Contributed By Anderson Lloyd
Legal Framework
The principal laws governing New Zealand’s construction industry are found in statutes and common-law authorities. Common-law authorities from similar overseas jurisdictions are not binding in New Zealand, yet are often influential.
Key Statutes
Building Act 2004
This is the primary legislation governing the building industry. Its stated purpose is to provide that people can use buildings safely and without endangering their health. This act provides the legal framework for the building code, which sets out the standard required for buildings in New Zealand and guidance for how to meet those standards. The Building Act 2004 also contains minimum mandatory warranties for building work in relation to household units.
Construction Contracts Act 2002
This act is predominantly concerned with regular and timely payments between the parties to a construction contract, given the importance of cash flow for contractors. This act:
Health and Safety at Work Act 2015
This law outlines the standard needed at work sites to ensure personnel are safe. The Health and Safety at Work Act also controls how this standard is measured and enforced.
Resource Management Act 1991
This act promotes the sustainable management of natural and physical resources. A construction project may need a resource consent to develop or use natural and physical resources and/or carry out activities that affect the environment. If a consent is granted, it will impose conditions on such use or activities. The act regulates this process.
There are no mandatory contracts for construction projects in New Zealand. However, there are common and standard form New Zealand contracts for construction and for key construction consultants.
The New Zealand Standard (NZS) Series of Construction Contracts
The two most common standard form contracts for construction are provided by Standards New Zealand.
NZS 3910:2013 – Conditions of contract for building and civil engineering – Construction
This is a “construct-only” contract where the employer provides the design and the contractor is responsible for the construction component of the project.
NZS 3915:2005, which is a similar “construct-only” contract, is sometimes used instead of NZS 3910:2013 on projects where there is no “engineer” (see 2.1 The Employer).
NZS 3916:2013 – Conditions of contract for building and civil engineering – Design and construct
This is a “design-and-build” contract where the employer provides its requirements and the contractor is responsible for both the design and the construction of the project.
Design, which is the key distinction between NZS 3910:2013 and NZS 3916:2013, is discussed further in 3.3 Design.
Other Standard New Zealand Construction Contracts
Other standard form contracts that are found in New Zealand include the following.
The New Zealand Institute of Architects (NZIA) forms of contract
The Registered Master Builders Association forms of contract
Overseas Forms of Construction Contracts Commonly Used in New Zealand
Several overseas forms of contract are commonly used for construction projects in New Zealand, including:
Standard New Zealand Construction Consultancy Contracts
The most common forms of consultancy contract for construction professional services are:
Nature of Employers
The employer, also known as “the principal” in the NZS contracts, can be a wide range of persons, including:
Engineer as a Key Agent of Employers
The main NZS forms of contract includes the concept of “the engineer”, which is similar to the engineer in the FIDIC series of contracts.
Under the NZS 3910:2013 and NZS 3916:2013 contracts, the engineer administers the contract and has a dual role as an agent of the employer and a quasi-independent decision-maker. In the latter role, the engineer is expected to act fairly and impartially. Many of the roles of the employer referred to in this guide will actually be performed by the engineer (eg, issuing and assessing variations, confirming works are complete, etc).
General Rights and Responsibilities of Employers
Common rights
Common responsibilities
The Relationship Between Employers and Contractors
The employer and contractor will be the parties to the construction contract. The contractor is obliged to carry out the works specified in that contract and the employer is obliged to pay for those works in accordance with the contract.
It is also common for the employer to require security from the contractor to ensure the due, proper and punctual performance of the contractor’s obligations under the contract. This is usually achieved through a contractor’s performance bond or retentions from payments due to the contractor.
Once the contract is under way, the employer and contractor usually each have a single nominated representative to facilitate clear communication. For the employer, this is usually the engineer (or the engineer’s representative).
The Relationship Between Employers and Subcontractors
See 2.3 The Subcontractors.
The Relationship Between Employers and Financiers
See 2.4 The Financiers.
Nature of Contractors
There is significant variability in the size and nature of contractors commonly operating in New Zealand. Contractors range from large listed corporations (both local and overseas) to much smaller private companies. It is not unusual for larger projects in New Zealand to involve overseas organisations (often in a joint venture with local entities).
