Norway has no dedicated construction legislation. Construction law is instead founded on the principle of freedom of contract, whereby the parties themselves largely determine the terms of the project through their contractual arrangements. In practice, this means that standard contracts developed by the industry – particularly the NS series – serve as the principal framework governing the majority of construction and civil engineering projects; see further at 1.2 Standard Contracts.
Background Law
Where the contract is silent or ambiguous, it is supplemented by background law. The Sale of Goods Act 1988 (kjøpsloven) constitutes the most significant source of background law in commercial construction relationships between professional parties. The Act provides guidance for the interpretation and supplementation of contractual terms. In addition, general principles of construction law, developed through case law and legal scholarship, play an important role where the contract does not provide an answer.
Key Legislation
Several statutes affect the execution of construction and civil engineering projects in practice. The Planning and Building Act (plan- og bygningsloven) regulates building matters, permits and responsibility designations. The Working Environment Act (arbeidsmiljøloven) imposes requirements relating to health, safety and the environment, as well as working conditions on construction sites. The Pollution Control Act (forurensningsloven) establishes the framework for the management of contaminated land and emissions, while the Cultural Heritage Act (kulturminneloven) imposes obligations to halt work and notify the authorities upon discovery of automatically protected cultural heritage sites. The Limitation Act (foreldelsesloven) prescribes the general time limits for the enforcement of claims, including a supplementary one-year period in cases of latent defects. With respect to dispute resolution, reference is made to the Arbitration Act (voldgiftsloven) and the Dispute Act (tvisteloven), which are discussed further in 10. Dispute Resolution.
Direct links to selected legislation (published on Lovdata) are as follows:
Norwegian construction and civil engineering practice relies largely on standard contracts. The most widely used are:
NS 8406/8416 (simplified construction contract) is commonly used in smaller projects. It is more condensed, with less stringent notification provisions. FIDIC is primarily encountered in projects with an international profile.
Development and Legal Status
The use of standard contracts is not prescribed by law but reflects long-standing market practice. The NS contracts are developed by Standards Norway (Standard Norge) through broadly composed committees with representatives from the employer, contractor and consultant sides, which gives them the character of negotiated, balanced documents and explains their strong standing as a basis for interpretation by the courts. In HR-2026-780-A, the Supreme Court held that deviations from the NS standard must be made expressly and visibly in the contract’s ranked documents, and that an unclear reference to a party’s own standard terms is not sufficient to set aside the regulation of the standard.
Offshore Contracts
In offshore supplies, the NF/NTK family of contracts is used, which is based on knock-for-knock principles and ad hoc arbitration. NTK 25 replaced NTK 15 at the turn of 2025/2026 through a limited revision addressing ESG requirements and sanctions regulation.
Recent Developments
The most significant development in 2026 is NS 8408, a design-and-build standard for large and complex civil engineering projects. The standard draws elements from NS 8407 and the NTK family, featuring an NTK-inspired variation order system and new provisions on ground conditions risk that provide a better basis for pricing and reduce disputes.
Integrated Project Delivery
Partnering contracts has gained increasing prevalence, particularly in public projects, with a typical two-phase structure where the parties jointly develop the design basis (phase I) and agree on a target price with shared bonus/malus for the remaining works (phase II). There is no Norwegian standard, but contract proposals developed by the Enterprise Federation of Norway (EBA) and templates prepared by public employers are used in practice; see also 7.5 Risk Sharing.
Contractual Architecture
The contractual relationships mirror the architecture of the standards: employer–contractor in NS 8405/8406/8407, designer–client in NS 8401/8402, and contractor–subcontractor in NS 8415/8416/8417, the latter with extensive back-to-back adaptation to the main contracts.
Construction and civil engineering projects in Norway are carried out by both public and private employers. On the public side, state entities such as Statsbygg, the Norwegian Public Roads Administration, Nye Veier, and Bane NOR are among the largest clients, together with municipalities and county authorities. Public employers are subject to the Public Procurement Act and the Public Procurement Regulation, which impose requirements relating to competition, procedure and award criteria. On the private side, employers range from large property developers and industrial companies to smaller local developers.
Rights and Obligations
The employer’s fundamental right is to receive performance in conformity with the contract within the agreed time and free from defects. The scope of the employer’s obligations depends on the procurement model, and in particular on whether the employer or the contractor bears responsibility for design; see 1.2 Standard Contracts.
Under the standard contracts, the employer’s core obligations include, inter alia:
The employer normally bears the risk for ground conditions, and shall also co-ordinate with any side contractors, issue and respond to variation orders, and generally co-operate loyally in the execution of the project. See further in 3.2 Variations, 3.10 Completion, Takeover and Delivery, 4.3 Payment and 9.5 Retention and Suspension Rights.
Relationship With Subcontractors and Financiers
The employer has a direct contractual relationship with its contractors but normally has no contractual relationship with the subcontractors. Claims between the employer and a subcontractor must therefore, generally, be pursued through the contractual chain, unless separate direct agreements have been entered into. Financiers are likewise not party to the construction contract; their rights and obligations are governed by separate financing agreements. In larger PPP projects, however, direct agreements between lenders, the employer, and the contractor may secure step-in rights in the event of default; see 2.4 The Financiers.
Contractors in the Norwegian market comprise large national and international operators, regional construction firms, and specialised trade contractors in areas such as groundworks and concrete, HVAC, electrical and technical installations. Several of the largest contractors are listed companies with operations across the Nordic region. The market includes both companies that undertake design-and-build contracts and companies that exclusively perform specialised trade works as subcontractors.
Rights and Obligations
The contractor’s central right is to receive the agreed remuneration on time, together with extensions of time and additional payment in the event of variations to the contract works. The scope of the contractor’s obligations depends on the procurement model: the design-and-build contractor bears overall responsibility for both design and execution under NS 8407/NS 8408, whereas the construction contractor performs the works in accordance with the employer’s design under NS 8405.
Regardless of the model, the contractor must execute and complete the contract works in accordance with the agreed requirements and industry practice within the agreed timeframe. The contractor must remedy defects during the defects liability period, which is normally five years, and must notify the employer of errors in specifications, discrepancies in the design basis, and unexpected ground conditions. In addition, the contractor must provide the agreed insurances and securities; see 7.2 Guarantees and 7.3 Insurance.
Relationship With Subcontractors and Financiers
The contractor has a direct contractual relationship with the employer and bears full responsibility for the performance of its subcontractors vis-à-vis the employer. Subcontractors are engaged at the contractor’s own responsibility and risk, and the employer normally has no direct claims against them. The contractor likewise has no direct relationship with the project’s financiers; the role of the financiers is limited to their contractual relationship with the employer; see 2.4 The Financiers. For the contractor’s relationship with subcontractors, see also 2.3 The Subcontractors; for final settlement and limitation periods for legal proceedings, see 4.4 Invoicing and 10.1 Regular Dispute Resolution.
