In Mozambique, the legal regime applicable to construction is composed of scattered legislation (available at the National Press of Mozambique EP website), including the following, which are applicable to both public and private construction works:
The following are applicable to public works:
There is no standard type of construction contract in Mozambique. Mozambican civil and commercial legislation allows the parties to a private contract to agree on its terms and conditions, if these do not violate mandatory provisions of the law. The use of FIDIC (Fédération Internationale des Ingénieurs-Conseils), NEC (New Engineering Contract) or JBCC (Joint Building Contracts Committee) contractual models may occur in major projects, specifically those subject to multilateral funding.
Public construction contracts typically incorporate the relevant mandatory and supplementary legal provisions specified in the tender documents and adhere to the templates set out in Ministerial Decree No 93/2024. These templates are mandatory.
Any company or individual can act as an employer under a construction contract. In general, its main rights include:
On the other hand, the employer is typically responsible for:
The relationship between the employer and the contractor is the most important for the execution and completion of the works. However, it is often necessary to involve other entities, such as subcontractors, technical advisers and financiers, especially in major construction projects.
As a rule, subcontractors are required and authorised by the employer to assist the contractor in carrying out the work. Prior employer approval may be required for subcontracting.
Subcontractors are hired directly by the contractor. They usually have no direct relationship with the employer. Some construction contracts include subcontractors appointed by the employer (nominated subcontractors) to carry out specific works.
In project finance structures, financiers will typically enter into a financing agreement with the employer, but they usually require direct agreements between the employer, the financiers and the contractor. These aim to:
Contractors may be commercial companies or sole proprietorships, belonging to Mozambican or foreign citizens.
Construction activities are regulated. Entities acting as contractors must be duly authorised to perform construction work in Mozambique by means of a contractor’s licence or a temporary licence, the requirements for which are established by law.
National and foreign contractors have different rules for public works. A foreign contractor can obtain a permit for the permanent exercise of its activity in public works only if it is either a legally constituted company or a branch or subsidiary of a foreign company that has operated in Mozambique for at least ten years. However, it can operate on a temporary basis through a specific licence in situations such as international tendering, reciprocity agreements, subcontracting or under the Investment Law.
In private works, foreign contractors are not subject to the additional requirements applicable to public works, although a contractor’s licence remains mandatory.
The main rights of the contractor include:
Its main obligations typically are to:
Subcontractors tend to be smaller, specialised companies. The contractor–subcontractor and employer–contractor relationships are similar in terms of rights and obligations.
Thus, the subcontractor may have rights and responsibilities towards the contractor that mirror those the contractor has towards the employer, even though the employer ultimately benefits from the subcontractor’s work. Depending on the subcontractor’s scale and the work’s significance, a back-to-back contractual arrangement reflecting the main contract may be implemented. Regardless, the contractor is always solely responsible to the employer for the work carried out by its subcontractors.
The process is similar for public works, but legal restrictions apply. The contractor always requires the employer’s authorisation to subcontract and the subcontractor must fulfil the criteria specified in the contract formation phase for the contractor.
In Mozambique, construction projects are typically financed by a range of entities, depending on the size, scope and nature of the project.
The most common financiers include the following.
The foreign exchange regime in Mozambique is critical for construction projects, particularly those involving cross-border financing or international participants. Compliance with foreign exchange regulations is essential to ensure the smooth flow of funds, the ability to service foreign debt and the repatriation of returns. Early engagement with local banks and legal advisers is advisable to navigate regulatory requirements, obtain prior authorisations when required and structure transactions to minimise foreign exchange-related risks.
Financiers in Mozambique, as in many jurisdictions, are not typically parties to the construction contract itself. However, their rights and obligations are often established through separate financing agreements, direct agreements or security.
This framework, together with direct agreements, provides financiers with both contractual and proprietary rights, increasing the bankability of Mozambican projects for international lenders.
In Mozambique, construction consultancy firms or companies – whether national or foreign – typically serve as “designers” in construction projects, provided they are duly licensed.
The main obligations of the designer are typically as follows:
Their main rights include:
In construction projects, it is common for the project owner to engage specialised companies to develop architectural and engineering designs, which are then provided to the contractor for execution. For major or particularly intricate projects, the contractor may be responsible for preparing all or part of the design under an EPC or a design-and-build arrangement. In the context of public works, this design-and-build method is also legally authorised.
The scope of a construction contract depends on the nature of the works to be performed. It may include design and construction or it may be limited to construction only.
The contract typically specifies the works as all the work required to complete the project in accordance with the agreed specifications. This includes preliminary and ancillary work not explicitly included in the contract but necessary for the project’s completion. In a design-and-build contract, the scope is defined by the employer’s requirements, which detail the design specifications. Depending on the type of project, the specifications might be very detailed or more focused on the fit for purpose or performance standards. In a pure construction contract, the scope is defined by the approved execution design, among other things. In energy projects, contractors may undertake the obligation to operate the plants for a certain period.
For public construction contracts, the public employer may execute the construction contract based on a final design or on a design-and-build basis, in which case the requirements for the design to be submitted must be defined in the tender documents.
The Mozambican Civil Code generally regulates variations to private construction contracts, distinguishing between:
Although construction contracts contain specific variation clauses, the Civil Code sets some limits on variations.
