Norway’s power market is a cornerstone of its economy, characterised by a comprehensive regulatory framework that is aimed at ensuring efficient operation and sustainability. The Norwegian power sector is distinguished by its significant reliance on renewable energy sources, particularly hydropower, which accounts for a substantial portion of electricity generation. As of 2024, approximately 88% of the energy mix was derived from hydropower, while wind power contributed around 11% (see also 2.2 Electricity Imports and Exports).
Notably, more than 75% of Norwegian hydropower production is flexible, thanks to the presence of reservoirs that account for half of Europe’s total reservoir storage capacity. This not only underscores Norway’s commitment to sustainable energy, but also influences the structure and regulatory approach of the industry.
The Norwegian power industry’s ownership structure influences its operation, efficiency and strategic direction, and is characterised by a mix of state, municipal and private ownership. The public sector owns approximately 90% of the production capacity for electric power in Norway – mostly due to requirements for a minimum of two-thirds public ownership for hydropower (see also 1.4 Sale of Power Industry Assets). The largest producer is Statkraft SF, which is wholly owned by the state and is Europe’s largest generator of renewable energy. The Norwegian mixed ownership model, combined with a robust regulatory framework, supports Norway’s objectives of maintaining a reliable, efficient and sustainable power system.
Statnett SF, also a state-owned entity, owns almost 100% of the Norwegian transmission system, as well as a significant portion of cross-border cables, including subsea interconnectors. It is mandatory for all grid companies to be legally unbundled, and grid companies with more than 100,000 customers must also be functionally unbundled, as specified in the Energy Act (Sections 4-6 and 4-7). Most grid companies are primarily owned by municipalities and counties, although some are privately owned as well. There are no requirements for public ownership for wind power plants, solar power plants, and transmission or distribution facilities.
The governance of ownership and operations within the various segments of the Norwegian power industry is underpinned by several pivotal statutes, notably the Energy Act (Energiloven). This Act lays down the foundational legal framework for structuring the electricity sector in Norway, addressing aspects such as market regulation, system responsibilities, and fostering a competitive market landscape. Ownership of hydropower plants is regulated in the Waterfall Rights Act.
The Norwegian Water Resources and Energy Directorate (Norges vassdrags- og energidirektorat or the NVE) plays an instrumental role in regulatory oversight of the energy sector. The NVE handles licence procedures, ensures adherence to legal standards and monitors the energy sector to promote efficient and sustainable operations. The Norwegian Energy Regulatory Authority (Reguleringsmyndigheten for energior the NVE-RME) is the regulatory authority for the electricity and natural gas markets.
Other central authorities include various ministries within the Norwegian government, with the Ministry of Energy (Energidepartementet) being at the forefront, having the overall responsibility for the energy sector.
Production
As mentioned in 1.1 Law Governing the Structure and Ownership of the Power Industry, about 88% of production comes from hydropower, and 90% of hydropower resources are owned by public entities. The following players are at present the largest in Norway in the production segment:
Transmission
The transmission grid owner and operator/transmission system operator (TSO) is Statnett SF, which is 100% state-owned.
Distribution
Most grid companies are completely or partly owned by one or more municipalities; the following are at present the largest in Norway:
Electricity Suppliers
Electricity suppliers are mainly private-owned companies, with some public ownership added to the mix. Fortum Strøm AS and Fjordkraft AS are among the largest in this category.
Public Ownership Hydropower
To utilise water resources for electricity production, the power producer must acquire the necessary property rights for the waterfalls and pertinent rights (see the Waterfall Rights Act, which does not apply to small-scale hydropower plants under the limit of 4,000 natural horsepower).
Licences under the Waterfall Rights Act are exclusively granted to public entities. These entities may be Norwegian state-owned enterprises, municipalities or county authorities, as well as companies where public bodies make up at least two-thirds of the capital and the votes. Private entities are permitted to own up to one-third of a company that possesses a licence under the Waterfall Rights Act.
A licence application under the Waterfall Rights Act shall be filed to the Ministry of Energy.
According to the Energy Act (Section 4-8), only the TSO (Statnett SF) can own transmission grid facilities.
The Security Act
Foreign investments may be subject to ownership screening under the Security Act. This ownership screening requirement applies to entities that fall under the purview of the Act, as well as suppliers of goods or services involved in classified procurements. Under the Security Act, a ministry has the authority to determine that Chapter 10 (which covers ownership screening) should be applicable to businesses determined to have significant importance for national security.
When acquiring a qualifying holding in an entity that is subject to Chapter 10 of the Security Act, the acquirer is required to notify the Ministry. Currently, this requirement applies to only a limited number of entities within the energy sector.
No Special Protections or Incentives
The regulatory framework governing licensing is applied equitably to investors, irrespective of whether they are domestic or foreign.
There are no special protections that apply to foreign investors, or special incentives or protection to encourage foreign investment in the Norwegian power industry. Foreign investors may obtain the same property rights and will have access to domestic courts.
The principal laws governing the sale of power industry assets and transactions are the Waterfall Rights Act and the Energy Act.
The Waterfall Rights Act
The Waterfall Rights Act regulates waterfalls that have the potential to yield 4,000 natural horsepower or more. A licence for such waterfalls can only be issued to public entities, such as state-owned enterprises, municipalities and county authorities, or to companies where these entities hold at least two-thirds of the capital and voting rights. Private entities can own up to one-third of the capital and one-third of the voting rights in such companies. These requirements apply to sales of assets or businesses in companies holding waterfall rights pursuant to the Waterfall Rights Act, as well as in amalgamations and mergers.
Additionally, the transfer of regulation facilities or shares in regulation facilities can only occur simultaneously with the transfer of waterfall rights, as described in the Watercourse Regulation Act.
The Energy Act
According to the Energy Act, all grid companies must undergo legal unbundling, meaning they cannot engage in activities other than grid development and operation. Grid companies with more than 100,000 customers must also undergo functional unbundling, operating independently from other companies within a vertically integrated company group.
Transmission grid facilities can only be owned by the TSO (Statnett SF) and cannot be sold to others.
Furthermore, owning and operating an energy facility requires a licence under the Energy Act. In cases of amalgamations and mergers, the parties involved must ensure the transfer of the licence by applying to the NVE.
The energy authorities are responsible for processing licence applications and issuing licences for grid and production facilities. Most of the licences are issued by the NVE, which is also the supervisory authority.