Subcontractors in the Norwegian market comprise both general contracting firms and specialised trade contractors in areas such as plumbing, electrical, ventilation, groundworks, concrete, painting and similar trades. In large projects, the main contractor may have a considerable number of subcontractors engaged beneath it.
Rights and Obligations
The contractual relationship between the main contractor and the subcontractor is normally governed by NS 8415 (construction subcontract), NS 8416 (simplified construction subcontract) or NS 8417 (design-and-build subcontract). The subcontractor’s central right is to receive the agreed remuneration on time, together with extensions of time and additional payment in the event of variations. The subcontractor’s obligations include executing and completing the works in accordance with the agreed requirements within the agreed timeframe, notifying the main contractor of deviations and impediments, and remedying defects during the defects liability period.
Back-to-Back Arrangements
Subcontracts are typically entered into on a back-to-back basis against the main contract, so that the terms largely mirror the obligations the main contractor has assumed vis-à-vis the employer. The concept is, however, not precisely defined in Norwegian contractual practice, and effective risk allocation requires express regulation of which provisions are actually mirrored. It is particularly important that notification periods in the subcontract are shorter than those in the main contract, and that provisions on risk allocation, variation management and limitations of liability are harmonised throughout the entire contractual chain. Paid-if-paid clauses are not entirely uncommon but may be considered unreasonable and consequently interpreted restrictively by the courts where the subcontractor’s rights are not adequately safeguarded.
Relationship With the Employer and Financiers
The subcontractor normally has no direct contractual relationship with the employer. Claims must, as a general rule, be pursued through the contractual chain via the main contractor, unless separate direct agreements have been entered into. The subcontractor likewise has no relationship with the project’s financiers. Consistent management of deadlines and notification requirements throughout the entire chain is essential to avoid the loss of claims; see also 10.1 Regular Dispute Resolution regarding the eight-month time limit.
The financing of construction projects is ordinarily provided by commercial banks, institutional investors, and public-sector bodies. The financier stands outside the construction contract and holds neither rights nor obligations arising from it. The exception is larger PPP projects, where direct agreements may grant lenders step-in rights in the event of default. For guarantees and securities, see 7.2 Guarantees to 7.4 Insolvency.
Design professionals play a key role in Norwegian construction law, as the allocation of design responsibility is one of the most dispute-generating issues in the industry. Design professionals include architects, consulting engineers, multidisciplinary consultancy firms, and specialised technical practices. In public projects, municipal or state specialist bodies may also perform design functions.
Contractual Position
The contractual position of the design professional changes fundamentally depending on the procurement model. In construction contracts, the design professional has a direct contractual relationship with the employer under NS 8401 (consultancy services at a fixed fee) or NS 8402 (assistance engagements). In design-and-build contracts, the design professional is engaged as a subconsultant to the contractor, using the same standard contracts.
Rights and Obligations
The core tasks of the design professional include developing the design basis, preparing drawings and specifications, and ensuring that the proposed solutions comply with public requirements and standards. The design professional’s central right is to receive the agreed remuneration, together with additional payment in the event of changes to the scope of the engagement.
The basis of liability is professional negligence, meaning that the consultant is assessed against whether the work has been performed with professionally sound care and diligence. The contracts contain limitations on the scope of liability (approximately NOK20 million for insurable liability) and exclude liability for indirect losses.
Professional Indemnity Insurance
The design professional’s professional liability is in practice covered by insurance, but the insurance terms may contain specific limitations – for example, where the consultant acts as a subconsultant to a design-and-build contractor (the so-called design-and-build exclusion). This may create a gap between the contractual liability the design-and-build contractor has assumed vis-à-vis the employer and the insurance coverage the consultant is able to offer. See further on insurance under 7.3 Insurance. For notification of defects and limitation periods, see 3.11 Defects and Defects Liability Period.
The scope of the works is described through functional requirements and/or detailed specifications depending on the procurement model, often structured using NS 3420 and associated description systems to ensure unambiguity in quantities and qualities. In design-and-build contracts, functional requirements with performance-based descriptions predominate, whereas construction contracts are based on detailed drawings, descriptions and bills of quantities provided by the employer.
Programme requirements, room schedules and any BIM deliverables are set out in contract appendices and form the basis for the management of variations and deviations; see 3.2 Variations. The choice of description method affects the allocation of risk, pricing methodology and the documentation available for the final settlement.
Variations are typically initiated by a written order from the employer in accordance with the contract’s variation provisions, with price adjustment and extension of time to the extent the variation affects cost and time. Under NS 8405 and NS 8407, the employer may not, without agreement, order variations representing more than 15% net addition to the contract sum.
The Supreme Court’s decision in HR-2025-977-A clarifies that NS 8407 operates a dual-track system for the calculation of the 15% threshold for variations: the concept of “variation” applies only to orders that entail a deviation from the contractor’s obligations under the contract. Unforeseen additional work required to achieve the contract’s requirements may be at the employer’s risk. This will typically include unforeseen ground conditions. Such additional work entitles the contractor to a price adjustment, but it is nevertheless not counted towards the 15% threshold, as it is not defined as a “variation”.
Irregular Variation Orders
Where the employer issues instructions that in substance constitute variations without following the formal variation order procedures (so-called irregular variation orders), the contractor is also obliged to carry out the work but must notify the employer without undue delay if the instruction is invoked as a variation. The notification obligation is mutual: the contractor may forfeit the right to additional payment in the event of late notification, and the employer may forfeit the right to contest the variation if objections are not raised within the contractual time limits.
Contractor-Initiated Claims
The contractor does not have a general right to demand variations but may submit claims for additional payment and extensions of time where circumstances within the employer’s sphere of risk affect the performance – for example, errors in the employer’s design, unforeseen ground conditions, or delayed deliveries on the part of the employer. The requirement of timely notification applies equally as a prerequisite for such claims.
Pricing of Variations and Time-Related Costs
The price for variations is determined either by agreed unit rates, cost-plus (time and materials) or an agreed new price. Time-related costs (costs associated with prolonged construction time) are priced separately, and in larger projects fixed formulae for the calculation of such costs are often agreed, entitling the contractor to automatic compensation upon extension of time. Schedule impacts shall be reflected in an updated programme with documentation of cause and effect; see 5.2 Delays to 5.4 Extension of Time.
The NS 8408 Variation Order System
The traditional variation order system described above has been radically restructured in the new standard NS 8408, which follows a system known from the NTK contracts (offshore construction).
Design responsibility rests with the employer in construction contracts (NS 8405), whereas the design-and-build contractor bears responsibility for design in design-and-build contracts (NS 8407/NS 8408), including co-ordination of consultants and disciplines.
In practice, shared design responsibility also occurs, typically where the employer provides a preliminary design or programme of requirements and the design-and-build contractor carries out the detailed design. The interface between the two is a classic source of disputes, and precise contractual regulation of the transfer of responsibility is essential.