The impact of each variation in price and time is usually defined by considering the agreed bill of quantities and unit price list (and the applicable time limits for each type of work). If the variation requires works not listed in these contract documents, the contractor is usually requested to provide market prices and time limits for the employer’s approval.
As for public works, the contractor must accept any additions or deletions to works, goods or services up to 25% of the initial contract value, provided that the same contractual conditions apply. Any variation exceeding these limits requires agreement between the parties and authorisation from the Minister of Finance. Additionally, the employer may demand the execution of additional works not included in the contract, but the contractor may refuse if the value exceeds 25% of the contract value or if it can prove that it does not have the means to perform the additional work.
The division of responsibilities for designing a private works project depends on the project’s nature and the intended contract model.
A design and build contract may be entered into, in which the contractor is responsible for the design and construction activities; or a construction contract, in which the contractor is responsible for the works necessary to construct the project in accordance with the design provided by the employer. Front End Engineering Design (FEED) may also be used for large-scale projects, such as infrastructure and oil and gas projects.
In a design-and-build contract, the contractor is initially responsible for all design aspects, but construction contracts often require the contractor to review the employer's design documents. This makes the contractor responsible for errors and/or omissions in these documents, as well as for any additional work required to address unidentified errors and/or omissions. The extent of design errors and omissions passed on to the contractor may change. It may include discrepancies or omissions in the design documentation or bill of quantities. In the FEED model, the employer will provide the preliminary design and planning, while the contractor will prepare and develop the detailed engineering.
In public design-and-build contracts, the contractor is responsible for any additional work to correct the relevant errors and omissions, unless they are caused by the elements provided by the employer. As for public construction-only contracts, there are statutory time limits for contractors to claim errors and omissions, after which the contractors are responsible for any additional work aimed at correcting unclaimed errors and omissions. When the tender documents permit and the contractor submits a variation to the base design, the contractor is liable for any errors or omissions, unless they result from data provided by the public employer.
The employer is responsible for paying the agreed price and providing the site, while the contractor is responsible for carrying out all the activities necessary to complete the project on time.
However, depending on the size and complexity of the project, other relationships may arise, such as those between the contractor and subcontractors and between the employer, contractor and third-party financiers.
Subcontractors have no direct relationship with the employer; they are liable to the contractor and the contractor is liable to the employer for the subcontractors’ actions. Some contracts allow employers to assume the role of contractors in subcontracts, particularly when the main contract is terminated.
In the case of public works, the responsibility for the site conditions, such as pollution, underground obstacles and geotechnical conditions, rests with the employer. The design provided by the public employer must define the site's characteristics. As a rule, the employer is responsible for any finds at the construction site, unless otherwise specified.
In the case of private works, there are no mandatory provisions on this matter. Responsibilities can be freely allocated.
The employer generally hands over the site to the contractor, who accepts responsibility for its suitability for the work, including non-visible conditions such as pollution, underground obstacles, geotechnical conditions and archaeological finds. The contractor is usually responsible for visible conditions, including access.
Given the importance of the site conditions for the complete and timely execution of the works, tests are usually done before the signing of the construction contract (or prior to delivery) for major projects. These tests include geotechnical, geological and environmental tests annexed to the contract and the contractor shall then develop the works accordingly.
To avoid claims arising from unforeseen effects of site conditions, construction contracts may transfer responsibility for them to the contractor. This is usually done by adding a clause stating that the contractor acknowledges the site’s conditions (including the subsoil) and has performed all necessary tests.
Before construction, the design must be approved by the relevant licensing authority. This requires the submission of detailed design documentation, including architectural plans, proof of land use rights and technical liability terms.
After the design is approved, a construction licence must be obtained. This licence authorises the commencement of the works and is issued upon submission of all the necessary documentation, including the approved design, cost estimates and proof of technical and contractor qualifications.
After construction, a use licence is required before the building can be occupied. This licence is granted following a technical inspection which ensures that the building complies with the approved plans and all legal and safety requirements.
Certain types of projects, such as industrial, commercial or tourism projects or those involving hazardous materials, may require additional approvals from central government ministries.
Although employers are generally responsible for obtaining the necessary permits, contractors and technical professionals (eg, architects and engineers) are often involved in preparing and signing technical documentation and liability terms.
Although the law places the responsibility on the owner by default, the parties may agree in a contract to allocate responsibility for obtaining certain permits to other parties (eg, the contractor or project manager). However, such arrangements do not exempt the owner from ultimate legal responsibility for compliance.
Usually, the contractor is responsible for managing site safety and maintenance and the works from handover to provisional acceptance. After this point, these responsibilities transfer to the employer without prejudice to the make-good period by the contractor. In energy projects, in particular, a maintenance and operations agreement is usually signed between the employer and the contractor, whereby the contractor becomes the operator and maintains the project for a certain period after acceptance. These contracts may include both ordinary and extraordinary maintenance as well as the supply of spare parts.
Employers may instruct contractors or third parties on functions such as design, licensing, construction, supervision, testing, operation, maintenance and financing.
This is particularly relevant in energy projects, where transferring operations to contractors is common. In the case of public concessions, the contractor often assumes financing responsibilities. Other contract structures may apply, such as the build-own-operate-transfer (BOOT) structure.