Common Rights and Responsibilities of Contractors
Common rights
Common responsibilities
Contractors are not relieved from their responsibilities to the employer if they subcontract works to third parties.
Relationship Between Contractors and Employers
See 2.1 The Employer.
Relationship Between Contractors and Subcontractors
See 2.3 The Subcontractors.
Relationship Between Contractors and Financiers
See 2.4 The Financiers.
Nature of Subcontractors
Subcontractors can be local, national or overseas entities. Subcontractors typically specialise in specific trades.
Common Rights and Responsibilities of Subcontractors
The rights and responsibilities of subcontractors are generally akin to the rights and responsibilities between a contractor and the employer. See 2.2 The Contractor.
Relationship Between Subcontractors and Employers
By default, due to privity of contract, the employer does not form a relationship with the contractor’s subcontractors. However, through its contract with the contractor, the employer typically places some controls on subcontracting, such as:
Moreover, it is not unusual for employers to have limited rights with regard to certain subcontract works by virtue of:
Relationship Between Subcontractors and Contractors
Subcontractors are engaged on a construction project through a subcontract with the contractor. It is customary for a contractor to engage a variety of subcontractors, each with a specific trade, on a single project.
A subcontractor’s scope of responsibility is generally limited to the work and risks outlined in its subcontract with the contractor. However, it is not uncommon for a contractor to seek to pass risks in its contract with the employer down to the relevant subcontractor.
Relationship Between Subcontractors and Financiers
See 2.4 The Financiers.
Nature of Financiers and the Financing of Projects in New Zealand
Financiers of construction projects in New Zealand tend to be local and foreign commercial banks, investment banks and institutional investors (such as pension funds). Multi-financier syndicates are common on larger projects.
Rights and Obligations of Financiers
Financiers are obliged to provide financing to the employer, but will not be party to the construction contract itself or otherwise have any direct obligations to the contractor. However, they may receive the benefit of undertakings from the contractor under a direct deed – as noted in the description of the relationship between financiers and contractors further on in this section.
In traditional construction financings, financiers take security over physical assets such as land and buildings, as well as over construction contracts and other material contracts such as sale agreements or leases. They may also receive the benefit of a guarantee from a parent company guaranteeing repayment of financing provided to its subsidiary and/or take security over the shares in the employer held by its shareholder.
In limited recourse project financings, the security package may be similar. However, the financiers will have a significantly enhanced focus on the cash flows arising from the operation of the completed project. Accordingly, they will exercise a much higher degree of diligence in assessing and monitoring matters arising under the construction contract and related contracts (such as completion guarantees), given that the achievement of completion under the construction contract will unlock the cash flow.
Relationship Between Financiers and Employers
The relationships between financiers and employers under construction projects are governed by the relevant finance and security documents. These will typically comprise a facility agreement and a general security agreement (providing for “all assets” security over the employer), as well as one or more specific security agreements – for example, providing for an assignment by way of security of specific project contracts or for security over the shareholder’s shares in the employer – and/or guarantees.
Relationship Between Financiers and Contractors
On financed projects it is common for a direct deed to be agreed between the financier, the employer and the contractor. A direct deed generally requires the contractor to:
Relationship Between Subcontractors and Financiers
It is rare for financiers and subcontractors to have a direct contractual relationship.
Sources and Descriptions of the Scope
The scope typically takes the form of:
Both requirements and specifications can also contain drawings setting out the locations, dimensions, forms and finishes required. Drawings are typically much more detailed in a construct-only contract.
Scope in Tenders
The employer will initially set out its requirement for the works (conventionally known as the “scope or specifications”) in a closed or open tender process. It is not uncommon for the contractor and employer to negotiate that scope (eg, to reduce the price) before the contract is finalised and executed.
Scope in Contracts
Once the contract is executed, the scope is generally fixed and can only be modified thereafter if – and to the extent – permitted by the terms of the contract itself (see 3.2 Variations).
