Overview

When government policy guidance, environmental protection and green building, and technological innovation jointly affect the Chinese construction business, the market presents multi-level development trends. First, the Chinese government may promote a more stable and balanced development of the real estate market through increased support for infrastructure construction, promoting new urbanisation development, and controlling fluctuations of the property price. These policies will directly affect the demand and development of the construction market. Second, as people’s attention to environmental protection and sustainable development grows, green buildings will become the future trend. The government may enact related policies to encourage and support the development of green buildings, thereby bringing new growth opportunities to the construction industry. Third, technological innovation will also become an important driving force for the development of the construction industry. For example, the application of BIM technology and smart building technology will become important directions for the future construction market, bringing more efficient and smarter solutions to the construction industry.

Reform in the Construction Engineering Inspection Industry

On 29 December 2022, the Ministry of Housing and Urban-Rural Development (MOHURD) of the People’s Republic of China issued Order No 57, announcing the reformed “Measures for the Management of Construction Engineering Quality Inspection”, which came into effect on 1 March 2023.

Construction engineering quality inspection, referring to those inspections on the material quality or the project quality, is often conducted by a certified institute or laboratory entrusted by the project owner or the government, and the inspection reports are required to be attached to the project files. It is a crucial aspect of controlling project quality, serving as a key means of government engineering quality supervision and an important basis for evaluating project quality. In 2005, the former Ministry of Construction issued the “Measures for the Management of Construction Engineering Quality Inspection” (Ministry of Construction Order No 141), which regulated the qualification licensing, business operations, and supervision of inspection activities of construction engineering quality inspection institutions, playing an important role in standardising inspection behaviours, maintaining the order of the inspection market, and ensuring the safety of project quality. However, with the continuous development of the construction market and inspection industry, and the increasing demands of the people for building quality, the content of Order No 141 can no longer fully meet the needs of industry development and regulation.

The amended regulation has expanded the types of entities in the testing market and strictly standardised the testing behaviours. More specifically as follows.

  • Enterprises, institutions, and partnerships with or without independent legal personality are allowed to apply for the qualification of testing institutions, enriching the types of market entities.
  • The process of testing, including commissioning, sampling, labelling, submission for testing, and sample acceptance, has been standardised. Testing institutions are required to establish and use an information management system to ensure the authenticity and accuracy of testing data.
  • Testing institutions are required to continuously improve their technical capabilities, strengthen personnel training, and regularly calibrate instruments and equipment to meet the requirements of engineering quality testing.
  • The responsibility system for construction project quality testing has been improved, clarifying the responsibilities and obligations of relevant units and individuals, and specifying related prohibited behaviours.
  • Specifications have been established for the reporting of testing results and data retention mechanisms.

Reform in the Qualification System of Contractors

On 6 March 2023, the MOHURD issued a notice titled “Notice on Further Strengthening the Management of Qualification Approval for Construction Enterprises”, which deploys measures to enhance the efficiency of qualification approval, unify national qualification approval authority, strengthen the assessment of enterprise restructuring, improve performance evaluation methods, and intensify dynamic qualification checks for construction enterprises. This notice is following the Ministry’s 2021 pilot projects in 15 regions to delegate the authority for qualification approval of construction enterprises, transferring part of the qualification approval to the provincial housing and urban-rural development authorities in the pilot regions.

The notice outlines the following key measures.

  • Enhancing the efficiency of qualification approval – authorities should improve the qualification approval mechanism and ensure timely decision-making within two months for qualifications under the Ministry’s responsibility.
  • Unifying national qualification approval authority – the Ministry will uniformly handle qualification approvals. Pending applications in pilot regions should be processed within the specified time. Qualifications issued during the pilot period will remain valid until expiration, and matters such as suspension of business, lowering qualification levels, revoking, or cancelling qualification certificates for enterprises will be implemented by the housing and urban-rural development authorities in the pilot regions.
  • Strengthening assessment of enterprise restructuring – assessment of original and successor enterprises for qualification approval due to restructuring must comply with qualification standards. Assessment for qualification approval due to merger should evaluate enterprise assets, personnel, and relevant legal relationships.
  • Improving performance evaluation methods – enterprises applying for qualifications under the Ministry’s jurisdiction must have projects graded A on the National Construction Market Supervision Public Service Platform.
  • Intensifying dynamic qualification checks – authorities should improve information tools to conduct dynamic checks on registered personnel and promptly disclose verification information. Enterprises failing to meet qualification standards will be marked as abnormal on the National Construction Market Platform, with a deadline for rectification.

These measures aim to streamline and standardise the qualification approval process, ensuring the credibility and efficiency of construction enterprises in the industry.