The contractor normally requests completion tests and inspections when the works are considered complete. Provisional acceptance of the works usually depends on successfully completing the specified contract tests and inspecting all the works. Contractors are usually responsible for the said tests. Responsibility for other tests usually depends on the results of these tests.
In pure construction projects, the tests usually cover only the installed equipment (without prejudice to the employer’s inspection of all works), whereas in, ie, energy projects, the tests are much more comprehensive. They include validation of compliance with the agreed performance ratios through detailed test procedures set out in the contract. The success of the tests will probably be linked to payment milestones.
The acceptance of private works is usually outlined in the contract and typically occurs in two stages:
Construction contracts often specify conditions for provisional and final acceptance. These include, but are not limited to, the following.
The transfer of risk of the works from the contractor to the employer shall take place upon provisional acceptance.
According to the Mozambican Civil Code, contractors are liable for any damage caused to the employer or future purchasers due to collapse or defects in the work for a period of five years after construction.
For construction contracts subject to consumer legislation (ie, if the employer or future purchaser is a non-professional), the law provides for a minimum warranty period against defects of five years for buildings and one year for equipment.
Public works have a similar supplementary warranty period of five years, unless otherwise stated. The warranty period must be at least one year and the law does not distinguish between buildings and equipment.
These periods run from the date on which the works are delivered to the employer. For construction contracts subject to consumer legislation, time limits are suspended while the consumer is unable to use the goods due to repair work.
During these periods, the employer and the consumers must comply with certain rules and deadlines regarding the notification of defects and the bringing of claims to courts. Failure to do so results in forfeiture of the corresponding right, as the Civil Code imposes strict time limits for exercising the right to remedy defects.
Before the warranty periods commence and upon acceptance of the works by the employer, the employer shall have the right to inspect the works and shall be obliged to identify any apparent defects, as well as any defects that are not apparent but have been identified by the employer.
If the contractor is not notified of the existence of such defects prior to acceptance, the contractor is not responsible for remedying them. Any apparent defects shall be deemed known to the employer, even if no inspection was conducted before accepting the work.
Following acceptance of the works and during the warranty period, the contractor shall be liable for any defects, as long as the employer complies with the maximum timeframe for reporting defects.
The contract price for construction projects can be determined using different methods:
Defining a global, fixed and non-revisable price is the most common method. It includes all the works and associated costs required to complete the awarded project.
When the required quantities of work for a project are unknown or cannot be determined in advance, the contract price can be established by multiplying the quantities of work performed by the agreed unit prices (unitary prices regime). In such cases, it is common to establish an “estimated maximum price”, which gives the employer the right to take any appropriate measures to reduce the project’s cost if this price is exceeded (or expected to be exceeded), such as seeking alternative, less costly technical solutions. The contract price may also be determined by an open-book system, whereby the main contractor subcontracts all or a relevant part of the works to subcontractors selected or approved by the employer, for an open-book fee. In return for this fee, the contractor assumes full responsibility for the subcontractors’ work. Sometimes, the price determined through an open book system becomes a global, fixed lump sum.
Finally, the contract price may be paid in either monthly instalments or milestones, the latter being more common in projects requiring significant equipment investments or relevant performance ratios.
Traditionally, contractors have been responsible for price fluctuations in private construction contracts, especially when the contract price is set as a fixed, non-revisable amount.
Generally, the price of public contracts is not subject to adjustment. However, if the contract provides for it, price adjustments may be applied, especially to contracts lasting more than one year. However, in public works, the risk of a significant increase in the price of a material that accounts for a large proportion of the job's cost is considered the employer's responsibility.
In recent years, contractors have been demanding price revision clauses in private construction contracts, as the prices of materials and equipment are subject to fluctuations. To manage this risk, it is common to link agreed unit prices to indexation formulas. These formulas trigger an adjustment, upward or downward, whenever price fluctuations surpass a specified threshold.
Construction contracts usually set out the consequences of late or non-payment of invoices, which may include:
Advance and deferred payments are common.
Advance payments are specified when the contractor must make relevant investments immediately upon commencement of the works, such as procuring essential materials and/or equipment or guaranteeing their cost. In private construction contracts, a first-demand bank guarantee is usually required to ensure completion of the works until the advance payment has been repaid. For public works, this is mandatory by law.
Deferred payments may be agreed upon when the contractor has completed the work, but validation of its correctness, functionality or performance is only possible after testing, which may occur at a later stage of the project. In such cases, it is common to stipulate that part of the price attributable to such work is only due once its correctness has been validated by testing.
If the parties consider it necessary for the project’s proper and timely completion, interim payments may be agreed upon during the execution of the work.
For public works contracts with unitary prices, the most common invoicing method is to submit monthly invoices based on the measurements of work carried out the previous month. For contracts with a global price, invoicing is done according to the financial plan and milestones.
This procedure is not mandatory in private construction contracts. However, it is common for the parties involved to use a similar procedure.
All invoices must comply with Mozambican tax laws, including the issuance of proper fiscal invoices that include:
While electronic invoicing is increasingly common, especially for larger contractors and employers, manual (paper-based) invoicing is still widely used, particularly among smaller construction companies or smaller projects.
The timeline for completing works under a construction contract typically includes global and partial deadlines agreed upon by the employer and the contractor and defined in a works programme attached to the contract.