The NVE has been designated as the emergency management authority by the Ministry of Energy (see the Energy Act, Chapter 9 and the Regulation on Security and Emergency Preparedness in the Power Supply System). The Directorate co-ordinates emergency response work and appoints the overall management of the Power Supply Preparedness Organisation (Kraftforsyningens beredskapsorganisasjon; KBO). The NVE ensures that provisions in, or in accordance with, the Regulation on security and emergency preparedness in the power supply system (kraftberedskapsforskriften) are followed.
Statnett, the nationwide TSO, is tasked with always ensuring a reliable and secure energy supply. This responsibility requires the maintenance of a power grid with sufficient transmission capacity. Additionally, Statnett manages peaks in electricity consumption and oversees the import of the necessary volumes of electricity to meet demands.
The NVE has been designated as the rationing authority by the Ministry of Energy. The NVE shall ensure that the necessary plans and procedures for notification, implementation, execution and termination of power rationing are always prepared.
Amendments to the Energy Act
Several amendments have been made to the Energy Act over the last year. Notably, the Act has been amended to incorporate a new Chapter 4A, which pertains to agreements for the purchase of electricity between power suppliers and consumers. This chapter is designed to improve the efficiency and consumer-friendliness of the electricity market by making it more transparent and easier to navigate for consumers. The five provisions within this chapter impose obligations on electricity suppliers to, among other things, offer customers a cooling-off period and make information regarding termination costs more accessible.
New Maturity Requirements for Grid Connection
Effective from 1 January 2025, new provisions in the Regulation on Network Regulation and the Energy Market (Forskrift om nettregulering og energimarkedet, or “NEM Regulation”) have been implemented to prioritise mature projects for connection to the power grid. These changes are a response to the sharp increase in demand for grid capacity in Norway in recent years, where grid companies face challenges in providing all the requested capacity. Grid companies are required to assess the maturity of projects based on criteria such as capacity needs, progress plans, and financing. Entities with mature projects can reserve capacity or queue positions, but must maintain progress to retain them. Significant deviations may result in the withdrawal of reservations. These changes also apply to projects with existing rights.
No Licence Requirement for Smaller Solar Power Plants
The Norwegian government has decided to introduce a 10-MW limit for requiring a licence for solar power plants. This means that from 1 July 2025, solar installations with a capacity up to 10 MW will no longer need a licence under the Energy Act, but will instead be handled by municipalities under the Planning and Building Act. This change aims to free up capacity at the NVE, though it remains uncertain whether it will speed up the development process.
Hydropower Development in Protected Watercourses
On 13 February 2025, the Norwegian Parliament passed a decision allowing for the concession processing of hydropower projects with an installed capacity of over 1 MW in protected watercourses. There are currently 390 such protected watercourses in Norway. Two criteria must be met for concession processing: significant societal benefits, such as flood mitigation, and acceptable environmental impacts. The decision does not repeal watercourse protection as such, but it allows for the consideration of hydropower development in protected watercourses, provided conservation values are upheld and societal benefits are substantial.
Fixed Price Rate for Electricity Consumption
The Norwegian government has proposed the Norgespris (the “Norway Price”), a voluntary, state-funded scheme enabling households to pay a fixed price per kilowatt-hour for electricity consumption. This initiative aims to provide households with more predictable electricity expenses amidst fluctuating and occasionally high prices. It applies to both residential and holiday homes, with a proposed fixed price of NOK0.4 per kilowatt-hour, excluding VAT and additional costs like grid fees. The scheme sets consumption limits at 4,000 kilowatt-hours per month for households and 1,000 kilowatt-hours for holiday homes. The government intends to present a legislative proposal and seek parliamentary approval before the summer holiday, targeting implementation from 1 October 2025 and initially running until 31 December 2026.
Reduced Electrical Power Tax
The Norwegian government has proposed a reduction in the electrical power tax as part of the revised national budget for 2025. This proposed reduction will be applicable to both private households and businesses. For a household with an annual electricity consumption of 15,000 kWh, this would result in savings of approximately NOK825 per year. Like the Norgespris, this initiative is part of the government’s strategy to provide greater predictability and lower costs for electricity consumers.
Partial Implementation of the EU’s Clean Energy Package
After negotiations that led to the Centre Party’s withdrawal from the government in January 2025, the Norwegian government decided that the EU’s Renewable Energy Directive from 2018, the Energy Efficiency Directives from 2012 and 2018, and the Energy Performance of Buildings Directive from 2018 will be incorporated into the European Economic Area (EEA) Agreement and made part of Norwegian law. These directives are part of the EU’s Clean Energy Package, adopted in 2018 and 2019. The government has indicated that four regulations and one directive from the Clean Energy Package will remain on hold until 2029. Although the directives now being implemented were revised in 2023/2024, the government has not yet made a decision regarding these revisions.
Further Amendments to the Energy Act
In May 2025, the Norwegian Parliament voted for several amendments to the Energy Act aimed at promoting the development of renewable energy and enhancing grid infrastructure. These changes also seek to streamline the concession process and make it more predictable. Among the key amendments is the empowerment of regulatory authorities to terminate the processing of energy projects early in the concession process if it is evident that the projects will not receive a licence. This authority can be exercised under specific circumstances, such as the dissolution of the company, placement of the project in protected areas, risk of natural damage or significant environmental drawbacks. Other key changes include the introduction of time limits for concession holders regarding the commencement and completion of projects.
Offshore Wind
Offshore wind is on the move in Norway as the Norwegian Continental Shelf is “going green”. The regulatory framework is still under development: updated information and the latest news about the Norwegian offshore wind development is available online.
The Norwegian energy sector is unique in several ways, particularly due to its geographical, climatic and legislative characteristics. Some of its distinctive features are as follows.
The Norwegian Wholesale Electricity Market
Norway’s electricity market is an example of a mature, liberalised energy system that has been evolving since the early 1990s. As part of the Nordic electricity market, Norway has been at the forefront of market-based energy trading, emphasising efficiency, competition and cross-border integration.
The Energy Act is the principal law governing the structure and function of the wholesale market. Regulation (EU) No 1227/2011 on wholesale energy market integrity and transparency (REMIT), the EU framework for detecting and deterring wholesale energy abuse, has not been implemented into Norwegian law. Many of the regulations that follow from REMIT are, however, implemented through the Energy Act and its Regulations, as well as the Nord Pool’s (private law) regulatory framework that prohibits market abuse.