Instructing Variations
The scope of an instructed variation tends to be at the sole discretion of the employer and, in NZS contracts, a variation is usually instructed by the engineer. In New Zealand, contracts typically permit the employer/engineer to:
Some events/circumstances are often variations, even though they do not arise from an instruction from the employer/engineer – for example, unforeseen ground conditions and archaeological discoveries.
Valuing Variations
The process for valuing variations differs across contracts. In New Zealand, particularly in NZS contracts, valuation is established by one of the following methods (in descending order of precedence):
Where rates do not include overheads and margins, or if the variation is valued on a net cost basis, allowances for overheads and margins are usually added.
Where variations prolong the works, time-related costs may apply (see 5.2 Delays).
In New Zealand, the two most common frameworks for allocating design responsibilities and risk are the following.
Construct Only
The contractor is responsible for its methodology of construction based on the design, but not for errors or omissions in the design itself.
Design and Construct
The contractor is responsible for both the design and the construction of the works (if the owner has a pre-existing design, it may be novated to the contractor).
The employer’s role in the construction itself is mostly limited to providing site access for the contractor and its subcontractors. However, the employer may be obliged to provide supplementary information/design clarification when requested by the contractor.
The contractor usually has the autonomy and primary obligation to:
Subcontractors are managed by the contractor and have a similar role to the contractor in respect of their subcontracted works.
The employer is responsible for making the site available to the contractor by a particular date for the purposes of performing the works.
In respect of the geotechnical site conditions, responsibility and risk can vary significantly by contract. Ordinarily, the employer will bear the risks of adverse conditions unless:
Contamination
Pre-existing contamination is usually the employer’s responsibility, whereas the contractor is responsible for ensuring that it does not contaminate or pollute the site in the course of construction.
Pollution and contamination are governed by the Resource Management Act 1991, the resource consent for the relevant project, and often local council guidelines.
Archaeological Finds
Archaeological discoveries, and any delays and additional costs caused by such discoveries, are mainly the employer’s responsibility.
Archaeological finds on a construction site are governed by the Heritage New Zealand Pouhere Taonga Act 2014, which requires that no person may modify or destroy a site if that person knows – or ought reasonably to have suspected – that the site is an archaeological site.
Common Permits
Responsibility for Permits
Arrangements for permits vary by contract. In most cases:
Most construction contracts exclude general maintenance obligations after completion. These become the employer’s responsibility.
Typically, the employer will either self-perform maintenance works or enter into separate maintenance service agreements with third parties for the proper operation and maintenance of the works. The NZS 3917:2013 fixed-term contract is available for such maintenance services.
For defects in construction works arising after practical completion, see 3.11 Defects and Defects Liability Period.
Finance and maintenance primarily sit outside the construction contract between the employer and the contractor. See 2.4 The Financiers and 3.7 Maintenance.
Some projects require key materials or equipment to be tested to ensure that they meet contractual or regulatory requirements.
The processes vary by contract. The contractor will typically give the employer notice of the date when it will be ready for such tests to be carried out. The contractor will then carry out the tests or arrange for the tests to be performed by specialists, with the employer having the right to attend (or to have an agent attend) such tests.
There are numerous potential testing types and stages, including:
Completion/Taking Over
Most standard forms set out a process for verifying/delineating when works are completed/taken over. In some contracts this can be a multi-stage process, including:
For construction contracts, the employer (or, more likely, its engineer) will typically inspect the works and issue a practical completion certificate, followed later by a final completion certificate, certifying the works meet the requirements of the contract.
However, there are also some actions (eg, taking possession and using the works before practical completion) that can result in the employer being deemed to have taken over the works.
Delivery
The term delivery is typically used for materials or equipment and is often linked to obligations to make payment and the transfer/allocation of risk or title.
In New Zealand, the point of delivery will usually be expressly stated in the contract. The International Chamber of Commerce’s Incoterms rules are not mandatory but are frequently referred to for international deliveries.
Most construction contracts have a limited period after the works are completed (typically ranging from a few months to one to two years), within which the contractor must remedy any snags/defects. This is known as a defects notification period (DNP). In addition, the employer will often require various standalone warranties for defects arising after the DNP.
Common standalone warranties relate to key materials/equipment remaining defect-free and the weather-tightness of the works. The NZS forms of contract include standard form warranties as a schedule to the main terms.