The contractor must comply with the specified deadlines while performing the works. Failure to do so will result in the application of delay liquidated damages or penalties and/or compensation for damages incurred and/or even termination of the contract, subject to its specific stipulations.
The works programme is then complemented by updates from the contractor showing the real progress of the works and their correspondence with the agreed deadlines.
Supervision, which is usually designated and sometimes mandatory, provides the employer with the necessary information to assess the progress of the work.
When the contract price is paid by milestones, the employer validates each milestone through inspection and, when applicable, tests. The employer then issues a milestone completion certificate. This entitles the contractor to payment for the portion of the contract price associated with the completed milestone.
The same procedure applies to payments based on monthly measurements of work done, where the contractor’s report on work performed in the relevant month is validated and the contractor subsequently issues an invoice for the approved work.
The legal and contractual consequences of delays in performing obligations under a construction contract depend on the party responsible for the delay.
There are no specific rules regulating concurrent delays and contracts rarely address them. Some legal principles relating to the causal link between a fact and damage may apply. Construction contracts often provide for a claim procedure by the contractor, subject to time limits under penalty of forfeiture of the right.
If the contractor delays completion of the work, the employer is generally entitled to the remedies identified in 5.2 Delays. Under Article 812 of the Mozambican Civil Code, the courts may reduce the amount agreed as damages if it is proven to be manifestly excessive.
In public contracts, delays in work execution are subject to statutory penalties, ranging from 0.5 to 1%, with a cap of 20%, unless the contract specifies a lower limit. If this ceiling is exceeded, the employer may terminate the contract.
Contracts typically regulate the procedure for extension of time. Contractually, any requests for an extension of time must be submitted in writing to the employer. The request must describe the reasons for the delay and prove that it is not the contractor’s fault.
The extension of time shall be determined by analysing whether the delay has affected the performance of the works and the critical path and whether the cause of the delay is within the contractor’s risk or not.
Generally, an extension of time is allowed for delays caused by force majeure, unforeseen constraints by the employer or by acts or omissions of third parties for which the contractor is not responsible. The definition of the contractor’s sphere of risk will generally result from the provisions of the contract or the lack thereof.
The same principles apply to public contracts. Except in cases of force majeure, the Regulation for Contracting Public Works does not establish deadlines for requesting an extension of time; such deadlines are to be defined contractually. In the event of a force majeure situation, the contractor must submit a request to the supervisor within eight days for certification of the occurrence and consequences of the force majeure case. The supervisor’s report shall be sent to the employer five days after its production or after the decision on reclamation, if any.
Given Mozambique’s exposure to natural disasters and regional instability, force majeure clauses are critical. The force majeure clause is commonly included in private construction contracts and is defined by the parties. This contractual definition usually includes only those events that were beyond the reasonable control of the party claiming force majeure, were not reasonably foreseeable and, if foreseeable, were unavoidable or could not reasonably be prevented or overcome.
It is also common practice to provide examples of events that may be considered force majeure, provided they meet the above criteria. These may include:
A party affected by a force majeure event is usually entitled to a time extension for the duration of the event. If the event lasts beyond a specified period (usually around 90 to 180 days), either party may terminate the contract. Unless otherwise agreed, each party typically bears its own costs if an event of force majeure occurs.
In public works, contractors are not responsible for defects or delays resulting from a force majeure event. The employer is responsible for any loss or damage caused by force majeure or any other event not attributable to the contractor (unless the contract states otherwise).
Mozambique’s Civil Code allows for the termination or modification of contracts due to unforeseen circumstances, in accordance with the principle of fairness (Article 437). This can be invoked only in cases of extreme gravity, where fulfilling the obligations of both parties would seriously affect good faith.
Employers often transfer responsibility for design errors, omissions and unexpected site conditions to contractors. This makes contractors responsible for any additional work required due to:
In public contracts, the contractor is entitled to financial compensation for additional costs resulting from substantial and unforeseeable changes in contractual conditions, provided that these costs are not considered risks for which the contractor is legally or contractually responsible. The contractor must also identify errors and omissions in the design, as well as unexpected site conditions, within the timeframe defined in the tender documents. The contractor must then submit a claim for variation. If errors or omissions cannot be identified within this timeframe, the contractor may submit a claim within ten days of their detection.
Under Mozambican law, disruption is recognised as a valid reason for an extension of time and/or compensation if the contractor can prove that the disruption was caused by the employer's breach of its contractual or legal obligations.
If the disruption is not the fault of either party, it may fall within the scope of Article 437 of the Mozambican Civil Code, which deals with “abnormal change of circumstances”. If there has been an abnormal change in the circumstances, the affected party may be entitled to the remedies mentioned in 5.6 Unforeseen Circumstances.
In public contracts, the contractor is entitled to claim financial compensation equal to the price difference caused by the abnormal and unpredictable circumstances, if the disruption is not included in the risk contractually or legally attributable to the contractor. If a public employer causes an increase in the project's costs, it must compensate the contractor. If the disruption falls under Article 236, the contractor can claim an extension.
Articles 809 and 800/2 of the Mozambican Civil Code allow for contractual exclusions or limitations of liability, if they do not apply to acts constituting a breach of duties imposed by public order rules. Liability arising from acts/omissions committed with gross negligence or intent or which result in injury or death, for example, cannot be covered by a contractual exclusion/limitation of liability.