At the heart of Norway’s electricity sector is a market-based trading system. This system is characterised by its high level of hydroelectric power, making the Norwegian market highly renewable and flexible. The unique aspect of Norway’s electricity generation is its capacity to act as a “green battery” for the region, given its ability to quickly adjust production levels from its hydroelectric plants in response to market demands.
Norway’s electricity market is integrated within a broader Nordic electricity market together with Sweden, Finland and Denmark. This integration extends beyond the Nordics, with Norway being connected to the European electricity market through several interconnectors. These connections not only allow for the import and export of electricity but also contribute to the security of supply and the stabilisation of prices through increased market liquidity and competition.
This Nordic integration is facilitated through Nord Pool, which serves as a central hub for electricity trading in the region. The wholesale market in the region consists of several markets where bids are submitted and prices are determined:
Nord Pool operates a day-ahead market and intraday market. Nord Pool provides a physical trading platform for electricity, where spot prices are determined. NASDAQ Commodities and EEX offer financial trading instruments that are often based on the prices set at Nord Pool, allowing participants to manage price risk. Almost all physical trading of electricity takes place through Nord Pool; however, bilateral power purchase agreements (PPAs), especially long-term contracts, are also common. These bilateral agreements often use reference prices set at the power exchanges.
Price Formation
In the Norwegian wholesale electricity market, the price of electricity is determined by the interplay of supply and demand, with a strong emphasis on competitive offers from generators. The Norwegian market is liberalised, without heavy regulation or state intervention. Electricity producers submit their offers to the Nord Pool market, specifying how much electricity they are willing to supply and at what price. These offers are typically based on the producers’ operational costs and the availability of resources, such as water levels in reservoirs for hydroelectric plants, which dominate Norway’s energy mix.
On the demand side, retailers, industries and other consumers submit bids indicating how much electricity they are willing to purchase at various price points. Nord Pool’s role is to match these offers and bids and calculate the spot price.
The Norwegian wholesale market consists of five bid zones due to transmission constraints and bottlenecks. Nord Pool therefore calculates zonal prices that reflect local supply and demand. Norway’s extensive interconnections with neighbouring countries help stabilise prices by allowing excess electricity to be exported and shortages to be mitigated through imports.
Structure of the Wholesale Electricity Market
The participants in the Norwegian wholesale electricity market include generators, suppliers, traders and brokers, high-load consumers, the TSO (Statnett) and distribution system operators (DSOs). These participants participate at Nord Pool, NASDAQ Commodities and/or EEX. The market is divided into five bid zones and is also highly connected to neighbouring countries through several interconnectors.
High-Load Consumers in the Electricity Market
High-load consumers are addressed in Norway’s electricity market through a combination of market mechanisms, regulatory frameworks and tailored agreements.
Given Norway’s abundant renewable energy resources, low energy costs and sustainable energy system, its electricity market has become a favourable environment for power-demanding industries, such as aluminium production and data centres, in which companies balance operational needs with sustainability goals.
High-load consumers can participate in the electricity market by either purchasing electricity directly from the wholesale electricity market or by entering into long-term PPAs. PPAs are often entered into by industrial cornerstone companies with neighbouring renewable power plants, to secure stable electricity prices and supply for a longer period of time.
High-load consumers in Norway are further encouraged to participate in demand response programmes with the TSO or local DSOs by reducing or re-allocating electricity use during peak demand periods and offering flexible services, such as frequency regulation or reservation of capacity, in order to help balance the grid and reduce electricity costs in the market.
The Norwegian electricity market is part of the Nordic and European power market. Most Norwegian power is produced from hydropower. Norway is a power surplus country, meaning that in a normal year Norway exports power to its neighbouring countries.
Norway’s international electricity interconnectors consist of a total of 17 cables, including both overland power lines and subsea cables. Norway has a total of seven undersea power cables projecting to other countries; four of these go to Denmark. These cables are old and have a much lower capacity than the new “highways” that have been built to the UK and Germany. The total installed capacity of the interconnectors is over 9,000 MW as of 2022, according to the Norwegian Energy Regulatory Authority (NVE-RME). This provides the theoretical potential to transfer approximately 80 TWh/year between Norway and other jurisdictions. Norway has a total theoretical transfer capacity of around 30 TWh/year to non-Nordic countries, namely the Netherlands, Germany and the UK.
The division between the import and export of electricity to and from Norway varies from year to year based on weather conditions, etc. In the period 2003–19, the average annual import amount was 8.4 TWh, while the annual export amount was 15.2 TWh. In 2020, there was a lot of precipitation and full power reservoirs in Norway. In total, Norway exported 25 TWh of electricity in 2020 and imported 8 TWh. In 2021, the situation was quite the opposite, especially in southern Norway in the second half of the year. There was little wind and precipitation, extreme gas and coal prices, and a doubling of CO₂ quota prices. Despite lower reservoir levels, power exports increased by 3.4% compared to the previous year. In 2023, Norway exported approximately 30 TWh, at an average rate of 86 øre/kWh, and imported approximately 13 TWh at an average rate of 80 øre/kWh.
Power exchange with other jurisdictions is handled by the Norwegian TSO (Statnett). Power exchange requires a separate foreign trade licence. There is a joint licence for the Nordic countries, which also covers new connections and capacity increases. The connections to the Netherlands, Germany and the UK each have their own licence. Licences are granted pursuant to the Energy Act.
In 2024, Norway’s total electricity production was 157.8 TWh (installed capacity, 40,334 MW). The supply mix was as follows.
There are no limits with respect to the percentage of electricity supply controlled by any one entity in the Norwegian electricity supply market. However, Norwegian competition authorities encourage competition amongst the power producers as this is an important mechanism to achieve reasonable pricing for consumers of electricity. Producers compete based on their ability to deliver electricity. To ensure well-functioning competition, it is therefore important that individual players do not have too large a share of the total power production. General competition law, which prohibits anti-competitive behaviour, applies to the electricity market.
Norway has, as of end of May 2025, not implemented REMIT. Regarding the work aimed at Norwegian implementation of REMIT, a consultation was initiated by the Ministry of Energy on 17 March 2023, with a consultation deadline of 28 April 2023. It is not known when REMIT will formally be implemented into Norwegian law (as of May 2025). Even though REMIT is not yet formally implemented, many of its provisions are, per se, implemented through the Energy Act and its regulations, as well as through private law regulations in the marketplaces.