The Digital Management of the Entire Lifecycle of Construction Projects

On 24 October 2023, the MOHURD issued a notice, deciding to launch pilot reforms for the digital management of the entire lifecycle of construction projects.

The decision to implement digital management reform pilot projects may have been based on an understanding and analysis of the current state of management in the construction industry, including possible issues such as information asymmetry, low management efficiency, and inadequate supervision.

The notice requires the local government and contractors to do the following.

  • In every department or region, use a standardised electronic platform with uniform application forms and materials for engineering construction project approval matters and build a standard sample database. Strengthen the application of electronic documents, electronic signatures, etc, focus on promoting paperless reporting, and achieve comprehensive electronic certification of approval results.
  • Establish coding and mapping mechanisms for individual buildings, by establishing work procedures and operational guidelines for the division, coding, and mapping of individual buildings, according to the “Unified Coding and Basic Attribute Data Standards for Building Construction”. In addition, the local government should assign a unique code to each building entity for the entire lifecycle, and associate it with the project code.
  • Establish a mechanism for collecting and sharing data throughout the lifecycle. The local government should promote the interconnection and collaborative application of related systems such as project approval, construction market supervision, real-name management of construction workers, quality and safety supervision, and housing safety management.

The MOHURD intends to make information at various stages of construction projects more accurate, timely, and shared, thus enhancing the efficiency and transparency of project management, as well as to reduce errors and delays in management processes and to promote the intelligent and informed transformation of the construction industry.

A National Survey of Natural Disaster Risks

The comprehensive national survey on natural disaster risks, initiated since 2020, was successfully completed by the end of 2023, with the participation of various departments, mainly including the Ministry of Housing and Urban-Rural Development, the Ministry of Transport, and the State Forestry and Grassland Administration.

The completion of this nationwide survey marks an important step forward for China in the field of natural disaster prevention and mitigation. By comprehensively understanding the situation of housing construction and municipal facilities, the government and relevant departments can more effectively formulate disaster response and prevention measures, thereby enhancing society’s resilience against disasters.

In addition, a large amount of data has been generated, especially data reflecting the spatial location and physical attributes of building structures, providing important references for urban and rural planning, land use, architectural design, and other decision-making aspects. The digitised management of this data also lays the foundation for future smart city construction and urban planning.

The issuance of a “digital identity card” for building structures will also help strengthen supervision over building safety and quality, thereby improving the safety and sustainability of buildings. Overall, this survey is of great significance for enhancing China’s disaster prevention and response capabilities and promoting urban development and construction.

At the same time, the survey achieved full coverage in the highway and waterway industries, forming a set of natural disaster risk zoning maps for the transportation industry and establishing a database for natural disasters in the transportation industry, comprehensively mastering data information on highway and waterway facilities attributes as well as natural disaster risk information.

Creation of “Super Priority Right” by the Supreme Court

Construction priority refers to the priority right enjoyed by the contractors, under specific circumstances, over the land or property involved in their ongoing construction project. This priority right even takes precedence over debts secured by mortgages. However, in April 2023, the Supreme People’s Court issued an official reply regarding consumer rights protection issues related to disputes arising from real estate developers’ failure to deliver purchased properties on time, titled “Reply on Issues Concerning Consumer Rights Protection in the Purchase of Commercial Housing”. The reply provides clear guidelines.

  • If a consumer purchases a property for residential purposes and has already paid the full purchase price, asserting their right to demand property delivery takes precedence over the construction priority right, mortgage rights, and other debts, the court should support this claim.
  • In cases where the property cannot be delivered and there is no possibility of actual delivery, if consumers claim the right to refund, the purchase price takes precedence over the construction payment priority right, mortgage rights, and other debts, and the court should support this claim.

These rights enjoyed by the consumer are now often referred to as “super priority rights” and will enhance the legal protection level for consumers when purchasing properties, boost buyer confidence, and promote the healthy development of the real estate market, especially given the context of “protecting livelihoods and ensuring property delivery” policy.

Supreme Court’s Further Clarification of the “Construction Priority Right”

In the third issue of 2023, the Supreme Court Gazette published a construction contract dispute case between Sichuan Zhongmei and a real estate company in Chengdu, confirming that pit support, dewatering, and earthwork engineering still fall within the scope of priority right for construction projects.

The cases published in the Gazette by the Supreme People’s Court, and provincial-level people’s courts are “for reference only” and do not have mandatory legal force, but they have a strong guiding role in the trial work of various levels of people’s courts.

To summarise the Supreme Court’s opinion: The building materials and labour invested by the pit engineering contractor in the construction project have been materialised into the building and are inseparable from the building itself. Therefore, the contractor of the pit construction contract should enjoy priority rights to be compensated for this part.