Liability for Design Errors
Liability for design errors is borne by the party carrying design responsibility, with professional negligence as the basis of liability for consultants and strict performance liability for the design-and-build contractor vis-à-vis the employer. Independent verification and the system of responsibility under the Planning and Building Act entail separate roles (responsible applicant, responsible designer, responsible constructor and responsible verifier) that affect interfaces and regulatory supervision.
Complex Projects Under NS 8408
In large civil engineering projects under NS 8408, the variation and collaboration mechanisms are further developed to manage complex design and interfaces during the early phases of the project.
The division of responsibility in the construction process depends on the procurement model. In divided contracts (employer-managed), the employer contracts directly with several side contractors and bears the co-ordination responsibility itself, often through an engaged construction manager or project manager. In general contracts, a single main contractor assumes co-ordination responsibility for the subcontractors, while the employer retains responsibility for design. In design-and-build contracts, the contractor bears the most comprehensive responsibility – encompassing design, execution, progress and management of the entire subcontract portfolio.
Roles of Subcontractors, the Employer and the HSE Co-Ordinator
Subcontractors carry out specialised works under the main contractor’s direction and co-ordination. The employer, for its part, contributes decisions, access to the construction site, permits and supervisory functions. In addition, the employer is required by law to appoint an HSE co-ordinator (health, safety and the working environment) responsible for safeguarding safety on the construction site throughout the project.
Testing, Commissioning and Takeover
Testing, commissioning and takeover procedures should be incorporated into the progress schedule with clear milestones and takeover criteria; see 3.9 Tests, 3.10 Completion, Takeover and Delivery and 5.1 Planning and Programme.
The allocation of risk for ground conditions is contractually governed and follows the fundamental principle that the contractor bears the risk for conditions it had reason to anticipate at the time of tender, while the employer bears the remaining risk. The assessment depends to a large extent on the information that was available during the tender phase: the tender documents will normally contain information on pollution, underground obstacles, geotechnical conditions and any archaeological finds. The employer is obliged to provide all known information regarding ground conditions of relevance to the contractor, and incorrect information is, as a general rule, at the employer’s risk. The contractor, for its part, must carry out a diligent inspection of the site and, under NS 8407, obtain available information on cables, pipes and other ground conditions.
Differences Between the Standard Contracts
There are important nuances between the standards. Under NS 8405, the design responsibility rests with the employer, who consequently bears the greater part of the ground conditions risk. Under NS 8407, the contractor is subject to a more extensive duty of investigation prior to submission of the tender, and it may be agreed that the risk of unforeseen ground conditions is allocated to the design-and-build contractor (except for material deviations) – a solution that is also prevalent among large public employers.
NS 8408 introduces an adjusted risk regime tailored to large civil engineering projects, with a clearer allocation of who shall procure ground investigations, what information shall be made available at the time of tender, and how deviations from the assumptions shall be notified and managed contractually. The aim is to provide the contractor with a more predictable basis for pricing risk and to reduce the number of disputes concerning ground conditions.
Mandatory Regulation
Regardless of the contractual regime, mandatory regulation applies in respect of archaeological finds and pollution: the Cultural Heritage Act triggers an obligation to halt work and notify the authorities upon discovery of automatically protected cultural heritage sites, while the Pollution Control Act governs the management of contaminated land; see also 1.1 Governing Law.
The building permit process under the Planning and Building Act normally requires a framework permit, a commencement permit, a temporary occupancy permit and a completion certificate. This is governed by statute and cannot be derogated from by the parties. The Planning and Building Act also establishes a system of responsibility roles:
Allocation of Responsibility for Permits
In practice, it is the employer, through the responsible applicant, who obtains the framework permit. The contractor normally assists with the commencement permit, the temporary occupancy permit and the completion certificate. In the absence of any other agreement, the risk that the necessary permits are in place on time rests with the employer.
Sector-Specific Permits
For major energy and infrastructure projects, additional sector-specific permits may be required – for example, a licence under the Energy Act for wind power and power line projects, a permit under the Harbour and Fairways Act for works at sea, or a discharge permit under the Pollution Control Act. Responsibility for such permits rests, as a starting point, with the employer.
Maintenance works typically encompass ongoing operation, preventative measures, and repair of damage not attributable to defects. Following takeover, the employer is responsible for maintenance. The parties may agree on a trial operation period; NS 6450 establishes processes for commissioning and trial operation to ensure that technical installations function as planned.
Separate Maintenance Contracts
In certain sectors, particularly infrastructure and energy, the contractor may assume maintenance obligations for an agreed period following takeover under separate service or maintenance contracts.
Operation, financing and ownership of the completed works are normally not regulated in the construction contract. The exception is public-private partnerships (PPPs), where a private party undertakes to finance, construct, operate and maintain the infrastructure for an agreed concession period before transfer to the public sector.
Testing and commissioning typically follow a staged process comprising factory tests, on-site tests, mechanical completion, functional testing and performance tests. Roles, procedures and acceptance criteria are regulated in the contract and associated appendices, and should correspond with the conditions set out in the takeover protocol; see 3.10 Completion, Takeover and Delivery.
Responsibilities of the Contractor and the Employer
The contractor bears the primary responsibility in the testing process. It is the contractor who plans, carries out and documents the tests, and who bears the cost and risk of failed tests until takeover. If a test is not passed, the contractor must remedy the deficiency and re-test at its own cost until the acceptance criteria are met.
The employer’s role is to make the necessary infrastructure available for testing – for example, power, water and access to the facility – as well as to participate in or approve test procedures and to accept or reject the test results. In projects involving technical installations, testing and takeover often proceed in stages, and detailed test procedures with clear acceptance criteria for each stage are recommended.
In Norwegian construction law, the takeover inspection constitutes the central point at which the contract works are deemed delivered from the contractor to the employer. In HR-2026-965-A, the Supreme Court held that takeover under the standard contracts may, as a starting point, only occur through a formal takeover inspection in accordance with the contract’s provisions, and that the employer’s use of the contract works does not in itself constitute takeover. There is accordingly no separate delivery stage distinct from takeover – completion, takeover and delivery are in practice parts of one continuous process.
Completion and the Takeover Inspection
Completion entails that the contractor has finished the contract works in accordance with the agreement, that the necessary tests have been passed (see 3.9 Tests) and that the required documentation is in place. Once these conditions are satisfied, the contractor shall summon the employer in writing to a takeover inspection. At the takeover inspection, minutes are recorded identifying those present, listing any defects with a deadline for remediation, and stating whether the contract works have been taken over or refused with reasons.
Legal Effects of Takeover
Takeover triggers several key legal effects. The employer obtains the right to put the contract works into use, and the risk of loss of and damage to the contract works passes to the employer. Liquidated damages (a pre-agreed daily amount for delay) cease to accrue. The contractor’s security is reduced from 10% to 3% of the contract sum with effect for three years, the defects liability period commences, and the final settlement process is triggered with deadlines for the final account and final invoice.