Defect Notification Periods
If a defect or fault emerges during a defect notification period as a result of defective workmanship or materials, the contractor is obliged to remedy the defect or fault. If the contractor does not remedy the works within a reasonable time, the employer may engage third parties to remedy the works and then recover the cost of doing so from the contractor.
Employers often retain some of the contract price as a retention until the end of the DNP, so as to incentivise the contractor to return to fix such defects (and thereby ensure the payment of the retentions to the contractor).
Statutory Warranties
Under the Building Act 2004, residential building work is covered by a ten-year warranty that building work will be carried out with reasonable care and skill – complying with plans and the building consent – and that the building materials will be suitable for the purpose for which they are to be used. Parties cannot contract out of this warranty.
Cost Structures
The following structures are among those used most frequently to price construction projects.
Payment Structures
In New Zealand, project payments tend to be based on either:
Advance Payments
Advance payments are common in New Zealand for long lead items and recently have been used more frequently as a means of locking in costs and reducing the risk of delays.
If materials are to be paid for before they arrive on site, separate agreements for offsite materials are often entered into to allocate the relevant risks and obligations. The NZS forms of contract include a standard form offsite material agreement as a schedule to the main terms.
Employers also often protect their interests in high-value advance payments by way of advance payment bonds.
Progress Payments
Typically, at regular intervals, the contractor submits a payment claim. The employer will then assess the claim and issue a payment schedule of amounts that it considers to be due.
Late Payments
Construction contracts in New Zealand generally include interest on late payments.
The Construction Contracts Act 2002 has default payment structures intended to ensure regular cash flow throughout the industry. If a qualifying payment claim/invoice (see 4.3 Invoicing) is not appropriately disputed in a payment schedule and is then late/unpaid, this law enables a contractor to:
Requirements for Tax Invoices
In New Zealand, an invoice will normally include:
Recommended Requirements for Construction Invoices
To benefit from the Construction Contracts Act (see 4.3 Payment), a payment claim/invoice should:
A payment claim must also be accompanied by an outline (in a prescribed form) of the process for responding to the claim and the consequences of not responding or paying the relevant amount.
Invoices issued after payment claims are mainly a formality to reflect the outcome of the payment claim and payment schedule process.
Role of, and Responsibility for, Construction Programmes
In New Zealand, a programme is usually prepared by the contractor at the outset of a project and it is often integral to setting up a project for success. The programme is often reviewed by the employer, who may provide comments/input, but good programming is ultimately the contractor’s responsibility.
Many contracts require the contractor to report against and update the programme regularly throughout the course of a project.
Standard Programme Requirements
Standard contractual requirements for a programme are that it should set out:
If a delay occurs, standard contracts in New Zealand include a process along the following lines:
There is an expectation in New Zealand that contractors will take reasonable measures to avoid potential delay events and mitigate delays if such events occur. In standard form contracts, failure to give notice can affect the contractor’s eligibility for extensions of time and variations if it deprives the employer of the opportunity to avoid or mitigate the delay.
Delay can cause additional cost for a contractor and loss for a principal. The responsibilities and remedies for such costs and losses (typically residing with the party responsible for those delays) and the applicable approach to concurrent delays, are described in 5.3 Remedies in the Event of Delays.
Contractor Delays
If the contractor is responsible for the delay, then contracts provide that the contractor:
Employer Delays
If the employer is responsible for the delay, then contracts ordinarily provide that the employer will:
Concurrent Delay
There is no single accepted definition of concurrent delay. However, the essence of concurrent delay is where the principal and the contractor each cause overlapping delay to the critical path of the works.
New Zealand courts are yet to address the issue of concurrent delay. Nonetheless, it is likely that they will adopt the approach set out in the High Court of England and Wales decision in Henry Boot Construction (UK) Ltd v Malmaison Hotel (Manchester) Ltd (1999) 70 Con LR 32. The Malmaison approach to concurrent delay is that the contractor is entitled to receive an extension of time for the full period of delay – but not prolongation costs – for the period of concurrency. However, in accordance with the principle of freedom of contract, the parties may agree to an alternative approach.