Mozambican law recognises the concepts of wilful misconduct and gross negligence. The main consequence of classifying certain behaviour as intentional or grossly negligent is that limitation clauses cannot be applied, even with the agreement of the parties involved.
The parties may agree to limit their liability as set forth in 6.1 Exclusion of Liability. Typically, it is limited to a percentage of the contract price and certain types of damages may be excluded, such as consequential and indirect damages or even loss of profit.
The amount of penalties payable under public construction contracts is limited by law to 20% of the contract price, unless the employer decides to terminate the contract.
Construction contracts use indemnities to limit risk. The following risks are generally covered by indemnities:
The obligations and risks associated with a construction contract are usually covered by guarantees. These can be bank guarantees, price retentions, insurance bonds or parent company guarantees.
Bank guarantees and price retentions remain the preferred method of protecting the employer against the risk of the contractor’s default. Insurance bonds are generally considered less protective because they depend on the insurance policy’s terms and conditions, while bank guarantees depend solely on their wording.
Bank guarantees and price retentions are usually used for security purposes:
These bank guarantees are often autonomous, on first demand, irrevocable and unconditional. The guarantor can only refuse payment if they have clear documentary evidence that its execution is fraudulent or abusive. This provides certainty to the market, as mere doubt does not allow them to refuse.
Although less common, a parent company guarantee or a letter of credit may be required from the employer. This would apply to capital-intensive projects in order to assure the contractor that the employer has the financial capacity to pay the contract price.
Performance bonds are usually provided by the contractor and amount to between 5% and 15% of the contract price.
There are three types of guarantees in public contracts:
The definitive guarantee is provided after the contract has been awarded and before its signing. It aims to ensure the proper and timely fulfilment of contractual obligations and may not exceed 10% of the proposed price. Upon completion of the works, the contractor must submit a guarantee covering 5% of the value of the work to cover defects during the guarantee period. The following guarantees are accepted:
All contractors are required to take out a third-party liability insurance policy, mostly covering the acts and omissions of the contractor (contractors’ all risk (CAR) insurance) and its personnel. Labour law also requires employers to provide insurance that covers workplace accidents and occupational illnesses.
The parties may agree on other types of insurance they consider necessary to fulfil the contract.
Construction contracts commonly include a provision allowing either party to terminate the contract in the event of the other party’s insolvency.
The validity of this type of provision is questionable in Mozambique because it may conflict with the principles and objectives of insolvency law, namely with Article 114 of the Mozambican insolvency law, which stipulates that an insolvency administrator may decide to comply with the contract if such compliance reduces or avoids increasing the debt of the insolvent estate. Therefore, this type of issue must be carefully regulated in the contract.
Most of the risks are generally allocated to the contractor, who typically has greater opportunities and abilities to manage them. Therefore, risk-sharing procedures are not common.
The employer is typically responsible for subsoil, pollution, archaeological findings, financial and licensing risks, while the contractor handles risks such as procurement delays or price increases (in the absence of a revision clause).
Construction contracts usually bind contractors to several obligations regarding their own personnel and those of their subcontractors.
The contractor is typically responsible for making sure that its staff (and those of its subcontractors):
The Ministerial Decree No 92/2025, of 22 September, set the new minimum wage for the construction sector at 8,400.00 MT, effective from 1 July 2025.
Subcontracting is generally accepted for private projects, except in exceptional cases. This is true even if the construction contract does not expressly provide for this possibility.
It is standard practice for construction contracts to expressly set out the rights and limitations of subcontracting. As such, this right is often granted with exceptions. For example:
Subcontracting is permitted for public construction contractors if they obtain authorisation from the public employer and provide the required information.
Architects and engineers who are responsible for the design of a property usually own all related intellectual property.
IP rights may be assigned to the employer by the owner. However, the moral rights must remain the property of the design’s author.
Architects legally have a moral right to prevent changes to the property they designed. This means that employers may not, either during or after construction, introduce changes without the prior consultation of the architect. In the absence of an agreement, the architect is entitled to repudiate ownership over the designed work and the employer will be forbidden from using, in its own interest, the architect’s name in relation to the work.
Under Mozambican civil liability principles, if one party breaches a contract, the other party is entitled to compensation for any resulting damage, including loss of profits, provided that the legal criteria for contractual civil liability are met. These are:
Whether the breach and the loss are causally linked is determined by establishing whether the loss would have occurred in the absence of the breach. If the loss had occurred even without the breach, there is no causal link.
The non-defaulting party may also terminate the contract for fair cause. However, termination of the contract may be subject to a remedy period. This applies to all contracts, including those between employer and contractor or employer and designer.
In the case of public contracts, the contractor shall be entitled to terminate the contract in accordance with the Regulation for Contracting Public Works, namely due to:
Termination of the agreement under these conditions shall entitle the contractor to the return of the definitive guarantee, to payment for works completed up to the point at which the termination takes effect and to payment for the decommissioning of the construction site.
On the employer’s side, the contract may be terminated, among others, in the following cases:
The execution of a public contract may be suspended in two cases, provided that the event causing the suspension is not the contractor’s fault:
Private construction contracts sometimes limit the remedies available to the parties in the event of breach. Without prejudice to other mechanisms, this is usually done by:
As for public contracts, the parties cannot restrict the legal remedies established by law.