Partial Takeover and Unjustified Refusal
Partial takeover may be agreed for identified parts of the contract works and affects remuneration, deadlines and the scope of the guarantee for the part taken over. If the employer unjustifiably refuses to take over, the contractor may demand that takeover be established, with consequential effects for risk, liquidated damages and final settlement.
The notification periods for defects are contractually agreed and may be derogated from by the parties. In order to pursue a claim for defects, the employer must under all Norwegian standard contracts notify the contractor of the defect within a short time after the defect was or ought to have been discovered. In addition, the notification must be made within the maximum notification period for defects, which is normally five years from takeover. If the notification periods have been exceeded, the employer’s claim is forfeited unless the defect is attributable to wilful misconduct or gross negligence. For parts of the contract works that have been remedied, a new five-year period runs from completion of the remediation, limited to a maximum of one year beyond the original period.
Limitation Periods
In addition, the employer must comply with the Limitation Act, which is mandatory. The Act prescribes a general limitation period of three years from takeover, with a supplementary one-year period for latent defects running from the time the employer obtained or ought to have obtained knowledge of the defect. Limitation may accordingly occur before the expiry of the notification period, and the employer must ensure that limitation is interrupted in parallel, if necessary, by commencing legal proceedings or entering into an agreement to extend the period. If the period is exceeded, the claim is forfeited.
Remedies Before and After Takeover
Prior to takeover, the contractor’s duty to remedy defects is strict and linked to contractual performance. Following takeover, the primary remedy is rectification within a reasonable time, provided that the costs are not disproportionate in relation to the result the rectification would achieve. Where rectification is not appropriate, the employer may instead claim a price reduction or damages. In the event of material breach, the contract may as a last resort be terminated.
The contract price is normally established through a tender process in which the employer invites tenders and the contractor prices the works based on the tender documents. The most common forms of remuneration are fixed price, unit rates, cost-plus (time and materials) and target price. In partnering contracts, a target price combined with bonus/malus is frequently used, meaning a bonus to the contractor if the final cost falls below the target price, and reduced compensation in the event of an overrun. The forms of remuneration may also be combined within one and the same contract.
Components of the Contract Price
The contract sum is typically broken down into site establishment and running costs, materials, labour, and provisions and profit. The parties support this with a payment schedule setting out when the various components fall due.
Milestone Payments
Milestone payments are common in Norwegian construction contracts. The parties typically agree that portions of the remuneration fall due upon the achievement of defined milestones, in addition to ongoing monthly instalments based on documented progress. See further on payment under 4.3 Payment.
Price indexation is common and is typically carried out on the basis of indices published by Statistics Norway (SSB), which cover various project types, including indices for apartment buildings, timber-framed detached houses, road works and pipelines, enabling the parties to select the index that best reflects the cost composition of the project in question.
Contractual Mechanisms
Most standard contracts contain price adjustment clauses linking price elements to an index according to an agreed method, unless otherwise agreed. The total index method entails that the contract sum is adjusted based on the movement in the chosen index from an agreed base month (normally the month of the tender deadline) to the month of execution, typically with quarterly or monthly settlements.
Derogation and Extraordinary Price Fluctuations
Price indexation may also be agreed as a fixed amount, or alternatively excluded altogether – for example, in market conditions with a short execution period or low-price volatility. Extraordinary price fluctuations falling outside the normal scope of index regulation must, if applicable, be addressed through separate contractual mechanisms.
Invoiced amounts ordinarily fall due within 28 calendar days of receipt, and the standard contracts provide for interest on late payment in accordance with the Interest on Overdue Payments Act. The rate of interest on late payment is set by the Ministry of Finance every six months and is 12% as of the first half of 2026. Advance payments are common and normally require security in the form of a bank guarantee.
Retention and Withholding
Under NS 8405, NS 8406 and NS 8407, the employer may withhold an agreed proportion of the invoiced amount as retention, which does not fall due until the final settlement. The employer may also withhold further payment where legitimate counterclaims exist.
Suspension for Non-Payment
In the event of material payment default by the employer, the contractor may suspend performance provided that prior written notice has been given affording the employer a cure period of not less than 24 hours. A justified suspension entitles the contractor to an extension of time and compensation.
Documentation Requirements
For an invoice to be deemed due and trigger interest on late payment, it must comply with the contract’s documentation requirements to enable the employer to verify the claim. The employer must, for its part, object before the due date if the documentation is considered insufficient.
Ongoing invoicing is normally carried out on a monthly basis on the strength of documented works performed. Under NS 8405, NS 8406 and NS 8407, invoices must be paid within 28 days of receipt. For an invoice to be deemed due and trigger interest on late payment, it must comply with the contract’s documentation requirements to enable the employer to verify the claim. The employer must, for its part, object before the due date if the documentation is considered insufficient.
Final Settlement
The final settlement follows detailed procedural rules designed to ensure verifiability and to preclude subsequent claims. The contractor shall normally submit the final account and final invoice within two months of takeover. The final account shall contain a comprehensive overview of all claims, including the original contract sum, agreed and disputed variations, index regulation, retention and any counterclaims.
The employer must raise objections within two months of receipt of the final account. Claims not included in the final account, or objections not raised within the deadline, may as a general rule not be pursued subsequently. Both parties forfeit the right to claims and objections that are not submitted in due time. The final settlement thus functions as a definitive settlement point binding on both parties. Disputed claims are subject to an eight-month time limit for commencing legal proceedings calculated from takeover; failure to comply may result in forfeiture of the claim; see 10.1 Regular Dispute Resolution. Under NS 8408, this applies to all unpaid claims.
Under NS 8405 and NS 8407, the contractor must submit a progress schedule within four or six weeks of the conclusion of the contract. The schedule must as a minimum cover the contractor’s main activities and activities upon which the contractor is dependent, including works carried out by the employer’s other contractors. In larger projects, detailed planning requirements at multiple levels are often agreed, comprising a contract baseline, detailed schedules, and associated reporting and documentation requirements.
Monitoring and Revision
The contractor is under a continuing obligation to inform the employer of actual progress and to notify the employer of material deviations from the schedule. In the event of material deviations, the contractor must submit a revised schedule. Planning is normally structured around a critical path – that is, the longest chain of dependent activities determining the project’s completion date – so that both the parties and any disputes can be related to the activities that actually affect completion.
The Employer’s Role
The employer contributes to the planning process through decisions, access, permits and clarifications that are prerequisites for planned progression. The employer normally approves the progress schedule and must itself meet its own milestones, including delivery of design, permits and access to the construction site.
Milestones and Milestone Payments
Milestones are common in Norwegian construction contracts and are used both as a management tool and as a contractual basis for sanctions. The parties may agree that milestones are subject to liquidated damages (0.1% of the contract sum per working day, capped at 10%); see 5.3 Remedies in the Event of Delays.