Contractors usually issue notices for extensions of time to the employer/engineer in writing.
Contractors are often required to set out the basis for an extension of time claim under the contract. Common grounds for an extension of time claim include:
In New Zealand, force majeure only applies if and to the extent that it is expressly included in the contract.
Force majeure clauses are not included in most New Zealand construction contracts as standard. However, most standard form contracts include some degree of relief for events that would usually be considered force majeure events and force majeure clauses are occasionally added to standard form contracts as special conditions.
Force majeure clauses may suspend or excuse the non-performance of contractual obligations for the duration of the effect of the force majeure event. They may also permit termination of the contract if the effect of the force majeure event extends beyond an agreed duration.
Relief for unforeseen circumstances is normally only available if it is included in the contract. However, New Zealand recognises the common-law concept of frustration, which can apply in some instances of unforeseen circumstances. Frustration is grounds for termination under the NZS 3910:2013 and NZS 3916:2013 contracts.
In standard form contracts in New Zealand, a contractor is entitled to additional time for unforeseen circumstances but not necessarily additional costs.
Disruption is an interruption to or hindrance of a contractor’s intended methodology, resulting in loss of productivity and efficiency. Disruption is recognised as a concept in New Zealand, but disruption claims and associated remedies are only available if allowed for under the particular contract and if the requirements of that contract have been met.
There is no universal method for demonstrating disruption. However, a popular method is the “measured mile” approach, whereby a contractor demonstrates the productivity it was capable of in portions of the project/site that did not experience disruption and then causally links a disruptive event with the lesser productivity achieved in the affected portion of the works.
Productivity-based approaches, which often use comparative projects and industry standards to establish achievable baselines “but for” the disruption, are also recognised. Alternative cost-based methods – whereby contractors compare estimated costs with actual costs – are possible but comparatively difficult to causally link with disruptive events, owing to the potential for tender insufficiency as an alternative cause.
Warranties under the Building Act 2004 cannot be contracted out of for residential construction. On policy grounds, a person cannot exclude liability for their own fraud.
The concepts of wilful misconduct and gross negligence are not well-established in the New Zealand courts. However, where contracts include limitations on liability (see 6.3 Limitation of Liability), such clauses often seek to ensure that any limitation of liability does not apply if the contractor engages in wilful misconduct or gross negligence.
Consumer Contracts
In consumer contracts in New Zealand, limitations of liability are restricted by the Consumer Guarantees Act 1993. By way of an example, a contractor cannot limit its liability for completing construction with reasonable skill and care, so that it is fit for purpose and on time or within a reasonable timeframe.
Commercial Contracts
In CBL Insurance Ltd (Liq) v Harris [2021] NZHC 1393, the High Court confirmed that clear limits of liability are enforceable in commercial contracts in New Zealand. Limitations of liability are not included in New Zealand’s most common standard form contracts; however, it is not unusual for parties to add such clauses.
Parties are mostly free to negotiate indemnities subject to policy restrictions – for example, not indemnifying certain court issued fines and penalties. Standard form contracts in New Zealand typically include indemnities:
It is not uncommon for parties to agree to further indemnities (to the extent permitted by law) for:
There are no mandatory guarantees in New Zealand. However, there are several forms of performance guarantee that are used frequently in the New Zealand market, such as bonds and parent company guarantees.
Bonds
Standard form contracts in New Zealand anticipate performance bonds. These may be provided by the principal to the contractor or by the contractor to the principal.
Parent Company Guarantees
If the contractor is a subsidiary and/or has limited assets, the employer may require (and financiers will usually expect) performance to be assured by way of a guarantee from a parent company.
In the NZS forms of contract, there are four types of insurances that are usually taken out by the parties:
However, it is not uncommon for other insurances (eg, marine cargo insurance) to be taken out where the specific project involves relevant risks.
Under most contracts in New Zealand, the insolvency of a party permits the other party to terminate the contract. The insolvency of the contractor also permits the employer to resume possession of the site.
Risk-sharing arrangements are not particularly common in New Zealand and are most often found in alliance agreements or target cost arrangements (see 4.1 Contract Price).