The admissibility of sole remedy clauses is a debated issue. Part of the doctrine recognises that they are not prohibited, provided that a case-by-case analysis confirms that the specific clause does not conflict with imperative legal norms.
As mentioned in 9.2 Restricting Remedies, the parties to a private construction contract in Mozambique may exclude or limit liability. This is not applicable to public works and is usually seen in relation to:
However, these exclusions are more common in major construction projects. In other cases, the parties usually simply refer to the applicable law (described in 9.1 Remedies).
The Mozambican Civil Code expressly recognises the contractor’s right of retention. This entitles the contractor to retain possession of the works and the site as security in the event of non-payment of the contract price or any other sums due in connection with the execution of the works. This prevents the employer from using the works.
Although construction contracts often state that the contractor waives this right, the validity of clauses that completely exclude the right of retention in all circumstances is disputed.
Conversely, the contractor’s suspension rights are usually limited in construction contracts, with clear definitions of specific cases in which the contractor may suspend the performance of the works.
However, this contractual restriction does not affect the legal right of either the contractor or the employer to invoke the “exception of non-performance” if the obligations of the two parties are reciprocal. In such cases, the non-breaching party may refuse to fulfil their obligations until the breaching party resumes theirs.
The Regulation for Contracting Public Works allows for the termination of public contracts in three ways:
The causes for unilateral termination are exemplified in 9.1 Remedies.
A party intending to unilaterally terminate the contract must notify the other party in writing, specifying the cause and grounds for termination. The notified party then has 30 days to remedy the breach. If the breach is not remedied within that period, the notifying party may proceed with termination.
Public contracts may also terminate automatically upon:
Under the Regulation for Contracting Public Works, the employer may suspend the contract for an indefinite period. Such suspension may lead to termination in the employer’s interest. In that case, the contractor is entitled to fair compensation, which includes all payments due up to the date of termination and reimbursement for actual losses or damages incurred as a result.
In private construction contracts, it is common for the parties to include provisions granting a right to immediate termination upon the occurrence of specific events. These typically include:
Civil law permits termination of a contract when a definitive breach by one party is established. A breach is considered definitive when:
Accordingly, the verification of a definitive breach depends on the prior delivery of a notice granting a period to remedy the breach.
Article 1229 of the Mozambican Civil Code, applicable to private construction contracts, establishes the employer’s right to withdraw from the contract at any time. To exercise this right, the employer must compensate the contractor for all expenses incurred, work performed and the profit the contractor would have earned from completing the works.
In Mozambique, there is no adjudication process, nor specific courts that deal solely with construction contract disputes. Generally, these disputes are resolved in the common or administrative courts or through arbitration. Arbitral tribunals are expressly foreseen in the Constitution of Mozambique.
Mozambique favours arbitration as a dispute resolution method, with a legal framework that supports it. Parties to a construction contract can choose arbitration, conciliation and mediation as alternative dispute resolution methods. These are governed by the Mozambican Arbitration, Conciliation and Mediation Law (Law no 11/99, of 8 July 1999), which aligns with the UNCITRAL Model Law on International Commercial Arbitration of 1985 and incorporates many commonly accepted best practices. Additionally, Mozambique is a party to the 1958 New York Convention on the Recognition and Enforcement of Foreign Arbitral Awards. As a result, arbitration clauses are frequently included in public and private construction contracts.
Av Fontes Pereira de Melo, 43
1050-119 Lisboa
Portugal
+351 213 197 300
plmjlaw@plmj.pt www.plmj.pt
Mozambique: Public Contracts, Foreign Exchange Constraints and Execution Risk in the Construction Market
Introduction
Mozambique continues to present meaningful opportunities for investors, sponsors, contractors and suppliers active in infrastructure, energy, transport and public works. The market remains relevant not simply because there is demand for new infrastructure, but because major projects in Mozambique often sit at the intersection of public policy, strategic investment and complex construction delivery. That combination continues to attract international contractors, external finance and cross-border supply chains. At the same time, however, the legal and commercial context in which construction contracts are performed has become more demanding, particularly where the execution of the works depends on imported inputs, offshore payments and carefully sequenced project programmes.
For construction lawyers and project participants, the central trend is no longer limited to how contracts are awarded but increasingly concerns how they can be performed once awarded. In Mozambique today, the legal analysis of a project cannot stop at tender compliance, contract formation or formal approvals. Those issues remain important, but they are no longer sufficient. The more difficult question is whether the contractual structure can absorb disruption in payments, procurement and delivery without quickly turning operational pressure into a formal dispute. In practical terms, a project may remain commercially desirable and legally valid while still becoming materially harder to perform in accordance with its original assumptions.
The most important driver of that shift is the shortage of foreign currency liquidity in the commercial banking system. Where contractors depend on imported equipment, materials or specialist services, delayed access to foreign currency can slow procurement cycles, disrupt supply chains and place immediate pressure on performance milestones. In that environment, what might once have been treated as a financial inconvenience or project management issue increasingly raises core questions of construction law: who bears the risk of delayed importation, whether the contractor is entitled to additional time or money, when suspension becomes legally defensible and how price and programme mechanisms should respond to a change in execution conditions.