Milestone payments are also common, with portions of the remuneration falling due upon documented achievement of defined milestones; see 4.1 Contract Price. Certificates in the traditional FIDIC sense are not normally used in Norwegian practice, but documentation of milestone achievement serves an equivalent function.
In the event of delays, both parties are obliged to notify the other party without undue delay. Timely notification is a prerequisite for preserving the right to an extension of time; failure to notify or late notification may result in forfeiture of the claim.
Extensions of Time and Additional Payment
Delay attributable to variations or circumstances within the employer’s sphere of risk may entitle the contractor to an extension of time and additional payment. Correspondingly, the employer may be entitled to an extension of time where the contractor obstructs the employer’s co-operation.
Time-Related Costs and Liquidated Damages
In the event of delays, the contractor’s claim for price adjustment may include increased time-related costs (costs associated with prolonged construction time); see further in 3.2 Variations. Where there is no basis for an extension of time, the delay constitutes a breach of contract and the employer’s primary sanction is liquidated damages; see 5.3 Remedies in the Event of Delays.
Concurrent Delays
In cases of concurrent or parallel delays, where the parties are each responsible for their respective cause, it is a disputed question how the contractor’s entitlement to an extension of time and compensation should be calculated. Case law is to some extent inconsistent. There are examples of the contractor being relieved of liquidated damages but losing the right to price adjustment for prolonged construction time. Alternatively, a proportionate allocation of both liquidated damages and price adjustment may also be applied.
The employer’s remedies in the event of delay by the contractor are liquidated damages, damages for excess loss in cases of gross negligence or wilful misconduct, and termination in the event of material breach, including where it is clear that material delay will occur.
Rates and Caps
Under NS 8405, NS 8406 and NS 8407, daily liquidated damages accrue at a rate of 0.1% of the contract sum for each working day of delay, subject to an overall ceiling of 10% of the contract sum. The employer’s entitlement to liquidated damages is not conditional upon proof of actual financial loss.
Interim Deadlines and Agreed Deviations
The final deadline is, as a general rule, subject to liquidated damages, but the parties may also agree on interim deadlines linked to milestones that are likewise subject to liquidated damages. The parties may agree on different rates and caps. In the event of wilful misconduct or gross negligence on the part of the contractor’s senior personnel, the employer may instead claim damages for the full documented delay loss in excess of the liquidated damages. Cumulation and caps in respect of direct and indirect losses are addressed in 9.4 Excluded Damages to 9.6 Termination.
Under all the standard contracts, the contractor is entitled to an extension of time in the event of variations, delays or deficiencies in the employer’s performance, and other circumstances within the employer’s sphere of risk.
Procedure and Measurement
Claims are submitted by written notification without undue delay, and the extension of time shall correspond to the actual and necessary impact of the impediment on the critical path. Account shall be taken of concurrent delays, necessary stoppage periods, and any shift to a more or less favourable season.
The contractor bears the burden of proof for both the grounds and the extent of the claim on the balance of probabilities. Procedural and preclusion rules require loyal and timely handling in order to preserve claims.
Acceleration
Where the parties disagree on an extension of time, acceleration may be a means of recovering lost time. Acceleration may occur in three forms.
Instructed acceleration entails that the employer instructs the contractor to accelerate the works and bears the additional costs where the delay is attributable to circumstances within the employer’s sphere of risk.
Voluntary acceleration entails that the contractor accelerates on its own initiative in order to avoid liquidated damages and itself bears the risk of the additional costs.
Defensive acceleration gives the contractor a limited right to accelerate at the employer’s expense where the parties are unable to agree on an extension of time, provided that the acceleration costs do not exceed a specified level. This mechanism provides the contractor with an alternative course of action where the extension of time claim is disputed.
Force majeure is recognised as a general principle of Norwegian contract law. Under the NS contracts, force majeure captures external circumstances such as exceptional climatic events, regulatory prohibitions and industrial action. Relief requires that:
Consequences
Neither party is treated as being in default. An extension of time is granted, but price adjustment is not normally available. The affected party must notify the other party without undue delay.
Unforeseen circumstances are primarily addressed contractually through risk allocation rules in the standard contracts, which allocate risk for specific circumstances such as unforeseen ground conditions (see 3.5 Site) and changes in public requirements. Hardship clauses may provide a negotiation mechanism. In exceptional cases, Section 36 of the Contracts Act may be invoked, but the threshold is very high in commercial relationships. Unforeseen circumstances may also qualify as force majeure; see 5.5 Force Majeure.
Disruption is recognised as a ground for claims for both extension of time and compensation where the causes are attributable to the employer and are sufficiently documented.
NS 8405 and NS 8407 expressly provide that “reduced productivity” may constitute a basis for additional payment. The Supreme Court’s decision in HR-2019-1225-A (HAB) clarifies the evidentiary requirements: the contractor must individualise the specific events, document which work operations have been affected and during which periods and demonstrate on the balance of probabilities that the consequences have in fact resulted in the alleged additional costs. Globally calculated claims are not normally accepted. General experience and norm-based calculations may be a factor in the assessment of the loss but are alone not normally sufficient to document productivity loss in the specific project.
Relationship to Extension of Time
Claims for extension of time must in principle be based on the underlying cause that has created the disruption or reduced productivity. NS 8405 and NS 8407 provide that the cumulative effect of previously notified variations and events must also be taken into account when assessing the schedule impact, so that accumulated variations and employer-related impediments may collectively form the basis for time compensation.
Norwegian law precludes contractual exclusion of liability for criminal liability, personal injury, product liability under mandatory statutory regimes, and duties arising under international conventions. The standard contracts do not limit liability by means of general caps but regulate indirect losses; see 9.4 Excluded Damages.
Wilful misconduct and gross negligence are central concepts that override agreed limitations of liability. The standard contracts provide that limitations and notification periods do not apply in such cases.
Pursuant to the principle of freedom of contract, the parties are free to agree on liability caps and other limitations. NS 8405 and NS 8407 do not contain a general liability cap, but in practice the parties frequently agree on differentiated limitations, including exclusion of indirect losses, liquidated damages as the specific and exclusive remedy for delay, and special clauses for particular risks.
It is primarily the contractor’s and the design professional’s liability that is limited in practice – through liability caps, caps on liquidated damages (normally 10% of the contract sum) and exclusion of indirect losses. The employer’s liability is less frequently limited but may also be circumscribed contractually.
Norwegian courts and arbitral tribunals will, generally, uphold agreed limitations of liability. The limitations may, however, be set aside where the loss is attributable to wilful misconduct or gross negligence on the part of the responsible party’s senior personnel; see 6.2 Wilful Misconduct and Gross Negligence.
Indemnity clauses are uncommon in the NS contracts. Risk is instead allocated through the standards’ other liability and compensation provisions. Offshore and energy contracts, by contrast, frequently employ knock-for-knock arrangements with mutual hold-harmless obligations for each party’s own personnel and property.
Bank guarantees and parent company guarantees are commonly agreed in order to secure performance.