The NEM Regulation contains provisions on market behaviour and transparency in the power market.
The NVE-RME is closely integrated with the NVE, which also oversees the physical distribution of power as well as the neutrality of grid companies. Pursuant to the NEM Regulation, the NVE-RME oversees market behaviour and ensures transparency in the wholesale electricity market, especially concerning the trading of physical power. The NVE-RME may, pursuant to the NEM Regulation, for example:
Violations of the Energy Act and NEM Regulation may also lead to criminal liability and can be reported to the prosecuting authorities. The NVE-RME may also impose an infringement fee on anyone who intentionally or negligently violates some of the rules in the NEM Regulation.
The financial power market is monitored by the Financial Supervisory Authority of Norway (Finanstilsynet), which ensures compliance with financial market regulations. This includes EU financial market regulations, such as the Markets in Financial Instruments Directive (MiFID) II and the Market Abuse Regulation (MAR). The Financial Supervisory Authority’s supervisory powers are similar to those of NVE-RME, allowing it to effectively monitor financial activities. Additionally, the Norwegian Competition Authority has an overarching responsibility to ensure effective competition, including in the power market, and has a broad range of powers to enforce the Competition Act. Meanwhile, the Consumer Authority is responsible for regulating aspects related to the sale and marketing of energy to consumers. In addition, private law regulations prohibiting market manipulation and insider trading apply to participants in the marketplaces for power trading.
The principal laws that govern the construction and operation of generation facilities are as follows.
The Waterfall Rights Act (Vannfallrettighetsloven)
The developer must have the necessary rights to the waterfalls used in energy production. For entities others than the state, a licence is required for the acquisition of such rights. The Act does not apply to small-scale hydropower.
Licences under the Waterfall Rights Act can only be granted to public entities. Public entities cover Norwegian municipal, county or state corporations, and companies in which such corporations hold at least two-thirds of both the capital and the voting rights, provided that such companies are clearly publicly owned. Private companies may possess proprietary rights in such companies (up to one-third of the shares).
Leases of hydropower plants subject to licensing under the Waterfall Rights Act are regulated in the more detailed Regulations on the Lease of Hydropower Plants Act. The regulations lay down certain requirements for the content of the agreements. Agreements must be approved by the Ministry of Energy.
The Water Resources Act (Vannressursloven)
The purpose of the Water Resources Act is to ensure socially responsible use and management of watercourses and groundwater. Small-scale hydropower plants, not covered by the Watercourse Regulation Act, may need a licence under the Water Resources Act. There are no ownership restrictions.
The Watercourse Regulation Act (Vassdragsreguleringsloven)
When a regulation or transfer of water increases the quantity of natural horsepower in one or more waterfalls affected by 500 natural horsepower or more, or in the river system as a whole by 3,000 natural horsepower or more, or if the regulation affects the environment or public interests to a considerable extent, a licence pursuant to the Watercourse Regulation Act is required.
The Energy Act (Energiloven)
The Energy Act establishes the framework for how electricity supply is organised. The purpose of the Energy Act (see Section 1-2) is to ensure that the production, conversion, transmission, sale, distribution and use of energy is carried out in a societal, rational manner, considering the public and private interests affected. The building, owning and operating of electrical facilities (including generators, transformers and transmission lines) requires a licence pursuant to the Energy Act.
The Planning and Building Act (Plan- og bygningsloven)
Before the NVE can grant licences for onshore wind power plants pursuant to the Energy Act, a local planning decision pursuant to the Planning and Building Act, granted by the municipality, is required.
Following amendments to the regulation on the Energy Act in 2025, solar power facilities with a generating capacity of up to 10MWAC are only to be considered by the municipality in which the plant is located, under the Planning and Building Act. See also 1.6 Recent Changes in Law or Regulation.
The Expropriation Act and the Expropriation Compensation Act (Oreigningslova and Ekspropriasjonserstatningsloven)
All developers need to obtain the necessary rights to conduct their projects, such as land use and waterfall rights. Should such rights not be obtained through agreements, the company may apply for permission to expropriate. Expropriation is regulated in the Expropriation Act. The amount of compensation for acquiring such rights is subject to the Expropriation Compensation Act.
The Offshore Energy Act (Havenergiloven)
TheOffshore Energy Act governs offshore renewable energy production. Offshore renewable energy production requires that:
The Application Process
The licence application process starts with a notification to the NVE. The Planning and Building Act requires that an environmental impact assessment (EIA) be conducted if a project may have significant effects on the environment. The purpose of the EIA is to ensure that all possible effects of the project are taken into account during the preparation of plans and measures. Wind power plants exceeding 10 MW and hydropower plants with an annual production of 40 GWh or more always require an EIA.
In the notification, the developer describes the technical plans and the effects known at the time of the notification. The NVE will submit the notification to affected parties for consultation, including local municipalities.
Once the licence application has been prepared, it is submitted to affected parties for consultation. To be granted a licence, the advantages of the project to society must outweigh the disadvantages.
For large hydropower, the NVE submits a recommendation to the Ministry of Energy. The NVE’s recommendation is subject to a (limited) consultation before the Ministry presents the case before the Royal Council, which makes the final decision. Projects that comprise more than 20,000 natural horsepower, and projects that are considered particularly controversial, must be handled by the National Assembly before the Royal Council makes a (formal) decision.
The NVE has the authority to grant licences for installations according to the Energy Act, such as onshore wind power plants and solar power plants. Prior to the NVE’s handling of a licence application for an onshore wind power plant project, a positive local planning decision from the local municipality according to the Planning and Building Act is needed. This does not apply to any other power plants. The local planning decision follows the procedures laid out in the Planning and Building Act. A licence decision made by the NVE can be appealed to the Ministry of Energy, which makes the final decision.
For smaller hydropower – ie, plants with less than 10 MW installed capacity and limited regulation, the licensing procedures are simplified. After receiving a licence application, the NVE sends out a consultation letter to affected parties. To be granted a licence, the advantages must outweigh the disadvantages. The decision of the NVE may be appealed to the Ministry, which in turn makes the final decision.
Typical Terms and Conditions
A licence for the acquisition of waterfall rights (see the Waterfall Rights Act) typically includes conditions on licence fees and mandatory sales of power to the municipalities where the waterfalls are located.