From a legislative and regulatory perspective, three recent developments may affect the construction sector in Mozambique:
Opportunity remains, while execution assumptions are harder to sustain
Mozambique remains a market where infrastructure and construction projects continue to attract attention, particularly in sectors linked to energy, logistics and strategic public investment. International market commentary continues to identify construction as a sector with growth potential, supported by infrastructure needs and by projects associated with power, transport and resource-related development. Yet the broader economic setting remains fragile, shaped by financing constraints, pressure on public expenditure and foreign exchange shortages. For project participants, this means that the opportunity side of the market remains intact, but the assumptions on which construction contracts are priced and programmed have become far less stable.
That distinction is important from a legal perspective. In many jurisdictions, delay risk is analysed primarily as a matter of contractor management, site productivity or technical underperformance. In Mozambique, however, delays increasingly reflect broader systemic pressures affecting procurement, importation, cross-border payment flows, contract administration and institutional responsiveness. This does not remove the contractor’s obligation to perform, but it does mean that performance risk can no longer be assessed solely by looking at design, resources or construction methodology. The legal resilience of the project now depends just as much on the realism of its commercial assumptions as on the quality of its engineering assumptions.
For sponsors, lenders, contractors and public counterparties, the practical consequence is that bankability and formal legality are no longer enough. A project may appear sound at the procurement stage and still become vulnerable at the execution stage if the contract assumes ordinary access to imported materials, smooth customs processing, predictable certification cycles and ready availability of offshore payment channels. The current Mozambican environment, therefore, rewards contracts that are structurally adaptable. In other words, the legal quality of the project is measured not only by whether the contract was validly awarded, but also by whether it contains workable mechanisms to manage disruption without immediate escalation into default, termination or entrenched dispute.
Foreign exchange scarcity: a construction law issue, not only a financial one
The shortage of foreign currency has become one of the most important sources of contractual tension in Mozambique’s construction sector. Business reporting and international financial commentary have both pointed to ongoing pressure in the market, linked to difficulties in obtaining foreign currency from commercial banks and delays in settling external obligations. Even where reserve indicators suggest a degree of macroeconomic stability, market participants continue to experience day-to-day frictions that affect the timing of international payments and the practical movement of goods and services required for project delivery. For construction contracts, this disconnect matters more than the headline macroeconomic narrative.
In public works and other complex construction projects, imported inputs are frequently indispensable. Contractors may rely on imported plant, electromechanical systems, specialist materials, technical components or offshore services that cannot be easily replaced at short notice. If those items cannot be procured or paid for within the time assumed by the contract, the contractor’s ability to meet milestones is weakened, even though the legal obligation itself remains unchanged. This immediately places pressure on clauses dealing with:
Once foreign exchange scarcity begins to affect supply, the legal question is no longer whether there is a problem, but how the contract allocates the consequences of that problem.
The legal complexity arises because foreign exchange constraints do not fit neatly into standard categories of construction risk. They are not always force majeure in the strict sense, but nor are they necessarily risks that can simply be absorbed by the contractor as part of ordinary commercial pricing. Much depends on:
In practice, the most difficult disputes are likely to arise where the contract says too little about currency-related procurement disruption, leaving the parties to argue later over whether the event was foreseeable, whether it falls within contractor risk and whether the employer should bear at least part of the time or cost consequences.
This issue is particularly acute in public contracts. Public projects often combine fixed pricing expectations, ambitious completion periods and limited tolerance for programme slippage. Those features become legally problematic if performance later depends on a supply chain that cannot operate under ordinary conditions. In that context, disputes may emerge over:
For that reason, foreign exchange scarcity in Mozambique should now be understood as a central issue of construction law rather than merely a macroeconomic background condition.
In public contracting, legal risk no longer ends at award
Mozambique’s public procurement environment continues to evolve through efforts to modernise administrative practice and improve procurement systems. External commentary, however, suggests that implementation remains uneven and that suppliers still encounter recurring issues linked to standardisation, coordination and the practical functioning of procurement procedures. For construction lawyers, the most important implication is that public procurement risk in Mozambique can no longer be treated as confined to the tender phase. The award remains important, but the more difficult legal questions now often arise after contract signature, when public law structures meet execution realities.
In the current market, public contracts are exposed to two overlapping layers of legal risk. The first is the classic public procurement layer:
The second is an execution layer shaped by external constraints that directly affect performance, including foreign exchange shortages, import bottlenecks and reduced predictability in procurement cycles. Each layer is manageable in isolation. The legal difficulty is that they now operate simultaneously. A contract may be procedurally regular and still become contentious if its performance structure is too rigid to accommodate changes in supply, timing or cost.
That interaction has important consequences for legal review. A tender may appear acceptable because the procurement documents are internally coherent and the award mechanism is clear; however, the contract may still prove fragile if it assumes that imported materials will arrive on time, that certification and payment will move without friction or that the sequencing of the works can be maintained despite disruption in procurement. The more rigid the contract, the greater the risk that execution difficulties will be channelled into formal claims for delay, disruption, remeasurement, substitution, price adjustment or even termination. In other words, a procurement-safe contract is not necessarily an execution-safe contract.