Contractor’s Security
Under NS 8405 and NS 8407, the contractor’s default obligation is to furnish security corresponding to 10% of the agreed contract sum throughout the execution phase, stepping down to 3% upon takeover for a residual guarantee period of three years. On-demand guarantees, under which the guarantor may not invoke the contractor’s objections, are not required under the standard contracts. Requirements for such guarantees may nevertheless be encountered in larger projects and/or international contexts. Parent company guarantees may be required where the contractor is a subsidiary.
Employer’s Security
Under NS 8405 and NS 8407, the employer is in principle required to post reciprocal security of 15% or 17.5% of the contract sum. In practice, this obligation is frequently waived for employers of established financial standing, and the NS standards expressly exempt publicly owned entities from the requirement. The amounts and duration are co-ordinated with progress, takeover and the defects liability period, and the handling of claims follows the contractual formalities. Direct agreements may supplement the security package in financed projects.
The contracts allocate insurance obligations for construction/works insurance, liability insurance, and project and operational risk. Alignment between contractual liability and insurance coverage is expected, but care should always be taken to verify that the insurer does not impose limitations that reduce coverage beyond what the contract provides for.
Contractor’s Insurance
Under NS 8405 and NS 8407, the contractor shall keep materials and works insured until takeover, with the employer as co-insured. In larger projects, the employer frequently takes out a CAR/EAR (contractor’s all risks/erection all risks) policy under which the contractor is co-insured.
Employer’s Insurance and Workers’ Compensation
In addition, the employer is required to take out occupational injury insurance for its own personnel pursuant to the requirements of the Working Environment Act. Insurance typically covers physical damage (fire, theft, natural perils) and third-party liability.
Professional Indemnity Insurance
The professional liability of design professionals is insured separately; see further in 2.5 The Designer.
Both parties have the right to terminate in the event of the other party’s insolvency. The employer’s right is excluded where performance will continue or satisfactory security is furnished. The insolvency estate retains a statutory right of assumption under the Satisfaction of Claims Act. The security mechanisms of the standard contracts (guarantees, retention) mitigate the performance risk.
Target price and partnering models share cost and gain deviations in defined percentages to incentivise joint optimisation. There is no Norwegian standard for partnering contracts, but contract proposals developed by the Enterprise Federation of Norway (EBA) are used in practice; see 1.2 Standard Contracts. Simpler target price mechanisms with bonus/malus are more prevalent than full-scale alliance agreements.
Each party shall appoint a representative with authority to act bindingly. The contractor may not replace key personnel without the employer’s consent, which may not be withheld without justifiable cause. The contracts also impose HSE compliance requirements.
The contractor must normally notify the employer or obtain the employer’s consent to the engagement or replacement of subcontractors, and remains fully liable for the subcontractors’ performance vis-à-vis the employer. Where reasonable grounds exist, the employer is entitled to refuse approval of a proposed subcontractor, provided that written notice of refusal is given promptly and in any event within 14 days of receiving the relevant particulars concerning the subcontractor.
In tender processes, the employer frequently requires tenderers to name key subcontractors in the tender and may limit the number of subcontractors, resulting in a pre-approved list of suppliers. The contractual chain must handle deadlines, notification and variation rules consistently in order to avoid gaps in chains of claims.
The employer is granted a right of use of design material for the completion, operation, maintenance and modification of the works, while the design professional normally retains the copyright to its own ideas and material.
In the event of a breach of contract, the parties have recourse to the classical remedies: rectification, price reduction, damages and termination in the event of material breach. The employer may also withhold payment within the agreed framework.
Notification as a Prerequisite
A prerequisite for pursuing remedies is that timely notification is given within the contractual deadlines (often “without undue delay” or “within a reasonable time”). Failure to comply with the notification periods will normally result in forfeiture of the claim. The contractor’s remedies in the event of default by the employer include, inter alia:
Other Breaches and Professional Liability
For breaches other than delay or defects, the aggrieved party may as a starting point claim damages for documented loss in accordance with general principles of contract law. For design professionals, professional negligence applies, with rectification and damages within the framework of the contract.
The standard contracts limit remedies by excluding indirect losses, capping liquidated damages, and requiring timely notification as a prerequisite for claims. Courts will uphold agreed limitations unless the loss is attributable to wilful misconduct or gross negligence.
The NS contracts operate on a sole remedy basis for delay and defects; additional damages may only be claimed in cases of wilful misconduct or gross negligence. Termination may be invoked in the event of material breach.
Indirect losses are frequently excluded. Claims for damages primarily cover direct costs, while indirect losses are reserved for cases of wilful misconduct or gross negligence. The offshore standards typically contain mutual indemnities for indirect losses.
The right to withhold payment is recognised in Norwegian background law and is also reflected in the standard contracts. The employer may, at its own risk, withhold sufficient payment to secure a legitimate specified counterclaim against the contractor.
Contractor’s Right to Suspend
The contractor has a right to suspend the works in the event of material payment default under NS 8405 and NS 8407. Suspension requires written advance notice with a 24-hour deadline for the employer to pay, and a justified suspension entitles the contractor to time and cost compensation. An unjustified suspension may give rise to liability for damages.
Employer’s Right to Suspend
The employer’s right to suspend the works is not provided for in NS 8405 or NS 8407. Employers that require the ability to suspend the works should therefore include an express suspension clause in the contract. The offshore standards contain a suspension clause under which the contractor is entitled to additional payment and an extension of time and may terminate the affected part of the contract if the works are not resumed within 120 days.
Termination may be effected in the event of material breach following notification and a deadline for rectification, and results in the release of both parties from future contractual obligations. The contractor is entitled to compensation for works performed.
Consequences of Termination
Where the employer rightfully terminates, the employer is entitled to recovery of necessary additional costs and foreseeable loss resulting from the termination. Where the contractor rightfully terminates, the contractor is entitled to recovery of additional costs, including demobilisation and winding-up costs, as well as lost profit on the part of the works not carried out.
Cancellation by the Employer
The employer further has the right to cancel all or part of the works. Under NS 8405, NS 8406 and NS 8407, the contractor is in such cases entitled to compensation for its loss resulting from the cancellation.
The ordinary courts have jurisdiction unless otherwise agreed. The Dispute Act governs the procedure, and the court structure comprises the District Court, the Court of Appeal and the Supreme Court. The venue is, as a starting point, the judicial district in which the construction or civil engineering works are carried out, unless otherwise agreed. Under NS 8405/8415, disputes involving amounts in excess of approximately NOK13 million (as of 2026) shall be resolved by arbitration, in which case the Arbitration Act governs the procedure.
The Eight-Month Time Limit
Under NS 8405/8415, NS 8407/8417 and NS 8408/8418, a practically critical time limit of eight months from takeover applies for commencing legal proceedings; failure to comply may result in forfeiture of the contractor’s or subcontractor’s claim. The takeover date for the subcontract and the main contract normally coincides, so that the eight-month time limit also coincides, which may create significant risk for the main contractor if an unexpected subcontractor claim is brought close to the deadline. This must be managed contractually in the subcontract chain.