Licences granted under the Watercourse Regulation Act contain manoeuvring regulations that establish parameters for water levels and releases. These include detailed provisions regarding the control mechanisms and procedures for reservoir drainage. Conditions stipulating minimum water flow in rivers and streams are determined based on a targeted assessment. Further, requirements for establishing a business development fund within the municipality where the development occurs may be imposed. The licences also contain the conditions of licence fees and mandatory sales of power to municipalities.
Licences under the Water Resources Act and the Energy Act also state the conditions and rules of operation. These conditions may include measures to secure a rational energy supply from the plant; provisions on the timing of initiation, construction, technical operations and terms of exploitation of the individual work; and conditions aiming to prevent or minimise damage to natural and cultural heritage. Individually adapted measures and conditions may be imposed if considered necessary.
Process to Obtain an Amendment or Relaxation of a Term/Condition
The process is as follows.
The process to obtain an amendment or relaxation of licences under the regulations mentioned in the foregoing follows the normal licence application procedures, as far as is deemed necessary.
Eminent domain, condemnation and expropriation constitute interference with the right to property. Therefore, the proponent, in the absence of an agreement, must apply for expropriation to the authorities. The authorities may only grant the approval if the legal conditions outlined in the Expropriation Act are met; the benefits of expropriation must outweigh the drawbacks.
The application for expropriation is typically submitted alongside the application for a construction and operation licence. The NVE, or the Ministry of Energy, will evaluate both the application for expropriation and the licence application simultaneously.
Every individual or entity subject to expropriation has a constitutional right to compensation. If the compensation cannot be agreed upon, it will be determined through a specific type of court proceeding. The compensation shall comprise the relinquishment of both the construction and operational work, as well as potential damage or inconvenience related to remaining properties. In accordance with the Expropriation Compensation Act, the compensation is determined based on the higher value between the selling price and the service value.
In the case of rights holders being subject to expropriation, such as reindeer grazing districts, the compensation is determined based on the loss suffered, which typically includes factors such as production loss and increased workload.
Hydropower Plants
If the state does not wish to take over a regulation facility regulated by the Water Regulation Act at the end of the licence period, and no new regulation licence is granted, the owner is obliged by order of the Ministry to remove the facility within a deadline set by the Ministry.
An owner of a watercourse facility regulated by the Water Resources Act has a duty of maintenance and responsibility for safety until the facility is shut down. The decommissioning of a watercourse facility is subject to licensing if it may cause significant damage or inconvenience to public interests. Decommissioning in any way other than removing the entire facility is always subject to licensing.
Onshore Wind and Solar Power
A wind power plant has a limited lifespan and must be decommissioned when the licence expires. The licence holder must fund the decommissioning. The NVE requires the licensee to submit a proposal for financial security by the end of the 12th year of the plant’s operation. The security must cover the costs of decommissioning to ensure that society is guaranteed available funds to decommission the power plant. The same conditions apply to solar power plants licences granted by the NVE.
The Norwegian grid system has three levels:
The principal laws that govern the ownership, construction and operation of transmission lines and associated facilities are the Energy Act and the Offshore Energy Act. Additionally, there are supplementary regulations that comprehensively regulate the system based on these legal acts.
The transmission grid is a nationwide system that connects consumers and producers across state borders. According to the Energy Act, only the appointed TSO can own and operate the transmission lines and associated facilities. Statnett is the TSO in Norway.
To construct and operate a specified installation, the Energy Act requires a licence from the authorities. This requirement stems from the fact that the electricity grid constitutes a natural monopoly. The licensing process aims to prevent exploitation of the monopoly position and ensure rational development and utilisation of the transmission system in the best interests of society.
When applying for a construction and operation licence, Statnett is required to review the consequences of the construction work and the operation of the power lines and associated facilities, such as transformation stations. EIAs play a crucial role in these evaluations. Additionally, the authorities place substantial emphasis on the environmental impacts when reviewing an application.
The regulatory process for obtaining the licence necessary for the construction and operation of transmission lines and associated facilities is both time-consuming and comprehensive. At a general level, the process may be summarised as follows.
When granting a licence to construct and operate a transmission line and associated facilities, the authorities normally impose various terms and conditions. Typical terms and conditions include the following:
The authorities may add additional terms and conditions to the approval at a later stage if deemed necessary due to fundamental interests.
The TSO, Statnett, may apply for an amendment or relaxation of a term or condition. The general rule is that the ordinary process for obtaining an approval, as described in 4.1 Constructing and Operating Transmission Lines and Associated Facilities and 4.2 Obtaining Approvals to Construct and Operate Transmission Lines and Associated Facilities, must be followed. However, if the amendments or relaxation requested are considered minor, the authorities may simplify the process.
Eminent domain, condemnation or expropriation rights are necessary for a proponent to undertake the construction and operation of electricity distribution facilities. The process and methodology for compensating affected property owners and rights-holders are equivalent to those described in 3.4 Eminent Domain, Condemnation and Expropriation Rights to Construct and Operate Generation Facilities.
In Norway, there is only one TSO, Statnett, which is wholly owned by the state. Statnett holds the exclusive right to construct, own and operate the transmission grid in order to provide transmission services. In addition to obtaining a licence, as described in 4.1 Constructing and Operating Transmission Lines and Associated Facilities and 4.2 Obtaining Approvals to Construct and Operate Transmission Lines and Associated Facilities, Statnett must comply with the regulations in the Public Procurement Act and the Public Procurement Regulation.
Considering the inherent nature of the transmission grid as a natural monopoly, the transmission charges and terms of service are thoroughly regulated. The NVE-RME sets an annual revenue cap for Statnett, which includes both costs related to grid operation and the system responsibility. The cap is determined so that the income generated over time covers the operational and depreciation costs of the installations, while also allowing for a reasonable return on investments assuming efficient operation, utilisation and development of the grid system. Further, Statnett is obligated to provide all services under non-discriminatory conditions, and in an objective manner, ensuring equal treatment for all parties involved.
Since the ability to own and operate the transmission grid is exclusively held by Statnett as the TSO, all grid services must be offered under non-discriminatory conditions and an objective basis. Consequently, Statnett is legally obliged to provide transmission services to all parties requesting transmission services within the legal framework for such services. This obligation includes, but is not limited to, an obligation to invest in the transmission facilities necessary to accommodate the requests.
As set out in 4.1 Constructing and Operating Transmission Lines and Associated Facilities, the Norwegian electricity grid system is structured into three levels. The principal laws that govern the construction and operation of electric distribution facilities are the Energy Act and the regulations derived from it, namely the Energy Act Regulation.