The ruling of this case is of great significance for clarifying the scope of priority for construction projects. Pit support, dewatering, and earthwork engineering are usually considered important links in construction projects, directly related to the safety and stability of buildings. Therefore, including these projects in the scope of priority for construction projects helps ensure the smooth progress of construction projects, guarantees the quality of engineering, and provides a clearer basis for construction parties to enjoy priority rights to be compensated during the construction process.

The Debate to Include Rural Housing into the Jurisdiction of Construction Law

On 29 April 2022, the collapse of an old rural building occurred suddenly in Changsha, Hunan Province, causing a casualty of 54 souls. In May 2023, the State Council’s executive meeting reviewed and approved the investigation report on the collapse, causing a nation-wide debate.

The collapse incident in Hunan may be seen as a triggering event that has drawn attention to and scrutiny of rural self-built houses. Against this backdrop, the MOHURD is considering incorporating rural self-built houses into the scope of the Construction Laws, which signifies that the government will strengthen the regulation and management of rural self-built houses.

There are a series of problems with rural self-built houses, including substandard construction quality, multiple safety hazards, and lack of supervision. However, rural self-built houses are not directly regulated by Construction Laws. Traditionally, rural self-built houses are often designed and constructed by farmers themselves, with less government oversight.

Therefore, incorporating rural self-built houses into the scope of building law adjustments will help regulate rural construction activities, improve the quality and safety level of rural buildings, and strengthen the supervision and management of rural self-built houses, thereby reducing the occurrence of similar accidents. This measure is of positive significance for ensuring the safety of farmers, promoting rural construction, and rural revitalisation.

The Establishment of Court-To-Court Mediation Co-ordination Mechanism

The joint establishment of the “court-to-court” online litigation and mediation co-ordination mechanism in the housing and construction field by the Supreme Court and the MOHURD is an important initiative. Specifically, the core of this mechanism is to integrate the resources of the Supreme Court and the MOHURD through an online platform, providing convenient litigation services and dispute resolution channels for parties involved, thus more effectively addressing civil disputes in the housing and construction sector.

This online litigation and mediation co-ordination mechanism typically includes the following aspects.

  • Online litigation services – parties can initiate litigation through the online platform and go through procedures such as case filing and evidence submission, facilitating a streamlined litigation process.
  • Dispute resolution channels – the online platform provides dispute mediation services, including online mediators assisting parties in mediation to resolve disputes.
  • Resource integration – the Supreme Court and the MOHURD integrate various resources, including legal experts and mediators, to provide comprehensive legal support and services to parties involved.

This “court-to-court” co-ordination mechanism is expected to enhance judicial efficiency, reduce litigation costs, and promote social stability and the rule of law. Through the application of online platforms, dispute resolution becomes more convenient and efficient, which is conducive to promoting legal protection and standardised development in the housing and construction field.

Merits & Tree Law Offices

Unit 1801
Raffles City Changning Office Tower 1
No 1133 Changning Road
Changning District
Shanghai 200051
People's Republic of China

+86 21 5253 3500

+86 21 5253 3599

Zheyuan.jin@meritsandtree.com www.meritsandtree.com
Author Business Card

Law and Practice

Authors



Merits & Tree Law Offices has a real estate and infrastructure team led by four key partners and more than ten supporting partners, in addition to over 20 lawyers. The team provides contentious and non-contentious legal services in the sector, including construction and engineering of buildings and infrastructure, real estate development and sales, land acquisition, project mergers and acquisitions, urban renewal, property management and operation, project investment and financing, project tax planning and asset-backed securitisation. The lawyers advise local giant real estate developers as well as various construction companies in China, such as Vanke, Longfor and Greentown. The team provides strategic and professional solutions to clients on contract negotiation, bidding and tendering, construction claims and disputes, and on-demand guarantee-related matters.

Trends and Developments

Authors



Merits & Tree Law Offices has a real estate and infrastructure team led by four key partners and more than ten supporting partners, in addition to over 20 lawyers. The team provides contentious and non-contentious legal services in the sector, including construction and engineering of buildings and infrastructure, real estate development and sales, land acquisition, project mergers and acquisitions, urban renewal, property management and operation, project investment and financing, project tax planning and asset-backed securitisation. The lawyers advise local giant real estate developers as well as various construction companies in China, such as Vanke, Longfor and Greentown. The team provides strategic and professional solutions to clients on contract negotiation, bidding and tendering, construction claims and disputes, and on-demand guarantee-related matters.

Compare law and practice by selecting locations and topic(s)

{{searchBoxHeader}}

Select Topic(s)

loading ...
{{topic.title}}

Please select at least one chapter and one topic to use the compare functionality.