Limitation Periods
The limitation periods under the Limitation Act also apply; see 3.11 Defects and Defects Liability Period.
Under the standard contracts, disputes should first be attempted to be resolved amicably. Court-facilitated mediation, conducted by a sitting judge once pleadings have been exchanged, in practice represents the single most effective mechanism for resolving construction disputes in Norway, with a substantial proportion of cases reaching settlement at this stage. Out-of-court mediation with party-appointed mediators is also frequently used.
Project-Integrated Mediation and Expert Determination
NS 8407 and NS 8408 provide for project-integrated mediation (PRIME), under which a mediation panel assists the parties in resolving disputes on a continuing basis during the contract period. The standards also provide for expert determination, in which an independent expert renders an advisory decision that becomes binding if both parties accept it within one month. Even where the decision has not become binding, it shall in many cases nevertheless be complied with until it is set aside by agreement or by a court or arbitral tribunal. The mechanism provides a rapid means of resolving disputed claims during the project.
Arbitration
Norwegian arbitration law follows the UNCITRAL Model Law framework. An arbitral award is final and binding, there is no right of appeal on the merits, and a challenge on procedural grounds (invalidity action) faces a stringent threshold. Both NOMA and the OCC administer institutional arbitration proceedings, with fast-track procedures and mediation services also available.
The offshore standards provide, as a general rule, for ad hoc arbitration, whereas onshore contracts normally follow court proceedings unless arbitration has been agreed. Arbitration is the default for disputes under NS 8405/8415 exceeding approximately NOK13 million (as of 2026).
Cort Adelers gate 33
PB 1829 Vika
0123 Oslo
Norway
+47 22814500
post@sands.no www.sands.no/
General Introduction
The past year has in many ways been challenging for the Norwegian construction and civil engineering industry. After a period of increased activity following COVID-19, the market has seen a steady decline since the third quarter of 2022. This trend continued in 2025.
The downturn has been driven in particular by lower levels of privately initiated residential construction. Costs for key input factors have increased, and the industry has seen a high number of bankruptcies. In addition, capital costs have remained relatively high, with continued uncertainty surrounding the central bank’s future interest rate policy.
Uncertainty relating to tariffs, war, sanctions and disruptions in global supply chains has also dampened investment appetite. ESG remains a major focus area, which creates further complexity in projects. The combination of challenging framework conditions and significant uncertainty indicates that 2026 will also be a relatively weak year for the Norwegian construction and civil engineering industry, although a moderate improvement may be expected.
As always, broader market trends will influence which legal issues receive increased attention. Below, we outline some developments from the past year, supplemented by predictions for the year ahead.
New Standard Contract NS 8408 and Increased Focus on Standardisation
The Norwegian construction and civil engineering market makes extensive use of standard contracts. These contracts are negotiated by committees consisting of representatives from industry organisations and the public sector, and they are generally considered to be relatively balanced. The use of standard contracts makes risk easier to manage for both parties in a project, as the provisions of the standard are incorporated into internal procedures and project methodology.
There is also a substantial body of case law clarifying issues of interpretation. At the same time, it is not uncommon for the parties to agree on special terms. Deviations from the standard may in many cases simply be improvements tailored to the specific project, but they will often shift the allocation of risk between the parties. This is particularly visible in public construction and civil engineering contracts, where the employer often sets the contract terms unilaterally, and the contractor risks being excluded from the tender if it takes reservations against those terms.
In spring 2026, Norway’s Minister of Trade and Industry encouraged public contracting authorities to make greater use of standard contracts instead of applying unbalanced special terms. According to the statement, this would reduce risk and increase predictability for an already pressured contractor market. The statement does not specify which special provisions should be avoided. As one example, however, it is reasonable to expect employers to make a more detailed assessment of the allocation of risk for long lead time items and the choice of index. Uncertainty in supply chains and cost increases for key input factors can affect contractors severely, and it should not be assumed automatically that contractors must bear this risk themselves.
It is unclear to what extent Norwegian public contracting authorities have followed the Minister’s encouragement. However, it is reasonable to expect some movement towards more standardised contracts for public projects in 2026 and beyond.
2025 also saw the launch of a new standard contract. NS 8408 has been developed specifically for large and complex turnkey contracts in civil engineering projects, while the related NS 8418 applies to subcontracts in the same types of projects. The standard is undoubtedly the most specialised contract in the Norwegian Standard series for construction and civil engineering. It has a relatively narrow scope, but addresses a specific and clearly identified need.
The largest projects in Norway often use standard contracts based on NS 8407, but with significant amendments to reflect the need for more detailed project management, risk management, handling of variations and dispute resolution. NS 8408 is intended precisely for these types of projects, although its scope is limited to civil engineering. The contract contains several innovations that also reflect broader market trends in recent years. Among other things, it places increased emphasis on co-operation and collaborative working, particularly in the start-up phase, although the contract itself is not a partnering contract.
The contract also includes rules on digital collaboration through project management tools and other digital communication. This largely reflects existing practice in the Norwegian market, especially in larger projects.
One particular innovation is the introduction of PRIME, or project-integrated mediation, under which disagreements are to be resolved on an ongoing basis with the assistance of experts. The aim is to prevent disputes from remaining unresolved, as unresolved disputes may affect the rest of the process and damage cooperation between the parties.
The contractor is also given a right to receive interim payment in the event of disagreement over price adjustments resulting from variations. This must be regarded as a clear shift from earlier standards, under which the employer, in the most extreme case, would only have to pay disputed claims once a final and binding judgment had been issued. The provision must be seen in light of the fact that large and long-term projects normally involve a significant number of disputed claims. If such claims remain unpaid for a long period, this may have serious consequences for the contractor’s liquidity, which in turn may put project delivery at risk.
The standard also contains provisions on the allocation of risk for ground conditions through the use of a reference ground baseline. Ground conditions must now be assessed specifically against a standardised reference ground baseline prepared by the employer and used by the contractor as the basis for its tender. The employer bears the risk for deviations that go beyond the variations that could reasonably be expected based on the reference ground baseline.
The regulation is therefore not fundamentally different from the other standards. The question will still be whether there is a deviation from what the contractor could understand based on the information provided by the employer before the tender deadline. However, the documentation that must now be prepared should hopefully make disputes better documented, more standardised and easier to resolve.
At the time of writing, no projects have announced that they will use NS 8408 as their standard contract. There are, however, indications that several major infrastructure projects are considering the model. Implementation is likely to be relatively slow, given the contract’s narrow scope and a relatively slow market.
At the same time, knowledge of the contract model will be essential when relevant projects are announced. This is particularly true for international players with ambitions to operate in Norway. Historically, such players have had a particular focus on large Norwegian road and civil engineering projects, making familiarity with NS 8408 important once it is put into use.