To construct and operate electric distribution facilities, the grid company must possess one of the two types of grid licence, and the licence must cover the relevant installations.
One type of licence is the area concession. Holding such a licence eliminates the need for individual approvals for each installation within the designated area. Area concessions are only applicable for installations carrying 22 kV or lower.
The other licence type is the licence to construct and operate specified electricity distribution facilities that are not covered by an area concession.
The regulatory application process for obtaining these licences is similar to the process for the transmission grid, as described in 4.2 Obtaining Approvals to Construct and Operate Transmission Lines and Associated Facilities: the public is invited to participate and provide input at several stages of the process, and the applicant is obligated to conduct a comprehensive EIA.
Applications are submitted to the NVE. If the installations hold less than 300 kV or are shorter than 20 km, the NVE may process the application. However, for installations exceeding these limits, the NVE provides a recommendation to the Ministry of Energy. The Ministry of Energy processes the application before the King in Council makes the decision.
The timeline for obtaining the necessary licences varies depending on factors such as the magnitude of the installations, the impacted areas and interests, and the thoroughness of the application and the EIA. Consequently, the timeline can range from a few months to several years.
The typical terms and conditions imposed on approvals to construct and operate electric distribution facilities are equivalent to those imposed for transmission grid licences (see 4.3 Terms and Conditions Imposed on Approvals to Construct and Operate a Transmission Line and Associated Facilities).
Eminent domain, condemnation or expropriation rights are necessary for a proponent to undertake the construction and operation of electricity distribution facilities. The process and methodology for compensating affected property owners and rights-holders are equivalent to those described in 3.4 Eminent Domain, Condemnation and Expropriation Rights to Construct and Operate Generation Facilities.
Electricity distribution entities possess, through necessary licences, exclusive rights to provide distribution services within specified geographical areas. Here, the reasoning is that the electricity distribution grid constitutes a natural monopoly, as construction and operation of multiple power lines and facilities within the same area, along with competition among the relevant distribution entities, would be inefficient.
Charges and terms of service for the electricity distribution system are regulated and established by the same provisions as for the transmission system (see 4.6 Transmission Charges and Terms of Service).
Each distribution entity is assigned an annual revenue cap, which is determined individually by the NVE-RME. The revenue cap decision may be appealed to the Energy Complaints Board.
The distribution entities set the charges that consumers must pay for grid system connection. While these charges may vary among entities due to geographical, technical and operational differences, they must be objective and offered under non-discriminatory conditions.
The NVE-RME supervises and enforces compliance with the regulations. It has the authority to issue orders for compliance and to impose sanctions – ie, in cases of discriminatory service conditions. Decisions made by the RME-NVE may be appealed to the Energy Complaints Board.
General terms and conditions set out in legislation are not subject to appeal and can only be amended through the regular legislative process.
Postboks 359 Sentrum
0101 Oslo
Norway
+47 22 43 30 00
post@haavind.no www.haavind.noIntroduction
Overview of the Norwegian power sector
The Norwegian power sector is, in general, highly regulated – particularly when it comes to hydropower activity, which has more than 100 years of history and still forms the backbone of Norway’s power system. Overall, Norway has stable legal frameworks, which is clearly one of the reasons why there have been so many foreign investments into the Norwegian power sector.
For the most part, foreign investors can invest in the Norwegian power sector without specific restrictions – at least when it comes to investments in wind power, small-scale hydropower, grid companies, district heating and other infrastructure relating to the power sector. The main exception to this is large hydropower, where non-public entities (including foreign entities) are not allowed to invest in and own more than one-third of a company that owns such assets. Public entities, being allowed to own such assets, are defined as entities owned and controlled by public authorities and/or undertakings (at least two-thirds).
One important aspect of Norwegian hydropower is that – to a large extent – it is characterised by a flexible production method, as it can be stored using water reservoirs. More than 75% of Norwegian hydropower production is rendered flexible through the use of reservoirs, which represents half of Europe’s total reservoir storage capacity. This is a perfect counterbalance to the increasing amount of non-flexible production, exemplified by wind and solar power.
Overview of energy policies
The main priorities of Norwegian energy policy include:
Back in 2021, Norway’s former government issued a white paper on the long-term value created by Norwegian energy resources, including – for the first time – both the renewables sector and the oil and gas sector. The white paper points out that the Norwegian oil and gas industry currently faces major challenges as a result of maturing fields on the Norwegian continental shelf and increasing demand for lower emissions. However, it emphasised that the oil and gas sector will remain a significant factor in the Norwegian economy for years to come – albeit not on the current scale. The use of expertise and technology within today’s oil and gas sector to develop new “green” industries and technologies is another important goal for the government, exemplified by the current development of offshore wind power on the Norwegian continental shelf.
In September 2024, the Norwegian government presented a white paper on the sustainable use and conservation of nature. The report is an action plan to ensure that society’s use of nature is sustainable, with the aim of reducing the degradation of nature. The government wants to promote efficient, climate and environmentally friendly and safe energy production, while managing nature in a sustainable manner. In instances where it is deemed appropriate for nature to yield, priority should be afforded to societal needs of particular importance, such as the generation of renewable energy. Steering signals for land use are also given in updated state planning guidelines.
The power situation in Norway and nearby markets has become more challenging in recent years, largely due to Russia’s invasion of Ukraine. To ensure a secure supply, and to facilitate energy transition and green industry, the government aims to increase renewable energy production, strengthen the grid and improve energy efficiency. Among the government’s main objectives are to continue implementing the green transition and to take action to achieve climate goals.
The integration of European energy regulations and Norway’s involvement with the Agency for the Cooperation of Energy Regulators (ACER) have sparked significant debate within Norway, particularly concerning the nation’s control over its energy policy and sovereignty. The discord within the government regarding the implementation of the EU’s Fourth Energy Market Package (“Clean Energy for all Europeans”) culminated in the departure of one of the coalition parties from the government in January 2025. In the wake of this political shift, the Norwegian government resolved to incorporate several key directives into the European Economic Area (EEA) Agreement, namely the Renewable Energy Directive (RED II), the Energy Efficiency Directive and the Energy Performance of Buildings Directive. These directives form part of the Clean Energy Package, which was adopted by the EU in 2018 and 2019, and are instrumental in advancing the EU’s energy and climate objectives.