For this reason, legal review at the tender stage should no longer be limited to formal responsiveness and compliance analysis. It should also test whether the proposed contract includes practical mechanisms for:
Particularly in Mozambique, clauses on contract administration, compensation, notice and relief have become as important as those on eligibility, evaluation and award. This is one of the clearest ways in which public law and construction law now intersect in the market.
Contract administration becomes more important than formal contract formation
A further trend in Mozambique’s construction market is the increasing importance of contract administration as a source of legal protection. As projects become more technical, more supply-intensive and more dependent on cross-border logistics, the formal validity of the contract becomes only the starting point. The real legal stability of the project depends on whether:
In a stressed market, weak contract administration can do as much damage as weak drafting.
This matters because construction disputes rarely arise from a single dramatic breach. More often, they emerge from accumulated failures in managing change. Delayed approvals, ambiguous instructions, unresolved questions about substitutions, slow certification, incomplete records of disruption and unaddressed requests for extension of time may each appear manageable in isolation. Once foreign exchange shortages and procurement disruptions affect the project, those deficiencies compound. What might otherwise have been absorbed through cooperative administration becomes harder to regularise and the project shifts from controlled slippage into legal confrontation. In that sense, administration is no longer merely procedural; it is central to risk containment.
From a drafting perspective, this means parties need to pay close attention to the internal mechanics of the contract. Notice clauses, time bars, evidentiary requirements for claims, rules for valuing variations, interim payment procedures, testing and acceptance stages and escalation mechanisms for dispute management all assume greater significance when execution conditions are volatile. In a more stable market, these clauses may be treated as standard boilerplate. In Mozambique’s present environment, they are anything but standard. They are the legal architecture through which the contract either absorbs disruption or fails under it.
This is especially true in public projects, where administrative formalism may be high and decision-making can be slower than the pace at which site conditions evolve. Contractors, therefore, need more than technical competence. They need disciplined claims management, clear documentary records and early engagement with contractual remedies. Employers and public entities, in turn, benefit from recognising that administrative delay or indecision may itself become a driver of dispute where the execution environment is already under stress. In Mozambique, legal certainty in construction increasingly depends on the quality of contract management during performance rather than on the elegance of the contract at signature.
The role of foreign contractors and cross-border delivery structures
Another visible trend in the Mozambican construction market is the continued importance of foreign contractors on larger, more technically demanding projects. External market guidance identifies firms from several foreign jurisdictions as significant participants in Mozambique’s design and construction space, particularly on projects involving complex infrastructure, energy-related works or specialist technical inputs. This reflects a market in which large projects frequently require external capital, international supply chains and delivery structures that extend beyond the domestic contracting ecosystem.
From a legal perspective, the increased role of foreign contractors matters not because their presence is unusual, but because it often intensifies the importance of cross-border risk allocation. The more international the delivery structure, the greater the likelihood that contract performance will depend on imported goods, offshore procurement, foreign subcontracting relationships, specialist technical interfaces and payment flows outside Mozambique. That increases the relevance of clauses dealing with currency, sourcing, substitution, governing procedures for change, coordination among multiple contractual layers and the treatment of delays that originate outside the site but affect progress on site. Cross-border delivery structures are therefore not just a commercial feature of the market; they are a legal feature of risk distribution.
This does not make foreign participation negative. On the contrary, it often strengthens delivery capacity, technical sophistication and project discipline. But it does mean that projects in Mozambique should be documented on the assumption that procurement, payment and execution will interact across multiple jurisdictions and contractual levels. A main contract may appear balanced in isolation, yet still become vulnerable if upstream procurement obligations, shipping realities or external payment arrangements do not align with the timing and relief mechanisms in the works contract itself. The key legal question is therefore not simply who performs the works, but whether the contract recognises how those works are actually sourced and delivered.
What clients should focus on now
For clients entering or expanding in Mozambique, the current environment requires a more disciplined approach to construction contracting and public project execution. In particular, five legal areas deserve close attention.
Conclusion
Mozambique remains a market of genuine opportunity for infrastructure and construction participants. The most important recent development, however, is that project success now depends less on identifying opportunities than on structuring them realistically. Foreign exchange shortages have moved from the economic background to the centre of project execution, with direct consequences for procurement, timing, payment and contractual performance. For lawyers advising on public works and construction, that means the focus must shift from formal legality alone to the legal architecture of performance.
The key lesson is that, in Mozambique, public contracting and construction risks cannot be analysed separately. Tender compliance, award validity and formal approvals remain essential, but they do not determine the whole legal picture. The issues most likely to shape the project’s life are now risk allocation, extension-of-time entitlement, price flexibility, administrative discipline and the contract’s capacity to absorb disruption without collapsing into dispute. In the present market, execution architecture is the real centre of gravity of construction law.
In short, the defining trend in Mozambique is not the absence of projects, but the growing legal complexity of delivering them. The meeting point between public procurement and construction law increasingly lies in the execution phase: the point at which payment structures, sourcing assumptions, administrative responsiveness and contractual relief mechanisms determine whether the works can still be completed on the terms originally envisaged. That is the perspective from which construction contracts in Mozambique now need to be drafted, reviewed and administered.
Av Fontes Pereira de Melo, 43
1050-119 Lisboa
Portugal
+351 213 197 300
plmjlaw@plmj.pt www.plmj.pt