Updated Procurement Rules in 2026
The public procurement rules are highly important for the Norwegian construction and civil engineering market. Public contracts account for between 40% and 50% of the total market measured in value, and the market trend since 2022 has been that an increasingly large share is covered by the public sector. As a result, contractors that have previously dealt primarily with private employers may need to consider expanding their portfolio to include public projects in order to maintain revenue.
The Norwegian procurement rules are largely an implementation of EU Directive 2014/24, which is intended to ensure consistent practice in the internal European market. Since the rules entered into force in 2017, they have been amended several times. These amendments must be seen in light of the growing political focus on how public procurement can be used to promote broader societal objectives.
The politicisation of procurement has led to several deviations from the EU Directive. Of particular interest is the obligation, introduced in 2024, to include climate and environmental requirements as award criteria, as well as requirements relating to suppliers’ wages and working conditions from the same year. The general trend is that procurement rules are being used to promote ESG objectives by imposing requirements in tender processes and contracts that favour suppliers that prioritise these issues.
From a market perspective, this has favoured larger suppliers with the capacity to employ specialist personnel to handle the new requirements. The requirements are also important for international players wishing to operate in the Norwegian market, as any deviation from the common European rules creates a need for adaptation.
In 2026, the rules will again be updated. For smaller contracts, the threshold for application of the Procurement Act will be raised from NOK100,000 to NOK500,000. While most Norwegian construction and civil engineering contracts are significantly larger than this, the increase may be relevant for smaller operators working in water and wastewater, maintenance and operations. The purpose is to reduce the workload for contracting authorities so that they can focus on more complex procurements. At the same time, a number of ESG considerations will be incorporated into the Act, including climate and environment, wages and working conditions, human rights and universal design.
For the construction and civil engineering market, the rules on climate and environment, as well as integrity and responsible business conduct, are of particular interest. The market has already had some time to adjust to climate and environmental award criteria. This adjustment can be said to have been successful, although many public contracting authorities experience difficulties in designing award criteria that add value while also being realistic for a broad market to deliver on.
The new Act also introduces an obligation to include appropriate sanctions if a supplier breaches rules on societal considerations, including requirements relating to skilled workers and apprentices. Many market participants have already adapted to requirements for skilled workers and apprentices, but a stricter sanctions regime may have major consequences for parties that misunderstand the rules. Appropriate sanctions should primarily be understood as financial consequences, such as price reductions and liquidated damages. Several responsible business conduct models have previously relied only on requirements for rectification and termination.
This has meant that the employer has lacked a suitable and realistic intermediate sanction. The sanctions must be strong enough to have a real preventive effect, which may mean that a contractor’s margin disappears in cases of significant breach. Participants in the construction and civil engineering industry should also expect a stricter control regime to detect non-compliance.
Disputes concerning breaches of responsible business conduct requirements have so far received limited attention in the courts. This is likely to change as employers impose increasingly intrusive sanctions on their contractors.
The Red Rock Judgment and Possible Consequences for Revision of Construction Contracts
In HR-2025-251-A, the Norwegian Supreme Court held that an agreement for the purchase of shares had to be set aside in its entirety because it was contrary to section 36 of the Norwegian Contracts Act. The judgment does not concern construction contracts, but it may still have significance for them.
Section 36 of the Norwegian Contracts Act is an exception rule which provides that agreements that are unreasonable or contrary to good business practice may be set aside in whole or in part. In Norwegian law, the provision has functioned as a safety valve. The threshold for applying it is very high, particularly between professional parties. At the same time, it is not limited to any particular subject matter and may, in theory, be applied to any contractual relationship.
In HR-2025-251-A, six founders had jointly built up a company, Red Rock AS, over a number of years. In 2017, four of them sold their shares to the other two. After various later developments, a settlement agreement was entered into which significantly reduced the purchase price. At the same time, negotiations were ongoing with an external party, and the buyers had received a much higher valuation of the company. The buyers did not inform the sellers of this, and later sold the company to that external party at a much higher price.
The Supreme Court found that the background to the agreement was a common objective to sell the company in order to reward all the founders for their efforts. This strengthened the duty of loyalty between the buyers and the sellers. The Court also emphasised that the buyers had access to decisive information which they did not share with the sellers. On the contrary, the buyers indicated that the company was worth significantly less than the original estimate, which amounted to a failure to provide information.
Based on the above, and on the fact that the four sellers received significantly lower compensation for their efforts than the two buyers, the Supreme Court found that the agreement was unreasonable and set it aside in its entirety under Section 36 of the Contracts Act.
The judgment is a rare example of Section 36 of the Contracts Act being applied between professional parties. The duty of loyalty between the parties was particularly important, especially in light of their history and joint efforts. The judgment forms part of a line of recent Supreme Court cases clarifying the boundaries of the duty of loyalty between professional parties, together with, among others, HR-2026-280-A, which specifically concerned the duty to provide information between contracting parties. This legal development is well suited to clarifying different aspects of the duty of loyalty, which may contribute to better aligned expectations of conduct in contracts between professional parties.
HR-2025-251-A may be relevant to construction contracts, particularly where the parties have a long-term relationship. Norwegian standard contracts do not contain specific provisions on revision or invalidity due to unreasonableness, meaning that Section 36 of the Contracts Act also applies to them. However, the standards regulate the parties’ other obligations in considerable detail, and the threshold for applying Section 36 in construction matters must be regarded as very high.
At the same time, the standards impose a duty of loyalty between the parties. This will normally be considered breached in clear cases of failure to provide information, particularly if the parties have a special expectation of loyalty or if there is an imbalance in bargaining strength between them.
It is relatively rare for parties to invoke Section 36 of the Contracts Act in construction matters. The parties normally share an understanding that risk may have negative consequences for either side, and that even a party that suffers significant losses cannot demand contractual revision for that reason alone. Even where neither party is to blame for the risk, for example in classic force majeure events such as war and pandemics, the situation will normally be regulated by the contract’s own provisions.
At the same time, Section 36 of the Contracts Act undoubtedly covers a residual category of extremely unreasonable contractual outcomes and provisions. In a market where disruptions in global supply chains may have a major effect on existing contractual relationships, it will be interesting to see whether more parties consider invoking Section 36 to revise contracts that have had highly negative consequences for one party.
Closing Remarks
The Norwegian construction market is facing a challenging 2026. In addition to the points discussed above, this is likely to appear in several other ways. Particular points to highlight include increased focus on security and pressure on guarantees as a result of bankruptcy risk, increased use of contractual force majeure provisions due to geopolitical disruptions, sharper competition and more complaints in public procurement. It is also not unlikely that parties to construction contracts will show a greater willingness to pursue disputes as a result of a tighter market and narrower margins.
Filipstad brygge 1
P.O. Box 2043 Vika
N-0125 Oslo
+47 21 95 55 00
post.oslo@svw.no www.svw.no