The orthodox approach regarding risk in New Zealand is to allocate the risk to the party who is best placed to control that risk. Alternatively, a party may accept additional risk in return for a price premium (if accepted by the contractor) or reduction (if accepted by the employer).
Employers frequently require the contractor to:
The standard NZS construction contract prohibits a contractor from subcontracting the whole or substantially the whole works. Subcontracting generally requires the employer’s consent. Subcontracting does not relieve the contractor from any liability or contractual obligations owed to the employer under the contract.
Typically, the employer and the contractor will each retain their IP rights but grant licences to the other to the extent necessary for the project. Rights over new IP that may result from the work under a contract are negotiated and vary significantly. One common approach is shared ownership of the new IP with cross-licences. It is not uncommon for parties to agree indemnities for infringement of third-party IP rights.
Contract law in New Zealand recognises general damages for breach of contract. Sufficiently serious breaches of contract may also entitle a party to terminate the contract.
Common Employer Remedies
Common employer remedies include:
Common Contractor Remedies
Common contractor remedies include:
For further details of restricting remedies, see 6.1 Exclusion of Liability, 6.3 Limitation of Liability, 9.3 Sole Remedy Clauses and 9.4 Excluded Damages.
Parties often limit the duration of some liabilities. Liability under consultancy contacts, for example, is typically limited to six years from the date on which the services were completed.
Sole remedy clauses are not included in the standard NZS construction contracts but are enforceable in commercial contracts. Where a contract provides for delay liquidated damages, this will typically be considered the sole remedy for delay.
It is not unusual for commercial parties in New Zealand to exclude liability for:
Retentions
Retentions are permitted and commonplace in New Zealand construction contracts. Employers are required to hold retention monies on trust for the contractor under the Construction Contracts Act. Further requirements, such as holding retentions in a separate and compliant bank account in New Zealand and regularly reporting on those retentions, will come into force on 5 October 2023.
Suspension Rights
Contractors have statutory suspension rights for non-payment but, under the NZS forms of contract, are not usually permitted to suspend works owing to a dispute.
The power to terminate a construction contract, and the associated remedy, depends on the particular contract terms. Construction contracts in New Zealand usually permit termination for frustration and default, with the types of default enabling termination mainly being aligned with the obligations of each party.
Contractor Default
For contractors, events that may result in termination include:
Termination for contractor default ordinarily results in the principal being entitled to expel the contractor from the site and to have the works completed by third parties, with additional costs being recoverable from the contractor.
Some construction contracts also permit the principal to terminate the contract at its convenience. Such clauses may entitle the contractor to payment for completed works and under-recovered costs, as well as an allowance for lost profit.
Principal Default
For principals, events that may result in termination include:
Termination for principal default traditionally results in the contractor being entitled to payment for completed works and under-recovered costs, as well as an allowance for lost profits.
Termination Pre-requisites and Wrongful Termination
Most construction contracts in New Zealand require the terminating party to notify the defaulting party of the default and to provide an opportunity for the defaulting party to remedy the default within a contractually mandated period of time. If the default is not remedied, then the terminating party may proceed with termination.
New Zealand also recognises the concept of wrongful termination if a party purports to terminate the contract without a valid basis for doing so or without following the contractually required process, which can result in damages.
Courts
In New Zealand, four tiers of court may hear construction disputes. In descending order, they are:
Adjudication
In New Zealand, parties may not contract out of the adjudication process, which is set out in the Construction Contracts Act. Adjudication is a relatively swift but interim dispute resolution process that takes place entirely by way of written submissions. There are no hearings.
Adjudication decisions are binding and any awards must be paid within two working days of award. Notwithstanding the obligation to pay, parties may then proceed to litigation or arbitration for final determination of the dispute. Adjudications are determined by a single adjudicator from a recognised institution.
Recognised Institutions
In New Zealand, there are several institutions recognised as competent to appoint persons to hear construction disputes as adjudicators or arbitrators. These include:
The following private and alternative dispute resolution options are recognised in New Zealand.
Level 3
Australis Nathan Building
37 Galway Street
Britomart
Auckland 1010
New Zealand
+64 9 338 8300
+64 9 337 1115
lawyers@al.nz www.al.nz