Offshore Wind
In terms of developments, offshore wind is and will continue to be a major focus of attention in Norway. The Offshore Energy Act allows companies to apply for a licence to develop projects in appointed areas. Offshore renewable energy production requires that:
The government has appointed the current transmission system operator (TSO) for the Norwegian mainland, Statnett SF, as the TSO for the future grid infrastructure on the Norwegian Continental Shelf as well. The government has also announced that grid costs related to this future offshore grid will be borne by licensees rather than onshore grid customers.
The current tax regime does not regulate offshore wind specifically, which means that Norwegian companies will be liable to tax in accordance with the general tax rules. On 21 February 2022, the Ministry of Finance proposed a change to the Norwegian Tax Act, widening Norway’s taxation right on the Norwegian continental shelf to also cover foreign companies’ income from the production of energy from renewable resources, including offshore wind. The new rules entered into force in 2024, implying that foreign companies will generally become subject to the same tax rules as Norwegian companies. More information about taxation and financing are available online.
Southern North Sea II
The first large-scale, bottom-fixed Norwegian offshore wind area, Southern North Sea II (SN II), was awarded in March 2024. SN II’s first project phase will have a maximum developed capacity of 1,500 MW. A monetary auction with prequalified applicants was held on 29 March 2024. Ventyr SN II AS, owned by Parkwind and the Ingka Group, won the auction and will be the first to develop offshore wind in SN II. The winning bid in the auction was NOK115 øre/kWh, forming part of the contract for difference (CfD) that was later entered into between Ventyr SN II AS and the Norwegian state on 19 April 2024.
Utsira North
The Norwegian government opened three “project areas” within Utsira North (UN) for floating projects on 19 May 2025, each consisting of 500 MW. The Norwegian government intends to award the project areas in the first half of 2026. The deadline for applications to UN project areas is 15 September 2025. The government’s support scheme for UN amounts to NOK35 billion, and the notification process for the EFTA Surveillance Authority (ESA) was finalised, with approval from ESA, in April 2025. The players that are awarded the project areas within UN will have to apply for a licence pursuant to the Offshore Energy Act Section 3-1 and put forth a bank guarantee in order to participate in the competition for state aid. State aid will only be given to the project that requires the least amount of support in the competition for state aid. Several offshore wind players have already stated that they will not apply for the UN project areas, following increasing costs for offshore wind, and it remains to be seen how many applications for the UN projects areas the Ministry of Energy (MoE) will receive.
Further information on Norway’s offshore wind production can be found online.
Onshore Wind
As of July 2023, The Energy Act and the Planning and Building Act were amended with the aim of improving the licensing process for onshore wind projects. Before the Norwegian Water Resources and Energy Directorate (NVE) can conclude on a licence application pursuant to the Energy Act, an onshore wind project must secure a positive local planning decision from the relevant municipality. The objective is to strengthen the role of municipalities in the licensing process for onshore wind, to reduce the level of conflict, thereby laying the foundation for further expansion of onshore wind power, including by enhancing the power balance and achieving national climate goals.
Despite the legislative changes, there has not yet been a marked increase in the number of wind power projects reported to the NVE, or applied for. Nevertheless, there has been a noticeable uptick in activity, particularly in Finnmark, where the NVE approved study programmes for 11 new wind power projects in April 2025. However, several municipalities have adopted a principled stance against wind power plants within their jurisdictions, leading to rejections of such projects. This resistance highlights ongoing discussions regarding the need for further regulatory adjustments to address municipal concerns and facilitate project approvals. The balance between national objectives and local interests will be pivotal in shaping the future landscape of onshore wind energy in Norway.
Hydropower
Even though the vast majority of Norway’s hydropower potential has already been utilised, the NVE calculated in 2020 that the remaining hydropower potential was 23 TWh. Notwithstanding the potential for new builds, it is becoming increasingly important to upgrade existing hydropower plants – this is crucial not only to increase hydropower production in the energy mix, but also to maintain the production capacity of existing plants.
The higher electricity prices and the general energy crisis in Europe have led to several companies reassessing possible investments in projects that were shelved in recent decades. More volatile power prices result in an increased focus on capacity expansion and pumped-storage power plants.
Solar Power
Solar power currently constitutes a minor portion of the Norwegian energy system. The annual production for 2024 was approximately 517 GWh, accounting for about 0.2% of the total Norwegian power production. With the Norwegian Parliament’s ambitious goal of 8 TWh annual solar power production by 2030, significant activity is required in the next few years. However, in 2024 the newly installed capacity decreased by 45% compared to 2023. The majority of Norwegian solar power is building-integrated, and it is not a requirement to obtain a licence pursuant to the Energy Act in a market that is seemingly currently saturated.
Regarding larger solar power projects, the NVE has only granted ten licences. Three of the licensed facilities are operational, with a total installed capacity of 13.9 MWp. A further three of the licences have been appealed to the MoE. As of 19 May, the appeal has been rejected in one case, with the remaining two still under consideration.
Amendments to the Regulation on the Energy Act (Energilovforskriften), coming into force on 1 July 2025, will set the licensing threshold for solar power plants at 10 MWAC. Solar power facilities below the threshold are only subject to municipal processes. The amendment was presented as a move to free up resources at the NVE, as well as to ensure greater local self-determination of the development of solar power. The solar sector has also encountered familiar conflict from onshore wind power in relation to land use and encroachment on nature. Although less noisy, commercial-scale solar power is area-intensive. It remains to be seen whether the regulatory changes will contribute to faster and more efficient development of solar power.
Grid
General
There are several amendments and proposed amendments concerning grid regulations, against a background of increased demand for grid capacity along with slow development and investment in power lines, resulting in grid capacity becoming a scarce good. Additionally, the volatility in the energy market in recent years has prompted discussions about energy politics and thus the regulatory framework. The most important amendments and proposals are summarised in the following.
Mandatory maturity assessments
Amendments to regulations under the Energy Act (the Regulation on Network Regulation and the Energy Market, or the “NEM Regulation”; Forskrift om nettregulering og energimarkedet) concerning maturity assessments came into force on January 1, 2025. The amendments apply to requests for capacity exceeding 1 MW or requests for increased withdrawal exceeding the same threshold.
Under the new provisions, grid companies are now obligated to assess the maturity of projects when a request for capacity or increased capacity is submitted. The NEM Regulation provides a set of criteria that grid companies must evaluate. Additionally, grid companies may incorporate supplementary criteria in their assessments, provided these criteria adhere to regulatory requirements, namely the principle of objective and non-discriminatory practice. Based on the evaluation, grid companies may reserve a capacity volume for the project or prioritise the applicants/projects in a capacity queue based on the maturity level of each project.
To maintain reservations and their position in the capacity queue, grid customers must continuously document evidence of sufficient progress. Grid companies are required to solicit such documentation on a regular basis, and to continuously reassess project maturity. Should a grid company determine a material change or deviation in respect of meeting the maturity criteria, attributable to factors within the grid customer’s risk sphere, the company is required and entitled to withdraw their reservation or position in the capacity queue.
The amendments concerning maturity assessments apply to projects that received a reservation or a position in the capacity queue prior to 1 January 2025. This necessitates that grid companies must request documentation on maturity without undue delay, followed by a six-month deadline for grid customers to provide documentation. If the customer fails to meet this requirement, or if the grid company concludes that the project is immature, the reservation or position in the capacity queue will lapse.
Amendment to the Energy Act – more efficient licensing processes, etc
Various amendments to the Energy Act were recently approved by Parliament. Here, the major objectives are to reduce the processing time for obtaining the licences necessary for grid development and to ensure sufficient progress in both the application process and project execution. The amendments include the following, among others.
Extended threshold for submitting a notification to the NVE
Further, the government has recently enacted an amendment to the Regulation on Environmental Impact Assessments (KU-forskriften) concerning the requirements for submitting a notification for power lines to the NVE. The amendment increases the length of power lines that do not require notifications from 15 km to 50 km, while maintaining the voltage threshold at 132 kV.
Proposed amendments
The MoE has initiated a hearing concerning proposed amendments to the NEM Regulation, which introduce an obligation for grid companies to reserve/withhold capacity for withdrawal consumers within specified capacity thresholds; 1 MW in the regional grid and 5 MW (with expected annual consumption within 20 GWh) in the transmission grid. The proposal is intended to apply to all consumers within these limits. Connections must remain operationally sound, and grid companies must notify the Norwegian Energy Regulatory Authority (Reguleringsmyndigheten for energi, or the NVE-RME) if that is not the case.
The MoE has also initiated amendments to the NEM Regulation concerning operationally sound assessment and the ability to downgrade a grid customer’s maximum allowed withdrawal, under special circumstances, when the customer does not need the amount to be agreed upon in its entirety.
The proposed amendment for operationally sound assessments aims to make it mandatory for grid companies to publish assessments, and to establish and publish their principles in an easily accessible manner. With regard to the legal basis for grid companies to downgrade a customer’s maximum allowed withdrawal, the proposed amendment states that grid companies may downgrade only under special circumstances, and when the customer cannot substantiate the need for the full volume.
New Technologies and Innovation
Further digitalisation of the power sector
Digital innovations in the power sector are consistently enhancing operational efficiency, system maintenance, power supply reliability and preparedness. The advancement of digitalisation and the acquisition of higher-quality data not only refine the evidence base for investment decisions but also facilitate the automation of numerous decision-making processes. This shift necessitates the development of new regulations and business models, as well as adaptation on the part of customers. A prime example of this is the widespread implementation of smart metering, which has led to the installation of new equipment in approximately 99% of all metering points across Norway.
Hydrogen
The Norwegian government is actively working in line with its national hydrogen strategy, which supports the development of new hydrogen technology and projects. To date, several hydrogen production projects have been supported through the Hydrogen Hub Program under Enova, a state-owned enterprise supporting emission reduction projects and technologies on the path towards meeting Norway’s climate goals. The aim is to support the development of hydrogen production and distribution along the Norwegian coastal line to enable the maritime sector to use hydrogen as an alternative fuel.
Norway is specifically looking at how to utilise hydrogen to cut the country’s second-largest emission producer, the transport sector. The aim is to halve the current emissions from the transport sector and maritime transport by 2030. Hydrogen will be an important factor in achieving this goal. Therefore, Enova also has programmes supporting investments in hydrogen and ammonia technologies and systems onboard maritime vessels, to enable demand to increase in parallel with production.
Carbon capture and storage
The government’s carbon capture and storage (CCS) efforts are still to a large extent focused around the “Longship” project. Longship is a full-scale CCS demonstration project. It encompasses carbon capture from Norcem’s cement factory (400,000 tonnes of CO₂ per year) and from the waste incineration plant at Klemetsrud in Oslo, operated by Hafslund Celsio (350,000 tonnes of CO₂ per year). Further, Shell, Equinor and Total form part of the JV “Northern Lights”, who will deliver CO₂ transport and storage solutions for the project. The first volumes from Norcem are expected to be transported and stored in the offshore geological reservoir operated by Northern Lights this year. Through the Longship project, Norway anticipates that carbon removal will facilitate a reduction of emissions exceeding 1 million tons between 2025 and 2030.
In the wake of the Longship project, several new initiatives pertaining to both CO₂ storage and CO₂ capture are starting to accelerate. The MoE has issued 11 licences for the exploration of potential offshore geological formations for CO₂ storage. Through the EU Innovation Fund, the Havstjerne project, operated by Altera on the Norwegian continental shelf, has been granted more than NOK2 billion to support the development of a new CO₂ storage site. The authors also see many small-to-medium-scale initiatives for CO₂ capture moving forward in relation to construction, and initiatives to establish CO₂ hubs for transport and storage are emerging, enabling access to storage infrastructure (including for smaller volumes).
The Norwegian government is expected to present support mechanisms for further realisation of CO₂ capture in the national budget for 2026, and it is also continuing to work towards further refinement and development of the legal framework. A proposal for revised CO₂ storage regulation is expected to be presented in 2025.
Concluding Remarks
The Norwegian energy sector is developing rapidly, with the line between the traditional power/electricity sector and the oil and gas sector becoming increasingly blurred. This development is being driven by strong political impetus towards both further electrification (including of oil and gas installations) and the development of new and profitable industries such as (floating) offshore wind, hydrogen and CCS, as part of the necessary transition of Norway’s oil and gas industry. Norway has considerable ambitions within these new industries. The high electricity prices in recent years, combined with the energy crisis and the geopolitical situation in Europe, are also contributing to even faster development and more investments. Overall, there are strong indications that the development that is unfolding today will be further strengthened in the years to come.
Postboks 359 Sentrum
0101 Oslo
Norway
+47 22 43 30 00
post@haavind.no www.haavind.no